Projects - DPP 1 status August 2007<br />
Conversion project on track<br />
Hull - Dubai Drydocks<br />
�Hull demolition work completed<br />
�Hull reinforcements ongoing<br />
�First dry-dock scheduled for October<br />
�Topside - Lamprell<br />
�M20 process module main deck completed, installation of process equipment starting<br />
�M80/90 power module fabrication of main deck ongoing<br />
�DRB fabrication in Dubai on schedule<br />
�Long lead items nearing completion<br />
�Gas Turbine No. 1 delivered to Dubai, No. 2 on schedule<br />
�Main process equipment delivered on schedule<br />
�Manufacturing of thrusters on schedule<br />
�DP control system completed on schedule