12.01.2013 Views

THE CROWN ESTATE Round 3 Offshore Wind Farm Connection ...

THE CROWN ESTATE Round 3 Offshore Wind Farm Connection ...

THE CROWN ESTATE Round 3 Offshore Wind Farm Connection ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>THE</strong> <strong>CROWN</strong> <strong>ESTATE</strong><br />

<strong>Round</strong> 3 <strong>Offshore</strong> <strong>Wind</strong> <strong>Farm</strong> <strong>Connection</strong> Study<br />

Prepared for<br />

Version 1.0<br />

Danielle Lane<br />

The Crown Estate<br />

16 New Burlington Place<br />

London<br />

W1S 2HX


Executive Summary<br />

This investigation presents an indicative set of optimum offshore and onshore electricity<br />

transmission network reinforcements required for the connection of up to 25GW of offshore wind<br />

generation as part of the <strong>Round</strong> 3 leasing process. It has been carried out by Senergy Econnect<br />

and National Grid for the Crown Estate to aid in the development of the potential <strong>Round</strong> 3<br />

development zones published earlier in the year. The final location of these zones is subject to the<br />

outcome of the Strategic Environmental Assessment currently being undertaken by the<br />

Department for Energy and Climate Change (DECC; formerly BERR) and further work with project<br />

developers.<br />

As the aim of this study was to identify the extent and costs of the works necessary to provide<br />

optimised transmission connections for all of the <strong>Round</strong> 3 offshore wind farms, an analysis was<br />

undertaken by Senergy Econnect as an annex to this report to ascertain at a high level the optimal<br />

ratio between the installed generating capacity offshore and the transmission capacity of the<br />

offshore transmission assets. This optimal utilisation ratio was determined to be 112%. In practice<br />

the offshore transmission asset designs provided in this report have a range of utilisation ratios<br />

from 81% to 112% because of the zonal capacities identified by The Crown Estate and the<br />

modular nature of the transmission assets themselves (with each additional cable providing a fixed<br />

increase in transmission capacity). National Grid are in the process of leading a review of the<br />

security standards for offshore generation connections to include projects of the size and distance<br />

form shore associated with <strong>Round</strong> 3, at the request of Ofgem. This review will culminate in a set of<br />

security recommendations including offshore transmission circuit capacity, which will be consulted<br />

upon and incorporated as revised text in the GB SQSS.<br />

In order to provide as accurate a cost model as possible a number of high voltage power<br />

equipment manufacturers and installers were consulted for the current costs of the equipment that<br />

would be required to realize the offshore connection designs described in this report.<br />

The offshore connection designs have been based around indicative zonal capacities provided by<br />

The Crown Estate. The location and installed capacities of the wind farms located within the zones<br />

as identified in this report have been determined by Senergy Econnect based on the principle of<br />

minimising the offshore transmission assets required for connection and identifying the associated<br />

costs. As such these designs may not provide the optimal solutions for the actual <strong>Round</strong> 3 wind<br />

farms, as the location, installed capacity, and offshore transmission technology and utilisation<br />

factor for the actual wind farms will be determined by the zonal developer and offshore<br />

transmission owner in collaboration with the selected technology provider. These solutions are<br />

designed to comply with the offshore GB SQSS proposals, except where expressly stated.<br />

The following Table summarises the optimal cost of connections resulting from this analysis.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 3 of 94


ZONE OWF<br />

Total<br />

Installed<br />

Capacity<br />

<strong>Connection</strong><br />

technologies<br />

Moray Firth C 500MW AC<br />

<strong>Connection</strong> Point<br />

(s)<br />

New substation on<br />

coast<br />

TOTAL<br />

COST<br />

TOTAL<br />

COST<br />

Per MW<br />

£193m* £386k<br />

Firth of Forth G 500MW AC Torness £150m* £300k<br />

Dogger Bank<br />

Hornsea<br />

Norfolk<br />

(without<br />

Sizewell C)<br />

H1 1237.5MW DC Creyke Beck<br />

H3 1237.5MW DC Creyke Beck<br />

J 1240MW DC Creyke Beck<br />

H2 1237.5MW DC Keadby<br />

H4 1237.5MW DC Keadby<br />

H5 1237.5MW DC Killingholme<br />

I1 1240MW DC Killingholme<br />

I2 1240MW DC Killingholme<br />

M 1237.5MW DC New substation on<br />

Lincolnshire coast<br />

N 1240MW DC New substation on<br />

Lincolnshire coast<br />

T 1240MW AC Sizewell<br />

Z2 1240MW DC Sizewell<br />

U 1237.5MW DC Norwich<br />

Z1 1237.5MW DC Norwich<br />

£5,910m £477k<br />

£1,728m £349k<br />

Hastings AA 500MW AC Bolney £184m £368k<br />

West Isle of<br />

Wight<br />

Bristol<br />

Channel<br />

Irish Sea<br />

DA 500MW AC Chickerell £175m £350k<br />

EA 1500MW AC New substation on<br />

Torridge Estuary<br />

IA 1237.5MW DC Deeside<br />

LA 1240MW DC Deeside<br />

JA 1237.5MW AC Wylfa<br />

NA 1240MW DC Stanah<br />

£430m £287k<br />

£1,632m £329k<br />

TOTALS 25,795MW £10,402m £403k<br />

Table 1: Optimal <strong>Connection</strong> Costs broken down by Zone<br />

*Total reinforcement costs dependent on GB transmission owner study currently in progress<br />

The total cost for connecting the round 3 wind farm projects, assuming no inclusion of Sizewell C,<br />

and the optimal design solutions identified in this report is £10,402 million. . Note that this Figure is<br />

based on 2008 price levels for the equipment required and does not allow for the additional<br />

equipment such as Static Var Compensation that may need to be installed at the onshore<br />

connection point of the HVAC connection solutions in order for the <strong>Offshore</strong> Transmission Owners<br />

to meet the reactive capability requirement of the System Operator/Transmission Owner code (e.g.<br />

an SVC sufficient to provide dynamic reactive capability for a 300MW wind farm would cost in the<br />

order of £12m).<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 4 of 94


Sensitivities were also investigated in some areas where new nuclear developments could occur in<br />

the same region and within the same timescales as the <strong>Round</strong> 3 development. If transmission<br />

reinforcement was not undertaken in an optimised manner on a strategic basis then offshore<br />

transmission asset costs could increase as a result of having to find alternative more distant<br />

connection points. An example of this is the Norfolk zone where the inclusion of Sizewell C<br />

increases the offshore transmission asset cost by £245m.<br />

As a function of these designs, the total installed generating capacity connected for round 3 is<br />

25,295MW (with a connection capacity of 22,980MW) with a £/MW cost ranging from £287k to<br />

£477k.<br />

In undertaking this work it became clear that, from a purely economic perspective, minimising the<br />

length of the offshore transmission network as much as possible is desirable. Typically the cost of<br />

the offshore network comprised roughly 90% of the total reinforcement cost. However, the need for<br />

significant onshore reinforcement, and the consenting risk that accompanies this reinforcement,<br />

was also identified. This was particularly the case for connection of the Dogger Bank, Hornsea and<br />

Norfolk development zones as well as areas with the potential for connection of new nuclear<br />

generation. Nevertheless, National Grid is confident that the network can be developed in an<br />

economic and efficient manner to facilitate renewable targets. In order to achieve this aim, work will<br />

need to occur in a timely manner, which implies that some of it may have to occur before specific<br />

individual projects materialise. The possible need for investment on an anticipatory ‘no regret’<br />

basis and the pressure to meet renewables targets places further emphasis on the importance of a<br />

coordinated approach to the design of an optimum offshore and onshore specific solution.<br />

Where onshore reinforcement options have been identified through this study, no environmental<br />

impact assessment of these reinforcements has been undertaken at this stage. Prior to<br />

undertaking any onshore reinforcement’s environmental impact assessments will be undertaken in<br />

accordance with best practice against a range of possible solutions.<br />

Some of the identified reinforcements will require planning consent and for this reason the<br />

Planning Bill, which received Royal Assent on 26 November, is seen as an essential process to<br />

enable significant energy infrastructure projects to be constructed, while enabling local<br />

communities and stakeholders to fully engage in the process . Identification of specific onshore<br />

reinforcements and the timing of these reinforcements are subject to the frameworks that currently<br />

govern the development of the transmission system such as the transmission access regime and<br />

the Great Britain Security and Quality of Supply Standards (GB SQSS). The onshore transmission<br />

owners are currently in the process of a fundamental review of these frameworks to ensure that<br />

they are fit for purpose for a GB electricity system that incorporates large volumes of variable<br />

generation from renewable sources.<br />

The power transfer capabilities of the HVAC and HVDC technologies available coupled with the<br />

potential installed capacity of the <strong>Round</strong> 3 OWF have to a large part dictated the offshore<br />

transmission designs presented in this report and determined that in the primary solution each<br />

OWF is connected directly to an onshore connection point, with no interconnection between the<br />

OWF in a particular zone.<br />

Applying an HVAC and HVDC solution to the same OWF has indicated that the choice of<br />

technologies used for the offshore transmission designs will be dictated by the transmission<br />

distance and that the cable route length at which HVDC Voltage Source Converter solutions<br />

become more economic than an equivalent HVAC solution is between 60km and 80km.<br />

Aggregated solutions, where multiple OWF are interconnected have been considered and costed,<br />

although these solutions do not compare favourably with the individual offshore transmission<br />

designs for the same OWFs in terms of cost per MW installed, except where solutions have been<br />

considered that utilise dual bipole HVDC overhead lines as opposed to underground cable to<br />

traverse the long distance overland routes from the coast to Norwich and Drax substations.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 5 of 94


The challenges posed in delivering the <strong>Round</strong> 3 offshore connections, regardless of design<br />

pursued, will be significant. Investment will be required by existing suppliers in expanding<br />

manufacturing facilities for HV cables, and in particular subsea cables. The HVDC VSC market is<br />

still at an embryonic stage, with the converter/bipole ratings used in this report yet to be deployed<br />

in the field. Hence there will be a technology risk as well as cost premium to be borne by the ‘first<br />

comer’ offshore transmission owner to specify this technology. Again it is likely that manufacturing<br />

facilities would need to be expanded to accommodate demand should <strong>Round</strong> 3 be developed in<br />

the timescales desired, with prices dropping as competition increases and with economies of scale.<br />

The HVDC converter manufacturers are confident that they can increase manufacturing capability<br />

to meet demand should they have sufficient assurance that projects will place orders. However<br />

Senergy Econnect have anecdotal evidence that one manufacturer is revising downwards their<br />

short to medium term forecasts for supplying the offshore market in the UK because of the delays<br />

in progressing offshore projects through the GB planning, consenting, and regulatory process, and<br />

the ability of the process to deliver the offshore wind farm capacity in the timescales desired.<br />

It should be noted that the offshore programmes of other countries and an increase in HVDC<br />

projects around the world will coincide with the <strong>Round</strong> 3 build programme, and hence <strong>Round</strong> 3<br />

developers or their <strong>Offshore</strong> Transmission Owners may potentially need to commit to production<br />

slots up to three or more years in advance to avoid the HVDC converters becoming a constraint.<br />

In order for the HVDC suppliers to have the confidence to increase their manufacturing capability,<br />

they will require an order book to be in place, which in turn means that the <strong>Offshore</strong> Transmission<br />

Owner regime needs to ensure that the procurement of equipment is triggered as early as possible<br />

in the process so that these lead times can be managed and reduced.<br />

Suppliers of the installation vessels necessary to install the cables and offshore platforms are<br />

bullish in their ability to quickly ramp up capacity to meet the demands of <strong>Round</strong> 3, although they<br />

acknowledge that to make the investment required in the timescales necessary they will need the<br />

security of retainer agreements or firm orders in place.<br />

The design and costing process has considered a “total solution” capable of handling the entire 25<br />

GW of <strong>Round</strong> 3 offshore wind. This assumes that the collective requirements for all the wind farms<br />

in a zone are required and that the overall onshore transmission system changes will all occur in a<br />

coordinated manner at any one location. Should piecemeal developments be undertaken, wind<br />

farm-by-wind farm, and/or wind generation capacity change incrementally over a period of years,<br />

the staggered timing of the works would result in multiple site/circuit extensions and this will<br />

increase the overall onshore costs and environmental impact. In order to avoid this extensive<br />

stakeholder engagement, coordination and collaboration is required.<br />

The report recommends that next steps should include a more detailed investigation of the<br />

environmental and planning constraints associated with the <strong>Round</strong> 3 zone connections and of the<br />

supply chain challenges likely to confront <strong>Round</strong> 3 projects. Further investigation into possible ‘no<br />

regret’ onshore reinforcements that have the potential to reduce the total connection cost would<br />

also be beneficial<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 6 of 94


Table of Contents<br />

Executive Summary .......................................................................................................................... 3<br />

1 Introduction.......................................................................................................................... 10<br />

2 Overall Design Methodology ............................................................................................... 12<br />

3 <strong>Offshore</strong> Design Methodology ............................................................................................. 14<br />

3.1 Establishing wind farm capacity & location.......................................................................... 14<br />

3.2 Establishing number and location of offshore platforms...................................................... 17<br />

3.3 <strong>Connection</strong> link technologies, capabilities and limitations ................................................... 18<br />

3.3.1 AC cables ................................................................................................................ 18<br />

3.3.2 HVDC....................................................................................................................... 20<br />

3.3.2.1 Current Source Converter HVDC technology .......................................................... 21<br />

3.3.2.2 Voltage Source Converter HVDC technology.......................................................... 21<br />

3.3.3 Gas Insulated Transmission Lines........................................................................... 24<br />

3.3.4 Superconductors...................................................................................................... 25<br />

3.4 Establishing offshore redundancy, security & quality of supply criteria ............................... 26<br />

3.5 Tailoring Installed Capacity to <strong>Connection</strong> Capacity ........................................................... 28<br />

3.6 Assessing landfall points, onshore cable routes & land availability..................................... 29<br />

3.7 Assessing offshore cable routes.......................................................................................... 29<br />

4 <strong>Offshore</strong> Cost Methodology................................................................................................. 31<br />

5 Onshore Design................................................................................................................... 37<br />

5.1 Assessing requirements for additional capacity on the onshore transmission system........ 37<br />

5.2 Scenario – Background assumptions on generation and demand ...................................... 38<br />

5.3 Onshore Transmission Requirements: Methodologies for Costing and Option Analysis .... 39<br />

5.4 Cost Basis ........................................................................................................................... 39<br />

5.5 Option Analysis.................................................................................................................... 41<br />

Zones with only one or two wind farms and relatively small overall capacities (1500 MW or less). 41<br />

Zones with several wind farms and larger capacities (approx. 3000 – 11000 MW) ........................ 41<br />

5.6 Scottish System Area .......................................................................................................... 41<br />

6 Overall Design Options and Potential Zonal Solutions........................................................ 41<br />

6.1 Moray Firth .......................................................................................................................... 42<br />

6.1.1 <strong>Offshore</strong> connection................................................................................................. 43<br />

6.1.2 <strong>Offshore</strong> connection alternatives ............................................................................. 43<br />

6.1.3 Onshore reinforcement ............................................................................................ 43<br />

6.2 Firth of Forth ........................................................................................................................ 44<br />

6.2.1 <strong>Offshore</strong> connection................................................................................................. 45<br />

6.2.2 <strong>Offshore</strong> connection alternatives ............................................................................. 45<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 7 of 94


6.2.3 Onshore reinforcement ............................................................................................ 45<br />

6.3 Dogger Bank & Hornsea...................................................................................................... 46<br />

6.3.1 <strong>Offshore</strong> connection................................................................................................. 52<br />

6.3.2 <strong>Offshore</strong> connection alternatives ............................................................................. 53<br />

6.3.3 Onshore reinforcement ............................................................................................ 56<br />

6.4 Norfolk ................................................................................................................................. 59<br />

6.4.1 <strong>Offshore</strong> connection................................................................................................. 62<br />

6.4.2 <strong>Offshore</strong> connection alternatives ............................................................................. 62<br />

6.4.3 Onshore reinforcement ............................................................................................ 63<br />

6.4.3.1 Zonal Infrastructure Works (without Sizewell C)...................................................... 64<br />

6.4.3.2 Zonal Infrastructure Works (with Sizewell C)........................................................... 66<br />

6.5 Hastings............................................................................................................................... 67<br />

6.5.1 <strong>Offshore</strong> connection................................................................................................. 67<br />

6.5.2 <strong>Offshore</strong> connection alternatives ............................................................................. 68<br />

6.5.3 Onshore reinforcement ............................................................................................ 68<br />

6.6 West Isle of Wight................................................................................................................ 70<br />

6.6.1 <strong>Offshore</strong> connection................................................................................................. 70<br />

6.6.2 <strong>Offshore</strong> connection alternatives ............................................................................. 71<br />

6.6.3 Onshore reinforcement ............................................................................................ 71<br />

6.7 Bristol Channel .................................................................................................................... 73<br />

6.7.1 <strong>Offshore</strong> connection................................................................................................. 74<br />

6.7.2 <strong>Offshore</strong> connection alternatives ............................................................................. 75<br />

6.7.3 Onshore reinforcement ............................................................................................ 75<br />

6.8 Irish Sea .............................................................................................................................. 77<br />

6.8.1 <strong>Offshore</strong> connection................................................................................................. 77<br />

6.8.2 <strong>Offshore</strong> connection alternatives ............................................................................. 79<br />

6.8.3 Onshore reinforcement ............................................................................................ 80<br />

7 Delivery Issues .................................................................................................................... 82<br />

7.1 <strong>Offshore</strong> Installation & Manufacturing resource .................................................................. 82<br />

7.1.1 HVAC and HVDC subsea cables............................................................................. 82<br />

7.1.2 HVDC converter equipment..................................................................................... 83<br />

7.1.3 Balance of plant equipment (e.g. transformers, switchgear, etc)............................. 83<br />

7.1.4 Assessment of the availability and cost of cable installation vessels ...................... 83<br />

7.2 Onshore transmission network delivery programme ........................................................... 84<br />

8 Conclusions ......................................................................................................................... 85<br />

8.1 Methodology and Assumptions ........................................................................................... 85<br />

8.2 Cost of Connecting <strong>Round</strong> 3 <strong>Offshore</strong> <strong>Wind</strong> <strong>Farm</strong>s ............................................................ 85<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 8 of 94


8.3 Individual Versus Aggregated <strong>Connection</strong>s......................................................................... 87<br />

8.4 Deliverability of <strong>Round</strong> 3 <strong>Connection</strong>s................................................................................. 87<br />

8.5 Benefits of a co-ordinated approach.................................................................................... 88<br />

9 Recommendations............................................................................................................... 90<br />

10 References .......................................................................................................................... 91<br />

11 List of Appendices ............................................................................................................... 92<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 9 of 94


1 Introduction<br />

Following the initial East Coast Transmission Network, Technical Feasibility Study [1] and<br />

subsequent meetings with key stakeholders such as the Scottish Government, National Grid,<br />

Ofgem, and the Department for Energy and Climate Change (DECC; formerly BERR), The Crown<br />

Estate now wish to understand the potential extent and cost of the works necessary to provide<br />

optimised transmission connections for the indicative <strong>Round</strong> 3 offshore wind farm project<br />

development zones 1 . This includes an assessment of the necessary onshore reinforcements to<br />

facilitate these connections, such that a coordinated, optimal design between onshore and offshore<br />

is achieved.<br />

A crucial starting point for this report was to establish the size and location of the offshore <strong>Round</strong> 3<br />

projects that could arise within the areas identified. Once this was established the challenge was to<br />

design a network topology with sufficient capacity to accumulate and transmit the power levels<br />

required. Selecting an appropriate capacity for each connection link is also important in<br />

establishing the financial case for such an offshore transmission scheme as the utilisation of these<br />

offshore assets (as part of demonstrating an economic and efficient test) will likely be a significant<br />

parameter in the competitive tender process to be overseen by Ofgem in awarding the <strong>Offshore</strong><br />

Transmission Owner licences.<br />

As well as understanding the size and location of the planned generation projects, the type of<br />

generation proposed is fundamental to designing a technically and economically efficient offshore<br />

transmission system. This study is based on current, prototype or proposed offshore wind turbine<br />

models that could achieve market realisation in the assumed timescales of the <strong>Round</strong> 3 projects.<br />

The maximum amount of power that could be lost in the event of a fault on the offshore network is<br />

of interest to the onshore system operator as they will need to put operational measures in place<br />

for this possibility. The possible extent of this power loss with regard to the <strong>Round</strong> 3 project<br />

timescales is discussed in Section 3.4.<br />

Of significant impact to the final network topology is the location of the connection points to the<br />

onshore networks within the geographical area of consideration and the reinforcements required to<br />

the onshore system in order to facilitate these connections. The final choice of connection point<br />

was determined iteratively by assessing the ability of the onshore networks to accept either a<br />

power infeed or outflow at certain nodes, the land available to extend either existing substations or<br />

create new substations, and the practicality and cost of either extending the 400kV overhead line<br />

network or providing an onshore cable route.<br />

This analysis was undertaken against generation background assumptions other than that of the<br />

currently contracted generation projects (i.e. those having a Bilateral <strong>Connection</strong> Agreement with<br />

the GB System Operator) that would normally be considered as part of a connection application<br />

process. The overall optimum solutions presented could therefore change depending on which<br />

generation projects actually come forward in future. Sensitivity studies have been undertaken on<br />

key variables, such as nuclear replanting, in order to mitigate as far as possible the effect of this<br />

future uncertainty.<br />

1 Subject to the outcome of the DECC Strategic Environmental Assessment<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 10 of 94


Once an asset optimised offshore and onshore design was achieved against the background<br />

assumptions made, each design was costed, based on updated pricing information received from<br />

Siemens, ABB, Areva, and Prysmian and the experience of National Grid in building onshore<br />

assets.<br />

There is currently a shortage of critical raw materials required for infrastructure development, such<br />

as copper, aluminium, and steel, as well as potentially significant restrictions in the capacity<br />

available to manufacture the elements of technology required to implement an offshore network<br />

scheme. It should be noted that an offshore scheme spanning the geographical areas outlined for<br />

<strong>Round</strong> 3 would also be beyond anything currently in operation. For this reason, a certain amount of<br />

design and development work will need to be undertaken, (for example refinement of the<br />

technology to support multi-terminal HVDC operation), before such a scheme could be<br />

manufactured, constructed, and operated. The tools necessary to install subsea cables and<br />

platforms, such as lifting barges and cable laying vessels, are also presently in short supply;<br />

therefore, this study ascertains how these restrictions will impact the lead time necessary to<br />

commission any proposed scheme.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 11 of 94


2 Overall Design Methodology<br />

A key feature of this work is an investigation into a coordinated offshore and onshore design for the<br />

connection of offshore wind generation, in an attempt to provide a more effective solution than<br />

simply connecting to the nearest point onshore. At a high level, the process is illustrated in Figure<br />

1.<br />

Network Design<br />

Engineering Design<br />

Standards and<br />

Assumptions<br />

Network and Turbine<br />

Technology<br />

<strong>Offshore</strong> Design<br />

Iterative<br />

Design<br />

Process<br />

<strong>Offshore</strong> and Onshore<br />

Costs<br />

Onshore Design<br />

Land, Planning,<br />

Consents and<br />

Network Installation<br />

Figure 1: Iterative <strong>Offshore</strong> and Onshore Design Methodology<br />

Overall<br />

Optimum<br />

Network<br />

Conclusions<br />

Projects arising out of the <strong>Round</strong> 1 and <strong>Round</strong> 2 offshore leasing process were predominantly<br />

small in size and close to the shoreline (almost exclusively within the 12 nautical mile limit of<br />

territorial waters) relative to the proposed <strong>Round</strong> 3 areas. For the majority of these <strong>Round</strong> 1 and<br />

<strong>Round</strong> 2 projects, cost benefit analysis clearly demonstrated that individual, AC, radial connections<br />

to the electricity system onshore were the most economic. In contrast, offshore areas earmarked<br />

for <strong>Round</strong> 3, such as the Dogger Bank, could be developed to levels of up to tens of gigawatts and<br />

are located more than 100km from the onshore system leaving greater scope for consolidation and<br />

optimisation in taking the energy to shore.<br />

The impact of where a project is connected to the onshore transmission system on connection<br />

timescales and overall cost has often been underestimated in the past, occasionally leading to<br />

unexpected revisions in assumptions on capital costs, additional consenting risk and the potential<br />

for sub-optimal overall design. This highlights the impact of the effect on the onshore transmission<br />

system as a result of a particular offshore design and the importance of the iterative nature by<br />

which the design process must take place in order to find the optimum combination between<br />

offshore and onshore assets. This is especially pertinent for projects of the size and geographically<br />

diverse locations characteristic of those expected to arise out of the <strong>Round</strong> 3 process.<br />

In considering the amount of transmission capacity required to facilitate the connection of the<br />

indicative <strong>Round</strong> 3 development zones it is important to note that this was assessed relative to the<br />

calculated potential capacity of these zones as well as the levels of electricity demand and the<br />

amount and spatial distribution of conventional generation (such as coal, gas and nuclear)<br />

assumed to share network capacity with onshore and offshore wind generation.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 12 of 94<br />

and<br />

Recommendations


The offshore network topology and technology is largely determined by the location of and<br />

distance to the optimum connection points onshore. The final choice of connection point has been<br />

determined by finding an economic balance between offshore and onshore reinforcement required,<br />

including the cost of both local (substation and circuits) and wider (Main Interconnected<br />

Transmission System (MITS)) reinforcement.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 13 of 94


3 <strong>Offshore</strong> Design Methodology<br />

The starting point for this report was to establish the nominal capacity and location of the forecast<br />

offshore <strong>Round</strong> 3 generation projects within the indicated, potential offshore zones for<br />

development. Once this was established a connection network topology was constructed with<br />

sufficient capacity to accumulate and transmit the power levels required. Selecting an optimum<br />

capacity for the links in this connection network is also important in establishing the financial case<br />

for such an offshore transmission scheme. Any offshore assets to be constructed under a<br />

regulated regime will be assessed by Ofgem as part of a competitive tender process for awarding<br />

<strong>Offshore</strong> Transmission Owner licences. Therefore demonstrating that these assets are designed to<br />

achieve optimum utilisation will be a key consideration. The following sections describe the<br />

methodology used to design and then cost the various <strong>Round</strong> 3 connection network topologies<br />

contained within this report.<br />

3.1 Establishing wind farm capacity & location<br />

Following the public announcement of the third round of offshore wind farm site leasing in 2007,<br />

The Crown Estate have published a map showing indicative <strong>Round</strong> 3 zones for development 2 (see<br />

Figure 2) however in order to arrive at a connection solution it was necessary to establish an<br />

indicative MW capacity that will be connected within each of the zones and also the locations of<br />

possible wind farm developments within each zone. To that end The Crown Estate allocated 25GW<br />

across the nine zones approximately in relation to the area of the zone. The allocation was carried<br />

out for the purposes of this study and is one of a number of possible scenarios for capacity<br />

allocation. It does not necessarily reflect The Crown Estate’s view on the likely outcome of the<br />

<strong>Round</strong> 3 tender. Additionally The Crown Estate provided a series of GIS shape files indicating<br />

areas within each zone that could potentially become sites for offshore wind farms, hereafter<br />

referred to as ‘Polygons’, as well as indicative connection capacities for each of the <strong>Round</strong> 3<br />

development zones, (see Table 2 below).<br />

Further it should be noted that this study does not take account of all environmental constraints.<br />

Therefore the location of the development zones and polygons will be dependent not only on the<br />

<strong>Round</strong> 3 tender but also on the outcome of the Strategic Environmental Assessment being<br />

undertaken by DECC and any environmental Impact Assessment of individual sites.<br />

2 Subject to the outcome of the DECC Strategic Environmental Assessment<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 14 of 94


Figure 2: <strong>Round</strong> 3 Zones for Development<br />

©Crown Copyright<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 15 of 94


<strong>Round</strong> 3 Development Zone<br />

Indicative <strong>Connection</strong> Capacity<br />

(MW)<br />

Moray Firth 500<br />

Firth of Forth 500<br />

Dogger Bank 9000<br />

Hornsea 3000<br />

Norfolk 5000<br />

Hastings 500<br />

West Isle of Wight 500<br />

Bristol Channel 1500<br />

Irish Sea 5000<br />

TOTAL 25,500<br />

Table 2: <strong>Round</strong> 3 Zonal Indicative <strong>Connection</strong> Capacities<br />

In order to assess each polygon’s potential for installed capacity, and hence each polygon’s<br />

contribution towards the zonal indicative connection capacity, it was necessary to establish a wind<br />

turbine array within each polygon’s boundaries. For the purposes of this report, these arrays were<br />

based on current, prototype, or proposed multi-MW wind turbine models that could achieve market<br />

realisation in the timescales of the <strong>Round</strong> 3 projects.<br />

Each polygon was allocated one of two wind turbine model types to maximise the power density<br />

achieved to meet the zonal indicative connection capacity required. The arrays were constructed<br />

based on standard wind farm turbine spacing principles of seven rotor diameters apart in the<br />

prevailing wind direction and four rotor diameters apart in the direction perpendicular to the<br />

prevailing wind [2]. The wind turbines used in this study and the corresponding array spacings are<br />

shown in Table 3. Note that the wind turbine types used here do not represent an exhaustive list of<br />

potential machines that could be used for the <strong>Round</strong> 3 offshore projects but as indicative wind<br />

turbine capacities for the purposes of this report.<br />

Turbine type Capacity Rotor Diameter<br />

REpower<br />

5M<br />

Clipper <strong>Wind</strong><br />

Britannia<br />

Prevailing wind<br />

array spacing<br />

Perpendicular<br />

array spacing<br />

5MW 126m 882m 504m<br />

7.5MW 150m 1050m 600m<br />

Table 3: <strong>Wind</strong> turbines utilised and corresponding array spacings<br />

Each wind farm’s array was orientated as far as possible to the prevailing wind direction in the UK,<br />

i.e. from the South West, and the potential power capacity established. Some of the polygons<br />

could accommodate far more wind turbines than required to meet the zonal indicative connection<br />

capacity, and hence the arrays in this case were limited by the connection capacity available<br />

and/or the contribution required to the zonal indicative connection capacity (see Figure 3). Some<br />

polygons were excluded from the connection designs in zones where the potential connection<br />

capacity of the polygons exceeded the zonal indicative connection capacity provided by The Crown<br />

Estate. The zonal and wind farm capacities arrived at are shown in Table7.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 16 of 94


Figure 3: Hastings Zone showing potential and utilised array area<br />

(KEY: Green Dot – <strong>Wind</strong> Turbine Blue Dot –offshore substation)<br />

3.2 Establishing number and location of offshore platforms<br />

The traditional voltage for interconnecting offshore wind turbines in the UK is 33kV however due to<br />

the power capacities accumulated in each <strong>Round</strong> 3 wind farm and the distance from shore it is not<br />

possible for the power to be transmitted to the connection points on shore at this voltage. Hence<br />

offshore substations will need to be established within each <strong>Round</strong> 3 wind farm to accumulate the<br />

power from the array and step up the voltage to a level appropriate for transmission over distance.<br />

The amount of power that can be accumulated at one offshore substation, and hence the number<br />

of offshore substations required for each wind farm will be dictated by the power carrying capacity<br />

of the onward transmission medium, the power carrying capacity of the array cabling, the number<br />

of wind turbines, and the distance from the platform to the furthest wind turbine in the array, (as<br />

using excessive lengths of 33kV cable to connect an array can lead to onerous power losses).<br />

For the purposes of this report it was deemed pragmatic to consider the use of 245kV three-core<br />

cross-linked poly-ethylene (XLPE) insulated subsea cable as the immediate transmission medium<br />

from each of the offshore platforms, irrespective of whether it would be AC or DC technology that<br />

would ultimately provide the transmission medium from the entire offshore wind farm or <strong>Round</strong> 3<br />

zone to the onshore connection point.<br />

To ascertain the power carrying capacity of the 245kV cable, ratings were derived from information<br />

provided by the cable manufacturers [3] and then derated as appropriate for cables situated within<br />

J tubes [4], which would be required to bring the subsea cables from the seabed onto the offshore<br />

platform itself. The resultant cable ratings used in this report are shown in Table 4.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 17 of 94


Cable<br />

Voltage<br />

Cable Type/Size Current rating Power rating<br />

Rating after<br />

12% J tube<br />

de-rating<br />

factor<br />

245kV Copper 1000mm 2 c.s.a 825A 350MVA 308MVA<br />

Table 4: Intra array cable ratings<br />

These cable ratings were then applied to each wind farm’s indicative installed capacity to establish<br />

how many platforms would be required for each wind farm and hence how many ‘arrays’ radiating<br />

out from those platforms each wind farm would contain. For the purposes of this report in order to<br />

minimize offshore transmission cable lengths (and hence losses and cost) the number of platforms<br />

was kept to a minimum and each platform was placed on the side of the wind farm orientated to<br />

the likely connection point, (although this would result in larger offshore platforms with a<br />

requirement for sixteen switch panels at 33kV and array cable lengths of up to 13km with minimal<br />

losses at full load). In practice the location and number of the offshore platforms will be dependent<br />

on the capital and operational costs for both the offshore transmission network and the wind farm<br />

cable array, with design parameters optimised for a particular wind farm.<br />

3.3 <strong>Connection</strong> link technologies, capabilities and limitations<br />

Section 3.1 described how the raw wind farm capacities were arrived at, however due to the large<br />

<strong>Round</strong> 3 wind farm capacities considered and the distance of some of the wind farms from<br />

potential connection points on the onshore network, the cost of the offshore transmission assets<br />

and therefore their capability will play a significant part in the economic viability of each project.<br />

For this reason a number of connection technologies and their capabilities and limitations were<br />

assessed for this report and each is described briefly below.<br />

3.3.1 AC cables<br />

The advantage of using AC cables as a connection medium is obvious when the requirement is to<br />

link an offshore farm or farms which are generating at AC with an onshore network that is<br />

supplying AC, however the capabilities and limitations of AC cables are also well known, especially<br />

when it comes to crossing long distances. A characteristic of AC cable circuits is the charging<br />

current induced in the cable due to the capacitance between each phase conductor and earth.<br />

The charging current can be mitigated by connecting reactive compensation at regular intervals<br />

along the cable, however as most of the <strong>Round</strong> 3 wind farms require long sections of subsea<br />

cable, providing this interstitial reactive compensation would present an added technological and<br />

financial challenge. However it may be possible to connect shunt reactive compensation to the<br />

cable at or close to the transition point from subsea to underground cable. Hence an assessment<br />

of the reduction in effective power carrying capability of the AC cable described in Section 3.2 due<br />

to charging current and resistive (I 2 R) losses and the effect of adding reactive compensation at<br />

three points along the cable route length was carried out using the PSS/Sincal power system<br />

analysis software. An explanation of the analysis methodology is given in Appendix 2 while the<br />

results of this analysis are shown in Table 5.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 18 of 94


Length<br />

(km)<br />

no<br />

rpc<br />

Reactive Power Compensation Optimised<br />

P received (MW) Q received (MVAr)<br />

Reactive compensation<br />

applied (MVAr)<br />

50/50<br />

split<br />

33/33/3<br />

3 split<br />

no rpc<br />

50/50<br />

split<br />

33/33/33<br />

split<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 19 of 94<br />

no<br />

rpc<br />

50/50<br />

split<br />

33/33/33<br />

split<br />

no rpc<br />

S total (MVA) I average (kA)<br />

50/50<br />

split<br />

33/33/<br />

33<br />

split<br />

no<br />

rpc<br />

50/50<br />

split<br />

33/33/33<br />

split<br />

0 330 330 330 -108 -108 -108 0 0 0 347 347 347 NA NA NA<br />

20 329 329 329 75 0.589 -1.429 0 37 26 338 329 329 0.709 0.717 0.713<br />

40 329 329 329 160 -0.558 1.387 0 79 52 365* 329 329 0.721 0.730 0.718<br />

60 328 328 328 247 0.784 0.446 0 120 80 411 328 328 0.747 0.745 0.726<br />

80 327 327 327 339 0.682 -0.149 0 162 108 471 327 327 0.785 0.765 0.736<br />

100 325 326 326 435 -0.808 -0.300 0 205 136 543 326 326 0.836 0.789 0.748<br />

120 323 325 326 537 0.876 0.128 0 247 164 627 325 326 0.900 0.814 0.763<br />

140 321 324 325 646 -0.830 1.315 0 291 192 721 324 325 0.978 0.843 0.780<br />

160 317 322 324 765 -1.249 -0.344 0 335 221 828 322 324 1.072 0.874 0.799<br />

180 311 321 323 896 0.071 -1.217 0 379 250 949 321 323 1.184 0.907 0.820<br />

200 303 319 322 1042 0.800 -0.993 0 424 279 1085 319 322 1.317 0.941 0.842<br />

Table 5: Power Transmission Capability of 1000mm 2 subsea cable against route length<br />

*Figures in red indicates where either the MVA or Current rating of the cable is exceeded<br />

Cable Data<br />

operating voltage<br />

offshore:<br />

275 kV<br />

X 0.18 ohms/km<br />

R 0.023 ohms/km<br />

C<br />

onshore:<br />

0.18 uF/km<br />

X 0.185 ohms/km<br />

R 0.023 ohms/km<br />

C 0.185 uF/km<br />

Thermal capacity 825 A<br />

Values from Electrical Cables handbook &<br />

from ABB XLPE Submarine cable system<br />

handbook


A further challenge posed by long AC cable circuits is the additional demands imposed on the<br />

circuit breakers providing protection and control functions due to the large capacitances created<br />

within the cable, and the attendant cable charging current drawn. Careful selection of circuit<br />

breakers and control equipment is necessary to ensure that integrity of operation can be ensured,<br />

particularly when the long offshore cables are being energised without the wind turbine<br />

transformers in circuit.<br />

For these reasons AC subsea cables have only been considered as a possible connection<br />

technology in this report where the total cable route length is less than 100km.<br />

3.3.2 HVDC<br />

In DC transmission, a charging current only occurs during the instant of switching on or off, (i.e. to<br />

charge and discharge the cable capacitance), and therefore has no effect on the continuous<br />

current rating (and hence power transfer capability) of the cable. In a HVDC system, electric power<br />

is taken from one point in a three-phase AC network, converted to DC in a converter station,<br />

transmitted to the receiving point by an overhead line or underground /subsea cable, and then<br />

converted back to AC in another converter station and injected into the receiving AC network<br />

(Figure 4).<br />

Figure 4 Overview of VSC HVDC bipolar transmission for offshore wind farms<br />

©ABB<br />

Traditionally HVDC transmission systems are used for transmission of bulk power over long<br />

distances because the technology becomes economically attractive compared with conventional<br />

AC lines as the relatively high fixed costs of the HVDC converter stations are outweighed by the<br />

reduced losses and reduced cable requirements.<br />

There are two technologies used in HVDC transmission: Current Source Converters (CSC) and<br />

Voltage Source Converters (VSC).<br />

CSCs are dependent on an external voltage source to drive the converter and feed its inherent<br />

reactive power demand. VSCs, on the other hand, function as independent voltage sources that<br />

can supply or absorb active and/or reactive power, therefore requiring no independent power<br />

source and making them ideal for offshore deployment.<br />

However, the power losses arising from the increased switching frequency of the devices used<br />

within the VSC technology and the power ratings of the technology currently available mean that,<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 20 of 94


at very high power transfer levels, CSC technology with some form of commutation support could<br />

become an option for offshore deployment.<br />

3.3.2.1 Current Source Converter HVDC technology<br />

CSC HVDC technology is older than VSC technology and is installed at many locations around the<br />

world. CSC technology requires a strong AC network to interface the HVDC link so is suited to<br />

connecting to strong points on existing AC networks.<br />

CSC systems are currently able to transfer the largest amounts of power for a given number of<br />

overhead lines or cables because the thyristor technology utilised is able to handle very high<br />

voltages and currents. ±500kV installations of CSC HVDC are in operation utilising overhead lines<br />

and ±800kV installations are planned which can transfer up to 6000MW. Utilising cables, the<br />

highest voltage available is ±500kV, due to the insulation technology of the cable.<br />

Although CSC HVDC systems are able to control very large amounts of real power flow they are<br />

unable to dynamically control the reactive power injected to or absorbed from the AC network, in<br />

contrast to a VSC HVDC converter station.<br />

Thus a CSC HVDC system requires reactive compensation to be connected to the AC side of the<br />

converter to compensate for the reactive power drawn by the converter and to provide the required<br />

reactive power to the grid.<br />

CSC HVDC converter stations require a strong AC network to interface with, because the thyristor<br />

technology utilised is “line commutated” (it can be switched on by a control signal but only ceases<br />

to conduct when the AC network changes polarity, which occurs 50 times a second in the UK). If<br />

connected to a weak network, commutation of the thyristors may not occur correctly and cause<br />

instability in the system. To use CSC HVDC technology to connect the <strong>Round</strong> 3 offshore wind<br />

farms may require additional compensation in the form of synchronous compensators to provide a<br />

strong voltage source to commutate the DC current.<br />

3.3.2.2 Voltage Source Converter HVDC technology<br />

VSC HVDC is the latest development in the field of HVDC technology, the main difference with<br />

CSC technology is that VSC converter stations are able to form their own AC voltage waveform<br />

and act as a true voltage source. This gives total flexibility regarding the location of the converters<br />

in the AC system since the requirements for the short circuit capacity of the connected AC network<br />

is low, enabling VSC HVDC systems to be connected to very weak AC systems. Therefore VSC<br />

HVDC can connect remote electrical islands such as offshore generation without the need for<br />

additional equipment.<br />

VSC HVDC technology has the capability to control both real and reactive power rapidly and<br />

independently of each other. The converter station can operate over a whole region of differing real<br />

and reactive power, unlike the CSC HVDC converter which can only provide discrete amounts of<br />

reactive power. This helps to keep the voltage and frequency of the associated AC system stable.<br />

The key technology that enables VSC HVDC converter stations to produce a voltage waveform is<br />

the high power Insulated Gate Bipolar Transistor (IGBT) which unlike the thyristors used in the<br />

CSC systems are self commutated, i.e. they can be switched on and off rapidly (up to 2000 times<br />

per second) to modulate a voltage waveform.<br />

At present the power handling capability of the largest available VSC HVDC converter module is<br />

1000MW at ±300kV, however capabilities of 1110MW may well be possible in the immediate future<br />

for single converter XLPE insulated bipole pairs operating at ±300kV, and 2000MW to 2200 MW<br />

for dual converter Mass Impregnated bipole pairs operating at ±500kV.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 21 of 94


Mass Impregnated cables have been the traditional medium for transmission in DC systems until<br />

now. As the name suggests the conductors are insulated with special paper impregnated with a<br />

high viscosity compound. They can be used for voltages up to 500kV.<br />

More recently, as the interest in Voltage Source Converter technology has grown, DC cables have<br />

also been developed that rely on extruded poly-ethylene as the insulation medium for the<br />

conductors. These cables are easier to manufacture and correspondingly cheaper than their MI<br />

equivalent, however currently can only operate at voltages up to 300kV which limits possible power<br />

flow.<br />

Figure 5(a) Mass Impregnated 500kV DC cable Figure 5(b) XLPE 150kV DC cable<br />

©Prysmian Cables ©Prysmian Cables<br />

Figure 6: HVDC VSC configuration<br />

©ABB<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 22 of 94


Figure 7: HVDC Dual Converter pair redundant bipole with metallic return path configuration<br />

©ABB<br />

The ability of the VSC HVDC converter station to rapidly control the active and reactive power<br />

provides many benefits to the associated AC grid in the form of added stability, flexibility and<br />

dynamic response, but a significant advantage of VSC HVDC over CSC HVDC is the possibility of<br />

flexible multi-terminal operation. Multi-terminal operation allows the HVDC system to interface with<br />

the AC system at any number of points by connecting more converter stations to the DC system.<br />

Although possible with CSC, control of the power flows in a multi terminal network is more onerous<br />

than with VSC due to the ability to minutely control the firing of the power electronic devices within<br />

the VSC converter.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 23 of 94


3.3.3 Gas Insulated Transmission Lines<br />

Traditional HVAC subsea cables and HVDC subsea bipole technologies are well understood and<br />

widely applied, albeit maybe not at the power capacities required for <strong>Round</strong> 3. However, due to the<br />

large connection capacity required and the distance offshore, other transmission technologies may<br />

become viable alternatives.<br />

One such technology is Gas Insulated transmission Lines or GIL. Gas insulated lines, as the name<br />

suggests encompass a high voltage AC conductor within a sealed aluminium pipeline which is<br />

filled with a SulphurHexafluoride (SF6)/Nitrogen mix as an insulating medium (see Figure 8).<br />

Figure 8: Cross section through a GIL showing conductor tube, enclosure and insulators<br />

© Siemens Power Transmission & Distribution<br />

The advantage of this technology is that it allows very high power transfers of up to 3000MW per<br />

three phase system [5], without the disadvantage of the charging current required by traditional AC<br />

cables, and can be installed underground, above ground or in tunnels (See Figure 9). Hence this<br />

technology is ideal for the bulk transfer of power over large distances where overhead lines are<br />

impractical, and has obvious advantages for connecting groups of large offshore wind farms.<br />

Figure 9: GIL directly buried and in tunnel arrangement<br />

© Siemens Power Transmission & Distribution<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 24 of 94


To date the longest length of GIL installed is the 4.5km at the Tehri Hydro Project in India [6],<br />

however the European Commission of Trans European Networks for Electricity is sponsoring a<br />

project looking at the use of GIL in the North Sea, focussing primarily on the installation techniques<br />

required, which are similar to those applied by the oil and gas industry to install the thousands of<br />

kilometres of subsea pipelines used in that field. The use of GIL to provide power corridors to<br />

group the output from a number of offshore wind farms is attracting particular interest in Germany<br />

because it reduces the impact on the environmentally sensitive areas of that country’s North Sea<br />

coast which has a parallel with the environmentally sensitive areas such as the Wash and the<br />

Humber estuary in the UK.<br />

The disadvantages of GIL for the purposes of <strong>Round</strong> 3, is that it is as yet an untried technology in<br />

the subsea environment, and over these distances, that the costs may be excessive compared to<br />

the more traditional technologies (see Section 6), and that the power capacity of the individual lines<br />

may be limited by the largest loss of power infeed that can be accommodated by the system<br />

operator, which is stipulated in the GB Security and Quality of Supply Standards (GB SQSS) (see<br />

Section 3.4).<br />

Some environmental concerns also exist over the increased use of the inorganic compound SF6,<br />

often used in the electricity industry for its dielectric properties, which has been shown to be a<br />

greenhouse gas with approximately 22,000 times the potency of carbon dioxide (CO2) if released<br />

into the atmosphere. This would also have to be taken into account when assessing the suitability<br />

of this technology for the connection of offshore wind generation, as existing onshore transmission<br />

owners have policies of minimising the use of this gas.<br />

However the GIL technology is based on seamless welding with practically zero losses (


Figure 10: Cross section of HTS ‘cold’ dielectric cable with copper core to carry fault currents<br />

© American Superconductor<br />

As with the GIL systems the advantage of using HTS is to minimise the offshore transmission<br />

system required for a given power transfer, however again as with GIL, the longest HTS system in<br />

operation at present (with the Long Island Power Authority in the US) is only half a mile long, the<br />

technology has never been used in an offshore environment, and due to the requirement for<br />

coolant pumping stations, the costs may be excessive offshore compared to the more traditional<br />

technologies. However HTS technology could be considered for some of the onshore connection<br />

routes as a viable alternative to multiple AC or even DC cables.<br />

3.4 Establishing offshore redundancy, security & quality of supply criteria<br />

One of the key criteria that any connection design must consider is the trade off between the initial<br />

capital investment, and the opportunity cost of lost energy due to losses within the system,<br />

unavailability due to scheduled maintenance, and unavailability due to faults (which can be of<br />

particular concern in the marine environment due to the difficulty in finding the faulted section and<br />

repairing it within a benign weather/tide window). This may result in some form of redundancy,<br />

either partial or full, being built into the design, which will add to the capital cost, but potentially<br />

reduce the operating costs.<br />

Redundancy will also be of interest to the respective onshore system operators, as they will need<br />

to cater for the loss of power infeed caused by sections of the offshore network tripping out under<br />

fault conditions.<br />

A great deal of work has gone into assessing the level of redundancy required for offshore<br />

transmission assets. In developing these deterministic standards to facilitate a regulatory regime<br />

for offshore transmission, the Centre for Sustainable Electricity and Distributed Generation (SEDG)<br />

were employed, on behalf of BERR (now DECC) to undertake cost benefit analysis that would<br />

underpin these standards. A report entitled “Cost benefit methodology for optimal design of<br />

offshore transmission systems” [8] has been published outlining the input assumptions, models<br />

used and results obtained from this work. The results arising out of this work informed the<br />

recommendations for an offshore security standard published by National Grid and used to<br />

develop draft text for new, offshore sections of the standard, which is currently under consultation.<br />

It is from the recommendations of this report that the designs within this study have been derived,<br />

although with some important deviations as explained in Table 5 below.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 26 of 94


OFFSHORE PLATFORM<br />

SEDG<br />

Results<br />

Platform export Capacity About 95% of installed<br />

capacity<br />

GB <strong>Offshore</strong> SQSS<br />

Recommendation [9]<br />

100% of installed<br />

capacity<br />

Criteria used for this<br />

report<br />

90%+ of installed<br />

capacity<br />

Transformer redundancy 50% 50% 50%<br />

HV / LV terminals<br />

connected<br />

Platform export capacity<br />

following outage of one<br />

AC circuit<br />

- Yes Yes<br />

- Minimum 50% Minimum 50%<br />

DC offshore platform No redundancy No redundancy No redundancy<br />

Maximum Power infeed<br />

loss following outage of<br />

single DC converter<br />

OFFSHORE CABLE NETWORK<br />

Network capacity 95% of installed capacity<br />

for geographically small<br />

wind farms<br />

90% of installed capacity<br />

for geographically large<br />

wind farms<br />

Maximum Power infeed<br />

loss for loss of single<br />

offshore transmission<br />

cable<br />

ONSHORE SUBSTATION<br />

1000MW 1000MW 1110MW*<br />

100% 90%+<br />

1320MW 1320MW 1800MW**<br />

Transformer redundancy 50% 50% 50%<br />

Table 6: Redundancy Criteria used for this report<br />

* The 1110MW DC converter power infeed loss is set by the maximum MVA rating of the HVDC voltage<br />

source converter stations as indicated by the manufacturers.<br />

**An 1800MW infrequent infeed loss limit (as opposed to the current 1320MW) is representative of the level<br />

of response and reserve that may be required to be held by the GB system operator in order to<br />

accommodate the next generation of nuclear power stations. This requirement for an increased level of<br />

response and reserve is currently under review. Although National Grid sees no technical barrier to its<br />

implementation, the economic implications are being thoroughly investigated and consulted upon before a<br />

final decision is made.<br />

It is also important to note that in the joint Ofgem/BERR Regulatory Policy Update dated 13 th June,<br />

2008 [16], the need to “Analyse and define the basis for an offshore security standard that can<br />

cater for generation projects of the size and location of <strong>Round</strong> 3 projects” was highlighted due to<br />

the limited scope of previous work. This further analysis, which forms part of the wider<br />

Fundamental Review of the GBSQSS currently underway [15], will seek to update previous work to<br />

ensure that it is fit for purpose and applicable to all projects that could reasonably be foreseen to<br />

arise in the future. This work, being undertaken by the three onshore transmission owners and<br />

supported by the SEDG Centre, has the potential to impact the design of the offshore transmission<br />

system (i.e. assets operated at 132kV and above) used in this analysis.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 27 of 94


3.5 Tailoring Installed Capacity to <strong>Connection</strong> Capacity<br />

The methodology described in Section 3.1 was used to establish the power capacity of each of the<br />

wind farms, adjusted to meet the zonal indicative connection capacities. However due to the<br />

capacities accumulated in each <strong>Round</strong> 3 wind farm and the distance from shore, the cost of the<br />

offshore transmission assets themselves will form a significant element within the overall capital<br />

cost of the wind farm, such that there will be a significant incentive to fully utilize the capacity of the<br />

offshore transmission assets as far as possible. Due to the variable nature of the wind resource,<br />

unavailability of individual wind turbines due to maintenance, and power losses in the array<br />

cabling, a connection design that was capable of transmitting the output from the entire installed<br />

capacity of the wind farm would only be fully utilized for a small percentage of the wind farms<br />

lifetime, hence an attempt was made at a high level within the auspices of this study to ascertain<br />

what the optimal installed generation capacity would be for a given connection capacity.<br />

The results of this analysis are given in Appendix 1, however in summary for an offshore wind farm<br />

in the North Sea with an average wind speed on the Dogger Bank of 8.8m/s [10] and an availability<br />

of 90% (Note. The <strong>Round</strong> 1 offshore wind farm at North Hoyle had an average availability of 87.4%<br />

in its third full year of operation (2006-07) [11]), the optimised installed capacity derived was 112%<br />

of connection capacity. This compares well with the results of the similar analysis carried out by<br />

SEDG which arrived at an indicative range of 105% to 111% depending on the geographical area,<br />

(and hence wind diversification), of the wind farm in question [8].<br />

This Figure of 112% installed capacity coupled with the technology ratings stated in Sections 3.2<br />

and 3.3, the zonal indicative connection capacities from The Crown Estate, and the raw wind farm<br />

capacities derived in Section 3.1 were used to establish the wind farm capacities listed in Table7<br />

on which the subsequent offshore and onshore designs were based.<br />

<strong>Round</strong> 3 Development Zone<br />

<strong>Round</strong> 3 <strong>Wind</strong> farm<br />

(defined by letter)<br />

Indicative (Installed) Zonal<br />

<strong>Connection</strong> Capacity<br />

Polygon Installed capacity<br />

(MW)<br />

Moray Firth 500 (500)<br />

Number of <strong>Wind</strong> Turbines<br />

C 500 100 x 5MW<br />

Firth of Forth 500 (500)<br />

G 500 100 x 5MW<br />

Dogger Bank 9000 (9907.5)<br />

H1 1237.5 165 x 7.5MW<br />

H2 1237.5 165 x 7.5MW<br />

H3 1237.5 165 x 7.5MW<br />

H4 1237.5 165 x 7.5MW<br />

H5 1237.5 165 x 7.5MW<br />

I1 1240 248 x 5MW<br />

I2 1240 248 x 5MW<br />

J 1240 248 x 5MW<br />

Hornsea 3000 (2477.5)<br />

M 1237.5 165 x 7.5MW<br />

N 1240 248 x 5MW<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 28 of 94


<strong>Round</strong> 3 Development Zone<br />

<strong>Round</strong> 3 <strong>Wind</strong> farm<br />

(defined by letter)<br />

Indicative (Installed) Zonal<br />

<strong>Connection</strong> Capacity<br />

Polygon Installed capacity<br />

(MW)<br />

Norfolk 5000 (4955)<br />

Number of <strong>Wind</strong> Turbines<br />

T 1240 248 x 5MW<br />

U 1237.5 165 x 7.5MW<br />

Z1 1237.5 165 x 7.5MW<br />

Z2 1240 248 x 5MW<br />

Hastings 500 (500)<br />

AA 500 100 x 5MW<br />

West Isle of Wight 500 (500)<br />

DA 500 100 x 5MW<br />

Bristol Channel 1500 (1500)<br />

EA (ac) 1500 200 x 5MW<br />

EA (dc) 1237.5 165 x 7.5MW<br />

Irish Sea 5,000 (4,955)<br />

IA 1237.5 165 x 7.5MW<br />

JA 1237.5 165 x 7.5MW<br />

LA 1240 248 x 5MW<br />

NA 1240 248 x 5MW<br />

TOTAL 25,500 (25,795)<br />

Table 7 <strong>Round</strong> 3 Polygon Installed Capacities<br />

3.6 Assessing landfall points, onshore cable routes & land availability<br />

As part of finalising the onshore network points of connection, desktop assessments using<br />

Ordnance Survey maps and satellite photography were made to ensure that there was sufficient<br />

land area around the onshore connection points to potentially accommodate the new substations<br />

or substation extensions and equipment, such as HVDC converter stations, necessary to facilitate<br />

the offshore network. This method was also used to identify potential landfall locations for the<br />

transition from the offshore subsea cable to the onshore underground cable, and then establish a<br />

possible onshore cable route from these landfall points to the onshore network connection points.<br />

Due to the differential in price between subsea and underground high voltage AC cables (in the<br />

order of 10%-20%), the onshore cable route length was minimized as far as possible, however<br />

where required, the cable routes were chosen to follow existing roads or disused railway beds in<br />

order to limit the elevation changes over the cable route, and also, as far as possible, avoid any<br />

obstacles such as river crossings that may require directional drilling.<br />

3.7 Assessing offshore cable routes<br />

<strong>Offshore</strong>, the most direct cable routes were established from the offshore substation locations to<br />

the proposed landfall points. These direct routes were then amended to avoid as far as possible<br />

any subsea obstacles, such as mineral extraction areas or other wind farms, or excessive changes<br />

in the depth of the seabed. Where the crossing of subsea obstacles such as gas and oil pipelines<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 29 of 94


was unavoidable, the cost of these crossings (using concrete mattresses and rock dumping etc)<br />

has been included in the overall costings. In order to minimize the cable route lengths onshore,<br />

wherever possible the subsea cable has been extended up through river estuaries before coming<br />

ashore. Due to the additional installation and cable protection requirements that may be required<br />

as a result, particularly in areas where there is heavy river traffic and existing pipeline and cable<br />

crossings such as the Humber, the potential cost saving in using subsea cables may be eliminated<br />

although again this will need to be assessed on a detailed case by case basis, which is outside the<br />

scope of this report.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 30 of 94


4 <strong>Offshore</strong> Cost Methodology<br />

In order to provide as accurate a cost model as possible a number of high voltage power<br />

equipment manufacturers and installers were consulted for the current costs of the equipment that<br />

would be required to realize the offshore connection designs described in this report.<br />

To that end information was very helpfully supplied by Siemens, ABB, Areva, Prysmian Cables,<br />

American Superconductor, ETA ltd, Senergy, and National Grid to facilitate this report.<br />

Due to the impact on cost of the actual installation conditions specific to the site, and the<br />

fluctuations in price of raw materials, and limitations of manufacturing resource, the costs of<br />

equipment quoted by the manufacturers can only ever be generic at this high level stage, and<br />

hence the cost estimates provided within this report are only indicative.<br />

The equipment costs provided by the manufacturers were combined with equipment cost<br />

information in the public domain such as that from the SEDG report [8] and an average price taken<br />

for each equipment element required for the offshore connection designs. It was these average<br />

equipment prices that were then used to cost the connection designs proposed.<br />

The offshore connection designs were costed from the HV transformers on the offshore wind farm<br />

platforms to the busbar clamps at the onshore substation. These points are also referred to as the<br />

Grid Entry Point and Onshore Interface Point, respectively, and together would form the extent of<br />

the offshore transmission system under the proposed offshore regulatory regime. Note that in<br />

some of the connection solutions proposed in this report, the offshore transmission system extends<br />

to more distant connection points onshore than those closest to the wind farm. This is because the<br />

designs proposed balance the need for offshore and onshore reinforcement in order to achieve the<br />

optimal solution. The connection design cost inclusions and exclusions are listed in Table8 below.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 31 of 94


<strong>Offshore</strong> <strong>Connection</strong> Design<br />

Cost Inclusions<br />

• 400kV double busbar AIS or GIS<br />

transformer /feeder bays<br />

• HVDC converter station onshore<br />

• Onshore reactive compensation<br />

• <strong>Wind</strong> farm substation compound land<br />

cost<br />

• Onshore 3 x single core AC cable<br />

supply & installation<br />

• Onshore DC bipole supply &<br />

installation<br />

• Transition pit civil works & cable<br />

winching<br />

• <strong>Offshore</strong> three core subsea AC cable<br />

supply & installation (Transmission to<br />

shore & inter-platform)<br />

• <strong>Offshore</strong> DC bipole supply & installation<br />

• <strong>Offshore</strong> platform provision and<br />

installation<br />

• <strong>Offshore</strong> DC converter<br />

• <strong>Offshore</strong> platform GIS transformer bays<br />

• <strong>Offshore</strong> reactive compensation<br />

• Earthing transformers<br />

• Subsea Oil/Gas pipeline crossings<br />

• 5% contingency<br />

Cost Exclusions<br />

• 33kV offshore switchboards<br />

• <strong>Wind</strong> farm 33kV array cabling<br />

• <strong>Offshore</strong> reactive compensation for array<br />

cabling<br />

• <strong>Wind</strong> Turbines and installation<br />

Table 8 <strong>Offshore</strong> connection design cost inclusions<br />

Each connection design was based on a generic 245/33kV offshore platform design, HVDC<br />

converter arrangement, and onshore 400kV transformer feeder bay arrangement which are detailed<br />

in Senergy Econnect drawing numbers 1845 009, 010, and 011 below. Drawing 009 represents the<br />

HVAC design used for the 500MW wind farms, drawing 011 the HVAC design for the 1200MW wind<br />

farms and drawing 010 the HVDC design for the 1200MW wind farms. Note that the equipment<br />

ratings shown in these drawings will change depending on the specific connection design.<br />

The cost of land required for converter stations and wind farm substation compounds will vary<br />

substantially depending on the location. However, for the purposes of this report an average land<br />

cost of £75k per hectare for brown field sites and £150k per hectare for green field sites was used in<br />

line with National Grid estimates.<br />

The cable costs include material, transportation from the factory, laying and burial with trenching of<br />

the subsea cable with water jetting down to a maximum of 1m and normal excavation for the land<br />

cable down to a maximum of 1m.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 32 of 94


The amount of reactive compensation included at both the offshore platform and onshore connection<br />

point have been derived from the results in Table4. The reactive compensation applied is solely to<br />

compensate for the capacitive charging current of the transmission cable and to maintain a unity<br />

power factor at the receiving end, and does not allow for any compensation of the wind farm array<br />

cabling. Note that the revised drafting of the System Operator/Transmission Owner Code (STC) to<br />

facilitate the proposed offshore regulatory regime includes an obligation on the owner of the offshore<br />

transmission assets to provide a reactive capability of 0.95 lead to 0.95 lag at the interface point with<br />

the onshore transmission network. The additional static and dynamic reactive compensation<br />

equipment required to meet this obligation has not been costed as part of this report as each wind<br />

farm could require a bespoke solution, however this could have a significant cost and land<br />

requirement implication for those zones connecting using AC technology.<br />

Initially each wind farm connection design was costed according to the appropriate technology used,<br />

however where a connection design could feasibly use either AC or DC technologies, both<br />

connection designs have been costed for comparison. In the same way where there is more than<br />

one technology that could be used to connect multiple wind farms within a zone to an onshore<br />

connection point, both options have been costed where possible to provide a comparison.<br />

As regards the switchbay technology used for the cost estimates onshore, Gas Insulated Switchgear<br />

(GIS) was used where the connecting substation was 5km or less from the coast, and Air Insulated<br />

Switchgear (AIS) used for all other cases. <strong>Offshore</strong> all the switchgear used was GIS.<br />

A summary of the costs for each wind farm connection design is provided in Sections 6&7 of this<br />

report with the detailed cost breakdowns forming the bulk of the appendices to this report.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 33 of 94


1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 34 of 94


1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 35 of 94


1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 36 of 94


5 Onshore Design<br />

The onshore electricity transmission system, as it exists today, has been built up over a period of<br />

time around the prevailing generation and demand background. It takes the electricity produced by<br />

generators across Great Britain and transmits it over large distances to points where the lower<br />

voltage, distribution networks take it further to the actual demand consumers. The transmission<br />

system is designed to ensure that electricity demand can be supplied at times of peak load and to<br />

facilitate competition in the electricity market in an economic and efficient manner.<br />

5.1 Assessing requirements for additional capacity on the onshore<br />

transmission system<br />

In assessing the need for additional capacity on the transmission system, transmission owners<br />

(including National Grid Electricity Transmission in England and Wales) are required by their<br />

transmission licences to design the system to accommodate peak demand levels according to the<br />

minimum, deterministic criteria outlined in the GB System Security and Quality of Supply Standards<br />

(GB SQSS) [12] complemented with a limited amount of additional cost benefit analysis for year<br />

round conditions. The total nominal output capacity of generating plant connected to the system at<br />

any given time exceeds the forecast peak demand, since a margin is required to cover for inevitable<br />

plant breakdowns and forecasting errors: in planning timescales there is always some uncertainty<br />

over the distribution of demand and the generators that will actually run to supply it. The GB SQSS<br />

sets out criteria for designing the system infrastructure (The Main Interconnected Transmission<br />

System, or “MITS”) in order to address these uncertainties.<br />

Currently, the generation fleet in Great Britain is largely comprised of conventional coal, gas and<br />

nuclear units with a peak-demand availability of > 80%, thus limiting the possible range of input<br />

assumptions to the analysis. Unless restricted by breakdowns, conventional generators normally run<br />

at, or close to, their maximum output since this is their most efficient mode of operation. Renewable<br />

generation generally exploits variable energy sources such as wind or solar energy. <strong>Wind</strong> turbines<br />

will seldom operate at full output individually, and even more rarely collectively. An economic and<br />

efficient onshore transmission system that incorporates substantial renewable generation will have to<br />

be designed to handle the variability of wind power together with its interactions with conventional<br />

plant availability and demand uncertainties.<br />

Over a year, the average output of offshore wind generators can be expected to be of the order of 30<br />

– 40% of their rated output, but wide variations will occur during the year. The network must be<br />

designed so that power can be exported from areas with wind generation when wind output is high,<br />

whilst allowing sufficient power to be imported to areas with wind generators when their output is low.<br />

To a large degree, the output from wind generation will share transmission capacity with<br />

conventional generation. This is particularly the case where the location and distribution of wind<br />

generation is similar to that of conventional plant in a given area and where the spread in marginal<br />

cost between wind and conventional generation is relatively large (i.e. areas where coal and gas<br />

generation are located with wind). The sharing of existing capacity will not occur to the same degree<br />

in areas of the system where this spread in marginal cost is much less (i.e. areas where nuclear<br />

generation is located with wind).<br />

The criteria in the current GB SQSS for design of the MITS are suitable for a system comprised of<br />

conventional generation with only a small amount of renewables and so need to be developed<br />

further to encompass large volumes of renewable generation. This has been the subject of much<br />

recent work in the UK which continues under the auspices of the Fundamental Review of the GB<br />

SQSS which is currently being directed by the GB-SQSS Review Group [13]. Modified standards<br />

arising from that Review will not come into force before 2010, so the analysis for this report has been<br />

done using the same interim methodology used for the 2008 Seven Year Statement, and outlined in<br />

Chapter 7 of that document [14].<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 37 of 94


In addition to criteria for design of the MITS, the GB SQSS also specifies requirements for the local<br />

connections to power stations. These must be designed to carry 100% of the output of a power<br />

station minus any local demand. These criteria have been applied in this project to determine the<br />

local transmission capacity needed at each point of connection to the GB Transmission System.<br />

5.2 Scenario – Background assumptions on generation and demand<br />

It is clear from Section 5.1, above, that the generation and demand pattern assumed in assessing<br />

additional capacity requirements for the onshore transmission system can have a large impact on the<br />

outcome of the assessment. In addition, the further one moves towards the future, the more<br />

uncertain the likely generation and demand pattern becomes. Therefore it is general practice to<br />

choose a scenario that represents one possible future outcome for analysis, as well as to investigate<br />

sensitivities around this scenario to identify the effects of different possible future outcomes.<br />

The proportion of generation by fuel type within the scenario utilised for this study is illustrated in<br />

Figure 11, below.<br />

Figure 11: Proportion of Generation by Fuel Type in Base Scenario<br />

From Figure 11, it is clear that the scenario used for this study is characterised by a large proportion<br />

of generation from renewable sources (approx. 40%) and that the bulk of this is provided by offshore<br />

wind. Also of note is that the proportion of electricity generated from coal is assumed to reduce<br />

significantly with new ‘Clean Coal’ technologies replacing all existing coal generators on the system<br />

to form only a small portion of the total. Gas fired generation will likely play a large role in a world<br />

with large volumes of renewables due to its flexibility and efficiency. Many of the existing nuclear<br />

stations have come off of the system and the scenario has assumed that only two new units will be<br />

constructed within the timescales considered. Some of the main sensitivities discussed in this report<br />

will be around the possibility of further nuclear connections, where this could affect the solution for<br />

the connection of <strong>Round</strong> 3 offshore wind.<br />

In this scenario, all onshore, transmission connected wind was assumed to connect in Scotland.<br />

Currently there is insufficient transmission system capacity to facilitate this level of generation in<br />

Scotland. The Electricity Networks Strategy Group (ENSG) has instigated a collaborative study<br />

between the three onshore transmission owners that will seek to ascertain the reinforcements<br />

required to facilitate the 2020 targets. Two potential reinforcement options being investigated are<br />

incremental upgrades to the onshore transmission system and offshore HVDC links which will bypass<br />

large, congested portions of the onshore network. This scenario has assumed that two HVDC<br />

links will be established; one on the West coast from Hunterston to Deeside and one on the East<br />

coast from Peterhead to Hawthorne Pit. The collaborative study is still ongoing, so this work has not<br />

yet concluded. However, in order to facilitate this investigation for potential <strong>Round</strong> 3 wind projects,<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 38 of 94


this was deemed a reasonable assumption. The scenarios used for this study and that of the<br />

collaborative study are broadly consistent, given the range of sensitivities considered.<br />

Projected peak demand levels also play an important role in the scenario assumptions. In the base<br />

scenario demand is expected to decrease by approximately 8% to 56.3GW, reflecting the potential<br />

impact of energy saving measures and increasing contribution of small, embedded generation<br />

projects.<br />

5.3 Onshore Transmission Requirements: Methodologies for Costing and<br />

Option Analysis<br />

As outlined above, the final choice of onshore connection points for the indicative <strong>Round</strong> 3 offshore<br />

development zones was determined by finding an economic balance between the offshore and<br />

onshore reinforcement required, including the cost of both local (substation and circuits) and wider<br />

(Main Interconnected Transmission System (MITS)) onshore reinforcements against the scenario.<br />

The onshore transmission system refers to the entire network beyond the onshore interface point<br />

forming the boundary between the onshore and offshore transmission systems.<br />

5.4 Cost Basis<br />

Costs for various components of the overall design have been based on:<br />

• <strong>Offshore</strong> and onshore AC & DC cables – Data provided by manufacturers through Senergy-<br />

Econnect, as outlined in Section 5. For onshore AC cables these have included comparisons<br />

with National Grid’s cost estimating system<br />

• Onshore substation work – Budgeted from either site specific estimates for revisions to<br />

existing installations, using National Grid’s cost estimating database, or using ‘generic’<br />

estimates around a range of basic transmission network elements – e.g. for new substations<br />

a series of standard arrangements have been assumed and cost estimates created for these.<br />

As such, costs may vary when local requirements at individual locations are taken into<br />

account<br />

• At each of the National Grid substations an evaluation of land requirements and availability<br />

was undertaken to determine if additional land and planning consents would be necessary.<br />

Where appropriate, estimates for undertaking this work have been included<br />

• New overhead lines – Where these are proposed, a generic cost estimate has been used,<br />

based on ‘standard’ circumstances- i.e. foundations, access, and routing (i.e. assuming<br />

reasonable sections of overhead line are in straight lines and do not require significant<br />

quantities of angle towers for changes of direction)<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 39 of 94


Onshore Transmission System Design Cost Inclusions<br />

• Busbar extensions for new connection bays<br />

• Busbar protection, for new connection bays<br />

• Substation extensions, including fencing, surfacing, drainage<br />

and internal access roads<br />

• Land purchase<br />

• Surveys and environmental impact assessments<br />

• An allowance for site screening<br />

• Obtaining planning permission, or overhead line consent for the<br />

National Grid works<br />

• Substation reconfiguration costs<br />

• Additional circuit bays for infrastructure modifications<br />

• Overhead line diversions into new substations<br />

• Where combined with a DNO connection all costs associated<br />

with providing this, including SGT’s and LV connections.<br />

• All civil works for National Grid assets<br />

• Protection and Control changes, including remote ends of<br />

modified circuits<br />

• Overhead line construction or re-stringing<br />

• For new sites/routes an allowance for siting and routeing studies<br />

and consultation<br />

• Works award process costs<br />

Table 9 Basis of Onshore Transmission Costs<br />

NB: All costs are based on 2008 price levels<br />

Cost<br />

Exclusions<br />

• System access<br />

constraints<br />

• Circuit outage – system<br />

uplift costs<br />

• Consent /planning<br />

permission mitigation<br />

• Third Party Costs<br />

Where new overhead line (OHL) routes are proposed route lengths have been estimated assuming<br />

that routes will avoid environmentally and visually important areas. In estimating the cost of these<br />

circuits no allowance has been made for the potential need to install sections as underground cable,<br />

apart from some line entries to substations or water crossings where it is apparent that this will be<br />

required. The overall cost of any new OHL routes could increase if sections of underground cable<br />

are required.<br />

The major new 400kV infrastructure overhead line routes considered have all been estimated on a<br />

‘stand-alone’ cost. The possibility remains, that for certain sections mitigation measures may be<br />

identified where adopting, and rebuilding an existing 132kV route owned by a Distribution Network<br />

Operator (DNO), may be appropriate. No allowance has been made for this, or for the creation of any<br />

additional DNO supply points that may arise as a consequence.<br />

The design and costing process has considered a “total solution” capable of handling the entire 25<br />

GW of <strong>Round</strong> 3 offshore wind. This assumes that the collective requirements for all the wind farms in<br />

a zone are required and that the overall onshore transmission system changes will all occur in a<br />

coordinated manner at any one location. Should piecemeal developments be undertaken, wind farmby-wind<br />

farm, and/or wind generation capacity change incrementally over a period of years, the<br />

staggered timing of the works would result in multiple site/circuit extensions and this will increase the<br />

overall onshore costs and environmental impact. In order to avoid this extensive stakeholder<br />

engagement, coordination and collaboration is required.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 40 of 94


5.5 Option Analysis<br />

In order to identify and cost the onshore connections and transmission reinforcements, three<br />

approaches to system design were considered:<br />

• Extending the offshore cables inland to existing onshore transmission sites;<br />

• Extending the GB Transmission System to new connection substations at the coast;<br />

• Hybrids of the above approaches<br />

An examination of the <strong>Round</strong> 3 zones show that they fall into two broad categories:<br />

Zones with only one or two wind farms and relatively small overall capacities (1500 MW or<br />

less)<br />

For these zones, typified by Hastings or West Isle of Wight, major reinforcements to the onshore<br />

transmission system were not required against the scenario, apart from extensions to existing<br />

substations or the establishment of new substations at the onshore interface point. The design<br />

process optimised the costs of cabling from a landing point to an existing substation, to a new<br />

substation on an existing transmission route, or to a new substation close to the coast, with the main<br />

interconnected transmission system extended to it. The savings in cable costs due to connecting to a<br />

new, rather than an existing substation outweighed the cost of the new substation in some instances.<br />

Zones with several wind farms and larger capacities (approx. 3000 – 11000 MW)<br />

For these zones – Irish Sea, Dogger Bank, Hornsea, and Norfolk – the approach was similar to that<br />

used for the smaller zones but the essential difference was that the larger power injection<br />

concentrated in one area of the system meant that transmission network reinforcement would be<br />

necessary. The design optimisation therefore included costs for reinforcing the main interconnected<br />

transmission system as well as the cost of simply connecting the offshore wind to one or more grid<br />

substations.<br />

The overall system changes required for these larger zones are such that a wind farm-by wind farm<br />

breakdown is misleading as the costs are driven by the totality of the installed wind generation, and<br />

cannot be itemised to individual wind farms. Put another way, each individual wind farm might<br />

require little or no reinforcement, but in combination they do. Solutions are therefore presented for<br />

complete zones.<br />

5.6 Scottish System Area<br />

The same approach was taken with regard to the zones located closest to the Scottish Transmission<br />

Owner sites. Working from published network data, high level evaluations were made of possible<br />

connection options.<br />

The costs estimates used have been based on an average of similar works proposed for the National<br />

Grid substation and overhead line works, and would require verification from the relevant<br />

Transmission Owner. The connection options identified for these areas are therefore more prone to<br />

revisions than those proposed for England and Wales.<br />

6 Overall Design Options and Potential Zonal Solutions<br />

The various options considered, high-level design considerations and potential zonal transmission<br />

network solutions are summarised below. These are presented against the input assumptions of the<br />

scenario, taking into account relevant sensitivities and a background of general reinforcements which<br />

are assumed to have already been completed within the timescales analysed.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 41 of 94


6.1 Moray Firth<br />

1<br />

2<br />

Option<br />

0.5GW AC<br />

to new<br />

substation<br />

0.5GW AC<br />

to Keith<br />

OWF <strong>Offshore</strong><br />

Transmission Substation<br />

Extension<br />

Onshore Transmission<br />

Network<br />

Reinforcement<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 42 of 94<br />

Total<br />

C £178m £15*m £193m<br />

subject to<br />

collaborative<br />

TO study<br />

outcome<br />

C £256m £3*m<br />

£259m<br />

Table 10 : <strong>Connection</strong> cost for Moray Firth Zone<br />

Comments<br />

- indicative<br />

onshore costs<br />

- based on<br />

England &<br />

Wales average<br />

- indicative<br />

onshore costs<br />

- based on<br />

England &<br />

Wales average<br />

* It is important to note that Scottish Transmission owners have not been consulted in putting together the onshore<br />

transmission costs and that these were compiled on the basis of average costs in England and Wales. This portion of the<br />

costs could change significantly as a result.<br />

Figure 12: Moray Firth zone connection overview


6.1.1 <strong>Offshore</strong> connection<br />

Due to the nominal capacity of the offshore wind farm (OWF) located in the Moray Firth and the<br />

distance to the potential connection points a HVDC connection solution was discounted for economic<br />

reasons. Instead an HVAC solution has been proposed consisting of two offshore 33/245kV<br />

substations interconnected with a single three core 245kV cable, and each with a single three core<br />

245kV shorelink cable to transmit the power accumulated from the wind farm to a transition pit<br />

located at the landing point onshore. From this transition pit six single core 245kV cables have been<br />

routed to the potential connection point at Keith 275kV substation. The onshore cable route follows<br />

the road network as much as possible however there are a number of obstacles that would need to<br />

be crossed along the proposed route. The estimated cost for directional drilling under these<br />

obstacles has been included as part of the overall offshore connection cost estimate. Due to the total<br />

HVAC cable length of this connection, a significant amount of reactive compensation is required to<br />

maintain adequate power transfer levels. This reactive compensation has been located both on the<br />

offshore substations and in an onshore substation compound adjacent to Keith substation along with<br />

the associated switchgear and step up transformers which form part of the offshore transmission<br />

assets. Both the offshore and onshore substations have been designed to comply with the offshore<br />

SQSS proposals (see Section 3.4) and are represented in diagrammatic form in Senergy Econnect<br />

drawing 1845 009 (p34). It has been assumed that a two switchbay extension to Keith 275kV<br />

substation would be required to connect the Moray Firth OWF however this would need to be<br />

confirmed with the onshore transmission asset owner.<br />

6.1.2 <strong>Offshore</strong> connection alternatives<br />

The alternative connection solution for the Moray Firth OWF follows the same offshore connection<br />

route and design but connects to a new 275kV substation a couple of kilometres from the landing<br />

point. As the assets from this point onward would form part of the onshore transmission network, this<br />

option is discussed in more detail in Section 6.1.3.<br />

6.1.3 Onshore reinforcement<br />

Currently, the onshore transmission system is unable to transmit the electricity generated by the<br />

large volumes of renewable generation expected to arise in Scotland down into England where the<br />

majority of demand for electricity is located. The original ‘Renewable Energy Transmission Study’<br />

(RETS) and ‘RETS revisited’ undertaken in 2003 and 2005 respectively, did not envisage the 6 to<br />

11GW of renewable generation now considered likely. Therefore a further collaborative study is<br />

underway between the three onshore transmission owners; National Grid Electricity Transmission<br />

(NGET), Scottish Power Transmission Ltd. (SPT) and Scottish Hydro Electric Transmission Ltd.<br />

(SHETL) under the Electricity Networks Strategy Group (ENSG), to develop the transmission system<br />

in order to facilitate the levels of generation assumed to be required to meet 2020 renewable targets.<br />

The study underpinning this document has not sought to pre-empt the outcome of the<br />

aforementioned collaboration and has made the assumption that the necessary reinforcements from<br />

Scotland into England are already in place. The impact of the need for these reinforcements on the<br />

connection of further rounds of wind leasing is predominately limited to those wishing to connect<br />

offshore in Scotland, such as the Moray Firth, north of this critically congested part of the network.<br />

The alternative connection option relies on potentially adopting an existing 132kV overhead line that<br />

runs from Keith towards the coast, upgrading this line to 275kV and establishing a new 275kV<br />

substation at the coast. The cost of this new substation has been included in Table9, but the cost of<br />

the line upgrade and associated distribution network works has not for the reasons identified above.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 43 of 94


6.2 Firth of Forth<br />

1<br />

2<br />

Option<br />

0.5GW<br />

AC to<br />

Torness<br />

0.5GW<br />

DC tied<br />

into VSC<br />

1.1 GW<br />

East<br />

Coast<br />

link<br />

OWF<br />

<strong>Offshore</strong><br />

Transmission<br />

Onshore Transmission<br />

Substation<br />

Extension<br />

Network<br />

Reinforcement<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 44 of 94<br />

Total<br />

G £135m £15m £150m<br />

G £165m n/a<br />

subject to<br />

collaborative TO<br />

study outcome<br />

Table 11: <strong>Connection</strong> cost for Firth of Forth Zone<br />

£165m<br />

Comments<br />

- indicative<br />

onshore costs<br />

- based on<br />

England &<br />

Wales average<br />

- HVDC<br />

interconnection<br />

assumed<br />

- Control system<br />

technical issues<br />

* It is important to note that Scottish Transmission owners have not been consulted in putting together the<br />

onshore transmission costs and that these were compiled on the basis of average costs in England and Wales.<br />

This portion of the costs could change significantly as a result.<br />

Figure 13: Firth of Forth zone connection overview


6.2.1 <strong>Offshore</strong> connection<br />

Again due to the nominal capacity of the offshore wind farm (OWF) located in the Firth of Forth and<br />

the distance to the potential connection points a HVAC solution has been proposed consisting of two<br />

offshore 33/245kV substations interconnected with a single three core 245kV cable, and each with a<br />

single three core 245kV shorelink cable to transmit the power accumulated from the wind farm to a<br />

landing point onshore. As the proposed connection point at Torness 400kV substation is on the<br />

coast, the design assumes that the subsea cable will be brought into the substation cable sealing<br />

ends, with no transition to single core underground cable.<br />

Again the necessary reactive compensation has been located both on the offshore substations and<br />

in an onshore substation compound adjacent to Torness substation along with the associated<br />

switchgear and step up transformers which form part of the offshore transmission assets ( see<br />

drawing 1845 009 (p34). It has been assumed that a two switchbay extension to Torness 400kV<br />

substation would be required to connect the Firth of Forth OWF however this would need to be<br />

confirmed with the onshore transmission asset owner.<br />

6.2.2 <strong>Offshore</strong> connection alternatives<br />

The alternative connection solution for the Firth of Forth OWF makes use of a proposal to introduce<br />

an offshore HVDC transmission link between Peterhead and Hawthorn Pit to reinforce the onshore<br />

transmission network and accommodate expected power flows from the generation capacity installed<br />

onshore and offshore in Northern Scotland. The route of this offshore transmission link is likely to<br />

pass very close to the Firth of Forth OWF and hence a 500MW HVDC converter could be connected<br />

to the HVDC transmission link at this point to allow transmission of generation output from the OWF.<br />

This solution relies on the HVDC bipole forming the section from the OWF to Hawthorn Pit being<br />

sufficiently rated to allow transfer of the expected power flow from Peterhead and the output<br />

expected from the OWF coincidentally. The connection design for the OWF relies on two 33/245kV<br />

offshore substations interconnected with a single three core 245kV cable, and each with a single<br />

three core 245kV cable to transmit the power accumulated from the wind farm to an offshore platform<br />

housing the HVDC VSC 500MW converter.<br />

As the East Coast Interconnector assets would effectively form part of the onshore transmission<br />

network, this option is discussed in more detail in Section 6.2.3.<br />

6.2.3 Onshore reinforcement<br />

As highlighted in Section 6.1.3, the study underpinning this document has not sought to pre-empt the<br />

outcome of the transmission owner collaborative study currently underway and has made the<br />

assumption that the necessary reinforcements from Scotland into England are already in place. The<br />

impact of the need for these reinforcements on the connection of further rounds of wind leasing is<br />

predominately limited to those wishing to connect offshore in Scotland, such as the Firth of Forth,<br />

north of this critically congested part of the network.<br />

The main options being considered under this work are incremental upgrades to the onshore<br />

transmission system and offshore HVDC links on the west coast from Hunterston to Deeside and on<br />

the east coast from Peterhead to Hawthorne Pit. This study has considered a scenario where the two<br />

offshore HVDC links are in place. Therefore, sufficient capacity is assumed to exist from Scotland<br />

into England in order to facilitate this investigation.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 45 of 94


6.3 Dogger Bank & Hornsea<br />

Due to the potential connection capacity and distance from shore of the Dogger Bank Zone, there is<br />

much greater potential for optimisation in bringing the wind power onto the onshore transmission<br />

system. Also because the offshore wind farms in the Hornsea zone are likely to connect in the same<br />

area of the network as the Dogger Bank offshore wind farms this initial investigation into a<br />

coordinated approach has assessed transmission network reinforcement requirements for both<br />

zones based on the following approaches:<br />

• <strong>Offshore</strong> transmission connections extended inland to existing National Grid substations at<br />

Creyke Beck, Thornton, Drax, Keadby and South Humber Bank<br />

• Hybrid arrangements combining connections to existing transmission sites at Creyke Beck,<br />

Keadby and Grimsby West and new substations to be established near Killingholme and on<br />

the Lincolnshire coast<br />

Note that in some of the connection solutions proposed in this section, the offshore transmission<br />

system extends to more southerly connection points onshore than those adjacent to the Dogger<br />

Bank zone on the North East coast. This is because the designs proposed balance the need for<br />

offshore and onshore reinforcement in order to achieve the optimal solution. The design issues<br />

associated with each of these options are outlined in Sections 6.3.1.and 6.3.2 and their costs are<br />

summarised in the table 12 below.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 46 of 94


Figure 14: Dogger Bank zone option 1 connection overview<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 47 of 94


Figure 15: Dogger Bank zone option 2 connection overview<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 48 of 94


Figure 16: Dogger Bank zone option 3 connection overview<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 49 of 94


1<br />

2<br />

Option<br />

DOGGER BANK<br />

2.2GW each:<br />

Drax<br />

Thornton<br />

Creyke Beck<br />

Keadby<br />

OWF<br />

<strong>Offshore</strong> Transmission<br />

<strong>Connection</strong><br />

Substation<br />

Onshore Transmission<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 50 of 94<br />

Cost<br />

H1 Thornton £530m<br />

J Thornton £580m<br />

H2 Drax £576m<br />

H3 Drax £595m<br />

H4 Creyke £540m<br />

H5 Creyke £560m<br />

I1 Keadby £664m<br />

I2 Keadby £682m<br />

HORNSEA<br />

2.2GW at South<br />

M South Humber £413m<br />

Humber Bank N South Humber £437m<br />

DOGGER BANK<br />

2.2 GW at Creyke<br />

Beck<br />

4.4 GW New<br />

substation Near<br />

Killingholme<br />

2.2GW at Keadby<br />

H1 Creyke £511m<br />

J Creyke £561m<br />

H2 Keadby £607m<br />

H3 Keadby £623m<br />

H4 Killingholme £568m<br />

H5 Killingholme £584m<br />

I1 Killingholme £612m<br />

I2 Killingholme £630m<br />

HORNSEA<br />

2.2GW at Grimsby<br />

M Grimsby £413m<br />

West N Grimsby £438m<br />

Substation<br />

Extension<br />

Cost<br />

£16m<br />

£19m<br />

£14m<br />

£10m<br />

£22m<br />

£14m<br />

£10m<br />

£62m<br />

£16m<br />

Network<br />

Reinforcement<br />

Cost<br />

Total<br />

Cost<br />

£290m £5,948m<br />

£319m £5,968m<br />

Comments<br />

Major Onshore work<br />

includes:<br />

- New 400kV OHL<br />

Willington to<br />

Chesterfield<br />

- New 400kV OHL<br />

Drax- Keadby (sensitive<br />

to review of GB SQSS)<br />

Maximum offshore costs<br />

due to extent of onshore<br />

cabling to existing sites<br />

Onshore work includes:<br />

- 400kV OHL; Grimsby<br />

West to Walpole (or<br />

Bicker Fen)<br />

- 400kV OHL; Creyke<br />

Beck to Drax (sensitive<br />

to review of GB SQSS)<br />

- 400kV OHL; Walpole<br />

(or Bicker Fen) to new<br />

substation north of<br />

Eaton Socon


3<br />

Option<br />

DOGGER BANK<br />

3.3 GW at Creyke<br />

Beck<br />

3.3 GW at new<br />

substation Near<br />

Killingholme<br />

2.2GW at Keadby<br />

OWF<br />

HORNSEA<br />

M<br />

2.2GW at new<br />

substation along<br />

Lincolnshire coast N<br />

<strong>Offshore</strong> Transmission Onshore Transmission<br />

<strong>Connection</strong><br />

Substation<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 51 of 94<br />

Cost<br />

H1 Creyke £511m<br />

H3 Creyke £541m<br />

J Creyke £561m<br />

H2 Keadby £607m<br />

H4 Keadby £619m<br />

H5 Killingholme £584m<br />

I1 Killingholme £612m<br />

I2 Killingholme £630m<br />

Lincolnshire<br />

coastal<br />

substation<br />

£404m<br />

Substation<br />

Extension<br />

Cost<br />

£17m<br />

£10m<br />

£52m<br />

Network<br />

Reinforcement<br />

Cost<br />

£23m<br />

Lincolnshire<br />

coastal £428m<br />

substation<br />

Table 12: <strong>Connection</strong> cost for Dogger Bank and Hornsea Zones<br />

Total<br />

Cost<br />

£319m £5,918m<br />

Comments<br />

- 400kV OHL; Grimsby<br />

West to Walpole (or<br />

Bicker Fen)<br />

- 400kV OHL; Creyke<br />

Beck to Drax<br />

- 400kV OHL; Walpole<br />

(or Bicker Fen) to new<br />

substation north of<br />

Eaton Socon


6.3.1 <strong>Offshore</strong> connection<br />

The capacity of the Dogger Bank and Hornsea OWF and their distance from the proposed<br />

connection points dictate that a conventional HVAC solution will be impractical and uneconomic and<br />

hence an HVDC solution has been applied in each case. For the reasons mentioned in Section<br />

3.3.2, VSC HVDC technology is ideally suited to applications offshore and it is this technology that<br />

has been used for these connections. Indeed the capacity of the OWF themselves has been tailored<br />

to the maximum power transfer rating (1110MVA) of a single VSC bipole/converter pair indicated by<br />

the manufacturers for this study. As each OWF would fully utilise the available power transfer<br />

capability of its dedicated VSC bipole/converter pair there is no advantage in this primary solution of<br />

interconnecting the OWF offshore, hence each OWF in these two zones is radially connected using<br />

an HVDC bipole arrangement to its onshore connection point as indicated in Table12 with the<br />

offshore (subsea) and onshore (underground) cable costs and obstacle crossings both onshore and<br />

subsea costed separately. Note that the offshore cable routes themselves are designed to avoid<br />

areas allocated for mineral extraction, other wind farms, or concentrations of oil and gas pipelines,<br />

however some pipeline and cable crossings are inevitable, and for some routes numerous, and as<br />

such the cost of these crossings has been included in the cost estimates within the appropriate<br />

connection designs.<br />

There are alternative technologies available which may allow and indeed favour interconnecting the<br />

OWF in these two zones and some of these options are discussed in more detail in Section 6.3.2<br />

<strong>Offshore</strong> the OWF connection design is based on two 33/245kV offshore substations each consisting<br />

of three 200MVA 33/245kV transformers with associated GIS switchgear. Each offshore AC<br />

substation is interconnected to an HVAC busbar on the offshore platform housing the HVDC VSC<br />

1110MW converter via a pair of three core 245kV cables. Although this design requires an extended<br />

33kV cable array to connect the wind turbines to the offshore substations, it has the advantage of<br />

reducing the number of platforms, transformers and switchgear, and 245kV AC cable length required<br />

offshore, and hence represents significant savings in capital cost. As stated previously an analysis of<br />

the full lifetime capital and operational costs will be required to optimise the overall electrical design<br />

for each specific wind farm; however such an analysis is outside the remit of this report.<br />

The power from the offshore converter is then routed through two HVDC cables (forming a bipole) to<br />

an onshore 1110MVA converter located in a compound adjacent to the National Grid connection<br />

substation where it is converted back from DC to AC for input into the onshore transmission network.<br />

Both the offshore and onshore substations have been designed to comply with the offshore SQSS<br />

proposals (see Section 3.4) and are represented in diagrammatic form in Senergy Econnect<br />

drawings 1845 010 and 011 (p35 &36). It has been assumed that a two switchbay extension will be<br />

required at those connection points that are existing substations to connect the Dogger Bank and<br />

Hornsea OWF in line with the requirement of the offshore SQSS for 50% redundancy in the onshore<br />

transformers. Again where a new double busbar 400kV substation is deemed necessary, two<br />

switchbays per wind farm have been allocated and costed as part of the offshore transmission<br />

assets.<br />

The three connection scenarios identified in Table12 and represented in Figures 14, 15 and 16 have<br />

been determined to illustrate the requirement for onshore transmission network reinforcement<br />

necessary for connection of the Dogger Bank and Hornsea zones (see Section 6.3.3). At each<br />

connection point sufficient land area has been identified (and costed based on a nominal £/per<br />

hectare rate) to locate the onshore HVDC converter stations for each OWF adjacent to the existing<br />

or proposed National Grid substation.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 52 of 94


6.3.2 <strong>Offshore</strong> connection alternatives<br />

The three offshore connection alternative options described below (and summarised in Table12) are<br />

designed to illustrate alternative technologies that could potentially be used in place of the HVDC<br />

VSC technology used in the primary solutions for the Dogger Bank. The onshore implications of<br />

using these connection alternatives have not been considered.<br />

Option 4 foresees the use of Current Source Converter technology to provide the transmission<br />

medium from the OWF to the onshore connection point. CSC technology combined with Mass<br />

Impregnated HVDC cables (see Section 3.3) allow for much greater power transfer capabilities than<br />

VSC. For example option 4 is based on a dual converter HVDC design operating at +/-500kV utilising<br />

four MI HVDC cables with a common LV return cable. This would give a power transfer capability of<br />

3000MW. However in order to minimise the inter wind farm AC cabling necessary to accumulate this<br />

amount of power at the converter platforms, option 1 foresees the installed wind farm capacity in<br />

polygon I of the Dogger Bank zone being expanded from 2480MW to 3360MW with the<br />

corresponding increase in offshore substations. The disadvantages of using CSC offshore such as<br />

the increased physical converter size, and the requirement to provide a strong voltage source in<br />

order for the converters to operate has been allowed for in the cost estimates. Note that as such<br />

technology has not been used offshore to date, the cost estimates below can only be indicative at<br />

this stage.<br />

Option 5 utilises the GIL technology introduced in Section 3.3.3 to provide a ‘power corridor’ out to<br />

polygon I in the Dogger Bank, in this option with an installed capacity expanded to 3105MW. The<br />

creation of these power corridors utilising GIL technology is one option being considered in Germany<br />

for the connection of their own offshore wind farms in the North Sea. However as yet this technology<br />

has yet to be installed in an offshore/subsea environment and hence the costs provided by the<br />

manufacturer for onshore installation have been extrapolated by Senergy Econnect based on<br />

pipeline and cable laying costs in order to provide the indicative cost estimates in the Table below.<br />

The other issue to note with this option is that it does not comply with the proposed offshore SQSS<br />

as the maximum power infeed loss (2771MW at 400kV) would exceed the 1800MW* limit (*see<br />

Section 3.4).<br />

Option 6 still utilises HVDC VSC technology offshore but recognises that the cable route between the<br />

land fall point on the coast and the connection substation at Drax for the H2 and H3 OWF identified<br />

in Option 1 is extensive. Hence the use of a single HVDC overhead line to transport the bipole<br />

conductors for both OWF on a more direct route from the land fall point to Drax substation may be<br />

considered an economic alternative. The costs for HVDC overhead line used in the cost estimates<br />

below have been derived from a manufacturer’s article in the IEEE Power & Energy magazine [19].<br />

Note that this option would not meet the current onshore GB SQSS criteria for the maximum power<br />

infeed loss (1320MW) for the loss of a double circuit overhead line.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 53 of 94


4<br />

5<br />

6<br />

Option<br />

DOGGER BANK<br />

I1 & I2 combined and<br />

enlarged to 3360MW<br />

installed and jointly<br />

connected via HVDC CSC<br />

to Killingholme<br />

DOGGER BANK<br />

I1 & I2 combined and<br />

enlarged to 3104MW<br />

installed and jointly<br />

connected via GIL to<br />

Killingholme<br />

DOGGER BANK<br />

H2 & H3<br />

Jointly connected onshore<br />

via HVDC overhead line to<br />

Drax<br />

OWF<br />

I1<br />

I2<br />

I1<br />

I2<br />

H2<br />

H3<br />

<strong>Connection</strong><br />

Substation<br />

<strong>Offshore</strong> Transmission<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 54 of 94<br />

Cost<br />

£M<br />

Cost<br />

per MW<br />

£k<br />

Killingholme £2,202m £655k<br />

Killingholme £3,185m £1,026k<br />

Drax<br />

£1,076 £434k<br />

Table 13: Alternative combination connection costs for Dogger Bank zone<br />

Cost per MW<br />

comparison<br />

£<br />

I1 & I2 to<br />

Killingholme<br />

£501k<br />

I1 & I2 to<br />

Killingholme<br />

£501k<br />

H2 & H3 to<br />

Drax<br />

£473k


Figure 17: Dogger Bank Polygon I CSC connection overview<br />

Figure 18: Dogger Bank Polygon I GIL connection overview<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 55 of 94


6.3.3 Onshore reinforcement<br />

In all cases, including those where the offshore HVDC links are brought into existing National Grid<br />

substations, reinforcement with new 400 kV lines would be needed to ensure enough local<br />

transmission capacity to carry the full capacity of the wind farms entering the onshore transmission<br />

system at the onshore interface. This is currently a requirement under Section 2 of the GB SQSS.<br />

Additionally, a new 400 kV overhead line route would be required to carry the increased power<br />

transfer southwards from the Yorkshire/Lincolnshire area. This requirement would be driven by the<br />

criteria of Section 4 of the GB SQSS for design of the Main Interconnected Transmission System<br />

(MITS).<br />

The choice of route for this new North to Midlands line depends on the connection points of the<br />

offshore HVDC links. With “inland” connections (Drax, Thornton, Creyke Beck, Keadby and Grimsby<br />

West/South Humber Bank – Option 1, above), the most effective option would be a new 400 kV line<br />

from Chesterfield to Willington, with uprating of the existing 275 kV Brinsworth-Chesterfield circuits to<br />

400 kV. With connections around the Humber Estuary (Creyke Beck, Keadby, Grimsby West and<br />

near Killingholme, or new substations close to the coast – Option 2 and 3, above), a route from<br />

Grimsby through Lincolnshire to Walpole (or Bicker Fen) would be preferred. To be fully effective,<br />

this line would have to be extended westwards from the Walpole (or Bicker Fen) substation to a new<br />

substation to be established on the existing Cottam – Eaton Socon circuits somewhere near<br />

Peterborough. This final section of required overhead line, extending westwards from Walpole (or<br />

Bicker Fen) would link two critical north to south circuits on the east coast and have the added<br />

benefit of providing additional onshore transmission capacity for connections into the East Anglia<br />

region as well as the potential for connecting any future offshore developments further south in the<br />

Wash.<br />

The locations of the potential major reinforcements required against the input assumptions used are<br />

illustrated in Figure 19, below.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 56 of 94


Figure 19: Dogger Bank & Hornsea Local Onshore Transmission Network and Location of Potential Onshore<br />

Transmission Reinforcement<br />

Arrangements that involved extending the transmission system eastwards to the coast<br />

(predominately north of the Humber) to connect all the assumed offshore wind generation in these<br />

zones involve more construction of new 400 kV overhead line routes and substations than the<br />

aforementioned options.<br />

As explained in Section 5, onshore transmission requirements are sensitive to the onshore<br />

generation background as well as to the energy coming ashore from offshore wind. Requirements<br />

may also vary as consequences of the current reviews of the GB-SQSS and transmission access<br />

arrangements. The optimum arrangement found in this investigation with 3.3 GW connected at both<br />

Creyke Beck and a new substation near Killingholme, and 2.2 GW connected at both Keadby and<br />

Grimsby West – may well cease to be the optimum choice if the background assumptions change.<br />

While the costs estimated in this work may be taken as indicative of the likely range of eventual<br />

costs, the connection arrangements eventually used will depend on the conventional generation<br />

projects that may be developed in the Yorkshire/Humber area in parallel with the offshore wind<br />

programme.<br />

As outlined above, a variety of solutions were considered, for the overall connection of 11GW from<br />

the Dogger Bank and Hornsea zones. These options ranged from onshore cabling to a variety of<br />

existing National Grid substations, to providing all new connection points on the Lincolnshire, or<br />

Yorkshire coasts. Overall the most economic solution is presently to undertake a mixture of cabled<br />

connections to existing sites and extending the National Grid MITS.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 57 of 94


The primary solution comprises three 1100MVA connections to be cabled to Creyke Beck and two<br />

1100 MVA connections cabled to Keadby substation. A new 400kV substation is proposed to be<br />

established at the existing Grimsby West substation along with a new 400kV overhead line, or at a<br />

new substation on a new Grimsby West – Walpole 400kV overhead line along the Lincolnshire coast<br />

to accommodate a further two 1100 MW connections,. An additional new 400kV substation to<br />

accommodate three 1100MW connections is proposed south of the existing Killingholme substation,<br />

to provide connections into three existing 400kV overhead line routes.<br />

As mentioned, in addition a new 400kV overhead line is required from Grimsby West to Walpole (or<br />

Bicker Fen) substation, continuing on to a new 400kV substation to be established on the Cottam –<br />

Eaton Socon double circuit and another new 400kV overhead line is required from Creyke Beck to<br />

Drax. The additional cost of this onshore infrastructure is £319m.<br />

All options require the construction of new 400kV overhead lines and substations to provide a<br />

compliant system, with all of the capacity connected. The substation extension and network<br />

reinforcement costs provided above assume that a coordinated approach is taken to the design of<br />

the offshore network. No environmental impact assessments of the reinforcement options have been<br />

undertaken at this stage.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 58 of 94


6.4 Norfolk<br />

For the Norfolk zone transmission system reinforcement requirements were assessed for offshore<br />

transmission connections extending inland to existing National Grid substations such as Norwich,<br />

Sizewell and Rayleigh<br />

Sizewell is a connection point for an existing, advanced gas-cooled reactor (AGR) nuclear generator.<br />

DECC has yet to complete the Strategic Environmental Assessment for nuclear siting, but the<br />

connection of new nuclear units at Sizewell is an option that could be constructed within similar<br />

timescales to that of <strong>Round</strong> 3 offshore developments. One scenario utilised for this study did not<br />

include nuclear replanting at Sizewell within the assumed timescales. However, British Energy<br />

currently has Bilateral <strong>Connection</strong> Agreements in place for the connection of two European<br />

Pressurised Water Reactor (EPR) nuclear generators at Sizewell with 1650MW in 2016 and a further<br />

1650MW in 2021. In light of this further assessments were undertaken to consider the infrastructure<br />

to provide sufficient onshore transmission capacity if these additional nuclear units at Sizewell<br />

proceed. The studies also assumed that the existing Sizewell B plant would still be generating as it is<br />

feasible that there will be some parallel running of both Sizewell B and Sizewell C stations for a<br />

period of time before decommissioning of Sizewell B takes place.<br />

Figure 20: Norfolk zone option 1 connection overview<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 59 of 94


Figure 21: Norfolk zone option 2 connection overview<br />

The design issues associated with each of these options are outlined in Sections 6.4.1, 6.4.2, and<br />

6.4.3 and their costs are summarised in the Table 14 below.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 60 of 94


1<br />

2<br />

Option <strong>Offshore</strong> Transmission £M Substation<br />

Extension £M<br />

2.2GW AC<br />

at Norwich<br />

2.2GW AC<br />

at Sizewell<br />

1.1GW<br />

Norwich<br />

1.1GW<br />

Sizewell<br />

2.2GW<br />

Rayleigh<br />

OWF<br />

T<br />

(AC)<br />

<strong>Connection</strong><br />

Substation<br />

Sizewell £223m<br />

Z2 Sizewell £436m<br />

U<br />

(DC)<br />

Norwich £410m<br />

Z1 Norwich £451m<br />

T<br />

(AC)<br />

U<br />

(DC)<br />

Z1<br />

Z2<br />

Onshore Transmission<br />

Network<br />

Reinforcement<br />

£M<br />

Cost<br />

£M<br />

Without new nuclear unit at Sizewell<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 61 of 94<br />

£30m<br />

£7m<br />

Sizewell £223m £23m<br />

Norwich £410m £4m<br />

Rayleigh £573m<br />

Rayleigh £559m<br />

With new nuclear unit at Sizewell<br />

£11m<br />

Total<br />

£M<br />

£171m £1,728m<br />

£187m £1,990<br />

Table 14: <strong>Connection</strong> costs for Norfolk Zone<br />

Comments<br />

Major onshore work includes:<br />

- Reconductor of two Sizewell-<br />

Bramford 400kV double<br />

circuits,<br />

- New Bramford 400kV<br />

substation<br />

- New 400kV Bramford to<br />

Twinstead double circuit OHL<br />

to create a Pelham-Bramford<br />

double circuit route and<br />

Bramford-Braintree-Rayleigh<br />

overhead line with<br />

reconductoring of Bramford-<br />

Braintree-Rayleigh OHL<br />

routes.<br />

The overall optimum design<br />

proposed for this background<br />

(i.e. with new nuclear at Sizewell)<br />

has sought to minimise onshore<br />

reinforcement requirements to<br />

reduce timescales. However, if<br />

onshore reinforcement where to<br />

begin in advance of financial<br />

commitment from users, it may<br />

be possible for a more economic<br />

solution to be delivered within the<br />

necessary timescales.


6.4.1 <strong>Offshore</strong> connection<br />

Due to the proximity of the OWF T and U in the Norfolk zone to their respective connection points at<br />

Sizewell and Norwich Main, cost estimates for both an HVAC and HVDC solution were derived.<br />

However due to the their distance offshore, AC solutions for OWF Z1 and Z2 were not deemed<br />

pragmatic and hence only HVDC connection solutions have been assessed for these two wind<br />

farms. As explained in Section 6.4.3, the connection points for OWF Z1 and Z2 and hence their<br />

respective bipole cable route lengths, (which form the bulk of the cost differential between the<br />

offshore costs in option 1 and option 2), have been determined by the presence or not of a new<br />

nuclear unit at Sizewell C.<br />

<strong>Offshore</strong> the OWF connection designs are based on two 33/245kV offshore substations each<br />

consisting of three 200MVA 33/245kV transformers with associated GIS switchgear. For the HVDC<br />

solutions each offshore AC substation is then interconnected to an HVAC busbar on the offshore<br />

platform housing the HVDC VSC 1110MW converter via a pair of three core 245kV cables.<br />

The power from the offshore converter is then routed through two HVDC cables (forming a bipole) to<br />

an onshore 1110MVA converter located in a compound adjacent to the National Grid connection<br />

substation where it is converted back from DC to AC for input into the onshore transmission network.<br />

Where a new double busbar substation extension to the existing National Grid substation is deemed<br />

necessary, two 400kV switchbays have been allocated and costed as part of the offshore<br />

transmission assets.<br />

The HVAC connection solution utilised for OWF T and U is different. In this design two 245kV three<br />

core cables are taken direct from each offshore substation to the landfall point (i.e. four three core<br />

cables in total). Where required there is a transition at this point from three core subsea cable to<br />

three single core underground cables per circuit (i.e. twelve cables in total) which are then routed to<br />

a 245kV busbar in a compound adjacent to the National Grid substation, the voltage is then stepped<br />

up to 400kV via two 600MVA transformers for input into the National Grid via two GIS or AIS 400kV<br />

double busbar switchbays as appropriate. The cost of crossing both the offshore and onshore<br />

obstacles along these cable routes, the cost of the transition, and the cable joints have all been<br />

allowed for in the cost estimates provided. This design meets the offshore SQSS requirement for<br />

50% redundancy in export capacity from an offshore platform following loss of an AC cable but does<br />

not require the offshore substations to be interconnected. This 1200MW HVAC design is represented<br />

diagrammatically in Senergy Econnect drawing No 1845-011 (p36)<br />

6.4.2 <strong>Offshore</strong> connection alternatives<br />

As explained in the previous section, alternative connection solutions for wind farms T and U were<br />

costed using HVAC and HVDC technology for comparison purposes. Options 3 and 4 (see Table14)<br />

demonstrate the breakpoint of where HVAC becomes uneconomic and HVDC economic and vice<br />

versa. Because OWF T is relatively close to Sizewell, the extra cost of the two HVDC converters<br />

outweighs the saving in cable cost in using an HVDC solution (two cables for DC as opposed to four<br />

for the equivalent AC solution), however for OWF U the cost of the additional AC cables particularly<br />

onshore (with twelve AC cables required as opposed to two for the DC option) more than covers the<br />

cost of the two converter stations (and their attendant platforms/compounds and switchgear).<br />

It is the length of this onshore cable route for OWF U and Z1 from the landfall on the Norfolk coast to<br />

the connection substation at Norwich that is addressed in option 5. This option looks at the impact on<br />

the overall cost of these two wind farms were the onshore section to be constructed using a HVDC<br />

double bipole overhead line rather than underground HVDC cable. The costs for HVDC overhead<br />

line used in the cost estimates below have been derived from a manufacturer’s article in the IEEE<br />

Power & Energy magazine [19]. Note that this option would not meet the current onshore GB SQSS<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 62 of 94


criteria for the maximum power infeed loss (1320MW) for the loss of a double circuit overhead line,<br />

or for the loss of two generator connection circuits, depending on how this line would be classified.<br />

Option 6 considers the use of CSC HVDC technology to assess whether combining the Z1 and Z2<br />

OWF, but reducing the combined installed capacity to 1680MW, and transmitting the power through<br />

a single CSC converter pair/bipole may be an economic alternative for connection to Rayleigh than<br />

using the two VSC converter pairs/bipoles in option 2.<br />

3<br />

4<br />

5<br />

6<br />

Option<br />

OWF T connected to<br />

Sizewell using HVDC VSC<br />

OWF U connected to<br />

Norwich using 245kV HVAC<br />

OWF U and Z1 jointly<br />

connected onshore via<br />

HVDC overhead line to<br />

Norwich<br />

OWF Z1 & Z2 combined<br />

and reduced to 1680MW<br />

installed and jointly<br />

connected via HVDC CSC<br />

to Rayleigh<br />

OWF<br />

6.4.3 Onshore reinforcement<br />

<strong>Connection</strong><br />

Substation<br />

<strong>Offshore</strong> Transmission<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 63 of 94<br />

Cost<br />

£M<br />

Cost<br />

per MW<br />

£k<br />

T (DC) Sizewell £356m £287k<br />

U (AC) Norwich £590m £477k<br />

U<br />

Z1<br />

Z1<br />

Z2<br />

Norwich £811m £328k<br />

Rayleigh<br />

£1,057m £629k<br />

Table 15: Alternative connection costs for Norfolk Zone<br />

Cost per MW<br />

comparison<br />

£<br />

T(AC) to<br />

Sizewell<br />

£180k<br />

U(DC) to<br />

Norwich<br />

£331k<br />

U & Z1 to<br />

Norwich<br />

£348k<br />

Z1 & Z2 to<br />

Rayleigh<br />

£457k<br />

Due to the proximity of parts of the offshore Norfolk zone to Sizewell (as little as 20km at points), a<br />

portion of the Norfolk zone generation can be brought ashore via AC cables. The distance from the<br />

offshore zone to Norwich and Rayleigh indicate that HVDC subsea cable could provide a more<br />

economic solution for connection to these substations. The choice of technology impacts the local<br />

substation works only in evaluating the onshore transmission reinforcements.<br />

To enable the full export of the power generated by the OWF onto the onshore transmission system<br />

plus the generation background assumed in the scenario, transmission reinforcement is required to<br />

transfer power further south towards the Essex area.<br />

Whether the Norfolk zone OWF are connected wholly into East Anglia or split between coonection<br />

points in East Anglia and further south (such as Rayleigh), there is a common set of onshore<br />

reinforcements arising out of the GB SQSS requirements. The additional incremental capacity<br />

available due to the construction of a new section of OHL and substation reconfiguration at<br />

Bramford, allows the full 4.4GW investigated to be connected within the East Anglia region thus<br />

minimising offshore cable lengths. However, if the connection of new nuclear generation at Sizewell<br />

is taken into account, further MITS reinforcement is required. The impact of this on the connection of<br />

OWF is dependent on the relative timing of these developments.


Extending the onshore transmission out to the coast to minimise the amount of onshore cabling from<br />

the East Coast wind farms was not considered in detail. This solution would necessitate a new<br />

400kV double circuit line from a new coastal substation to Norwich. As this option still injects the<br />

output of the OWF into East Anglia it does not alleviate the congested Sizewell to Pelham circuit<br />

corridor. In this way the onshore transmission reinforcements outlined above would still be required<br />

and therefore this option was not considered further at this time. However option 5 in Section 6.4.2<br />

does consider the use of HVDC overhead line from Norwich to the coast. As this route would<br />

traverse the Norfolk Broads the use of either HVAC or HVDC overhead line would depend on<br />

planning and project timescales.<br />

6.4.3.1 Zonal Infrastructure Works (without Sizewell C)<br />

The connection of HVDC converters at Norwich and Rayleigh substations would necessitate<br />

additional switchgear and substation extensions. The remaining 1.1GW HVDC connection in this<br />

zone cannot be accommodated in the existing Sizewell substation compound. As a result, the<br />

connection proposal is for a new substation (constructed in or around the Sizewell area) and<br />

connected to the existing Sizewell to Bramford overhead line route that would be a suitable collection<br />

point for the OWF. The extent of these substation works would be driven by land availability and the<br />

requirements of the GB SQSS.<br />

With the levels of OWF assumed in this zone, the increased cable costs associated with extending<br />

further inland to Bramford substation would outweigh the cost of establishing a new substation at<br />

Sizewell, given the cost assumptions used.<br />

The reinforcements required within the East Anglia geographical zone, have been identified at a total<br />

cost of £171m and include a new substation at Bramford (to accommodate the increase in power<br />

flows under system contingencies), a new circuit route from Bramford to Pelham and a new circuit<br />

route from Bramford to Rayleigh via Braintree. The new circuit routes are created by the installation<br />

of a new section of overhead line from Bramford substation to the circuit tee-point near Twinstead<br />

The locations of these potential major reinforcements required against the input assumptions used<br />

are illustrated in green on Figure 22, below.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 64 of 94


Figure 22: Norfolk Zone Local Onshore Transmission Network and Location of Potential Onshore<br />

Transmission Reinforcement<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 65 of 94


6.4.3.2 Zonal Infrastructure Works (with Sizewell C)<br />

The connection of Sizewell C nuclear generation requires the construction of a new 400kV<br />

substation and overhead line reinforcements out of the East Anglia area. This includes those<br />

reinforcements highlighted in Section 6.4.3.1 plus the reconductoring of the existing Rayleigh-<br />

Coryton-Tilbury overhead line route.<br />

Similar to the scenario without the new Sizewell C nuclear plant, the connection of a HVDC converter<br />

at Norwich (1.1GW) substation would necessitate additional switchgear and a substation extension.<br />

The connection of the new Sizewell C plant initiates the construction of a new substation as well as<br />

the substantial transmission system reinforcements highlighted above. Here it is assumed that this<br />

new substation can be extended to enable connection of a single 1.1GW HVDC converter.<br />

The approach towards establishing the overall onshore/offshore optimum network solution for this<br />

generation background was initially to try and minimise onshore reinforcement as much as possible<br />

by cabling offshore in order to reduce the timescales for connection of OWF (given the relative lead<br />

times of onshore vs. offshore transmission build). In taking this approach, the connection of 2.2GW<br />

into Rayleigh, along with the associated local substation work required, was introduced. This solution<br />

is considered optimum for this generation background if it is assumed that the current, approach to<br />

onshore transmission investment continues and that financial commitment is required from<br />

generators in order to invest in the necessary transmission capacity. This solution provides a trade<br />

off between cost and time to delivery if the aforementioned assumption is made.<br />

However, if onshore reinforcement were to begin in advance of financial commitment from users, it<br />

may be possible for a more economic solution to be delivered within the necessary timescales.<br />

There is potential for the total capacity of OWF in the Norfolk zone to connect into the East Anglia<br />

area in addition to Sizewell C nuclear generation, therefore reducing overall offshore cable lengths<br />

and hence costs, if a new OHL route were to be established from Walpole to a new substation on the<br />

Cottam – Eaton Socon line (highlighted in orange on Figure 22) as well as the reinforcements<br />

highlighted above.<br />

One final alternative option investigated, in order to further reduce onshore reinforcement<br />

requirements, was the connection 2.2GW of Norfolk OWF further south into Barking via the river<br />

Thames. The intention with this option was to bring the generation into the onshore transmission<br />

system as close to the demand as possible. Due to the complexity of delivering such a scheme, the<br />

lack of land availability at Barking for siting HVDC converter stations and a significant increase in the<br />

overall cost of this option relative to those proposed, this option was discounted.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 66 of 94


6.5 Hastings<br />

1<br />

Option<br />

0.5GW<br />

AC at<br />

Bolney<br />

OWF<br />

<strong>Offshore</strong><br />

Transmission<br />

£M<br />

Onshore Transmission<br />

Substation<br />

Extension<br />

£M<br />

Network<br />

Reinforcement<br />

£M<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 67 of 94<br />

Total<br />

£M<br />

AA £182m 1.4 0 £184m<br />

6.5.1 <strong>Offshore</strong> connection<br />

Table 16: <strong>Connection</strong> cost for Hastings Zone<br />

Figure 23: Hastings zone connection overview<br />

Comments<br />

This does not<br />

include the cost<br />

of reactive<br />

compensation<br />

equipment<br />

required to meet<br />

reactive<br />

requirements set<br />

out in the SO-TO<br />

code.<br />

Due to the nominal capacity (500MW) of the offshore wind farm (OWF) located in the Hastings zone<br />

and the distance to the potential connection point at Bolney a HVDC connection solution was<br />

discounted for economic reasons. Instead an HVAC solution has been proposed consisting of two


offshore 33/245kV substations interconnected with a single three core 245kV cable, and each with a<br />

single three core 245kV shorelink cable to transmit the power accumulated from the wind farm to a<br />

transition pit located at the landing point onshore. From this transition pit six single core 245kV<br />

cables have been routed to the potential connection point at Bolney 400kV substation. The onshore<br />

cable route follows the road network as much as possible however there are a number of obstacles<br />

that would need to be crossed along the proposed route. The estimated cost for directional drilling<br />

under these obstacles has been included as part of the overall offshore connection cost estimate.<br />

Due to the total HVAC cable length of this connection, reactive compensation is required to maintain<br />

adequate power transfer levels. This reactive compensation has been located both on the offshore<br />

substations and in an onshore substation compound adjacent to Bolney substation along with the<br />

associated switchgear and step up transformers which form part of the offshore transmission assets.<br />

Both the offshore and onshore substations have been designed to comply with the offshore SQSS<br />

proposals (see Section 3.4) and are represented in diagrammatic form in Senergy Econnect drawing<br />

1845 009 (p34). It has been assumed that a two AIS switchbay extension to Bolney 400kV<br />

substation would be required to connect the Hastings OWF.<br />

6.5.2 <strong>Offshore</strong> connection alternatives<br />

Alternative connection points were considered at the existing National Grid 400kV substation at<br />

Ninfield, and at a new substation to be created between Shoreham on Sea and Bolney. The former<br />

option was discounted due to the extended cable route length (and hence cost), while the latter was<br />

discounted because of the cost of the onshore transmission network extension necessary to create<br />

and then connect this new substation (see Section 6.5.3) compared to the cost of taking a cable all<br />

the way to Bolney.<br />

6.5.3 Onshore reinforcement<br />

For connections of the Hastings polygon, extension of the existing onshore 400kV substation at<br />

Bolney is recommended. No further infrastructure costs are incurred against the input assumptions of<br />

the scenario.<br />

Alternative options have considered similar connections to Ninfield, but these were dismissed due to<br />

a significant increase to the offshore transmission costs and minimal change to onshore<br />

requirements.<br />

An alternative option of providing a 400kV OHL from Bolney towards the coast and establishing a<br />

new 400/132kV substation close to the South Downs was considered to reduce the onshore section<br />

of the offshore transmission system (due to the substantial cost of onshore AC cable). This solution<br />

proposed the adoption of a section of existing 132kV OHL and reconstructing it as 400kV. The<br />

increased cost of the new substation and upgrade work was greater than the savings in onshore<br />

transmission cabling cost, and this option was not taken further.<br />

This part of the onshore system is characterised by one 400kV double circuit from Kemsley<br />

substation passing Canterbury North, Sellindge, Dungeness, Ninfield and Bolney before branching<br />

out into further routes at Lovedean. The significance of this solitary double circuit, is that the amount<br />

of generation connecting into this single route is limited by the need to cater for the loss of a double<br />

circuit overhead line route in planning transmission capacity (outlined in the GB SQSS). For the fault<br />

outage of a section of this double circuit route between Kemsley and the new Cleve Hill substation<br />

west of Canterbury North, all the generation connected southwest on this route will accumulate until<br />

it reaches Lovedean before it has further outlets onto the rest of the system. The scenario used for<br />

this study assumes one new 1.6GW nuclear unit at Dungeness. This 1.6GW, coupled with 0.5GW<br />

from the proposed Hasting OWF and a potential further 1.9GW import from the Anglo-French HVDC<br />

link would mean that if a second nuclear unit were to connect at Dungeness, a new 400kV OHL<br />

route would be required out of this region. This region of the system is illustrated in Figure 24, below.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 68 of 94


Figure 24: Hastings Zone Local Onshore Transmission Network<br />

If all currently contracted generators connected to this area of the system were to be considered in<br />

conjunction with the possibility of imports on the Anglo-French link, there would be no spare capacity<br />

on this part of the onshore transmission system. The timescales for connecting a project in this<br />

region would be impacted by those associated with any onshore transmission reinforcement<br />

requirements.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 69 of 94


6.6 West Isle of Wight<br />

1<br />

Option<br />

0.5GW AC<br />

to<br />

substation<br />

at<br />

Chickerell<br />

OWF<br />

<strong>Offshore</strong><br />

Transmission<br />

£M<br />

6.6.1 <strong>Offshore</strong> connection<br />

Onshore Transmission<br />

Substation<br />

Extension<br />

£M<br />

Network<br />

Reinforcemen<br />

t £M<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 70 of 94<br />

Total<br />

£M<br />

DA £160m £15m 0 £175m<br />

Table 17: <strong>Connection</strong> cost for West Isle of Wight Zone<br />

Figure 25: West Isle of Wight zone connection overview<br />

Comments<br />

This does not<br />

include the cost<br />

of reactive<br />

compensation<br />

equipment<br />

required to meet<br />

reactive<br />

requirements set<br />

out in the SO-TO<br />

code.<br />

Due to the nominal capacity (500MW) of the offshore wind farm (OWF) located in the West Isle of<br />

Wight zone and the distance to the potential connection point at Chickerell a HVDC connection<br />

solution was discounted for economic reasons. Instead an HVAC solution has been proposed<br />

consisting of two offshore 33/245kV substations interconnected with a single three core 245kV cable,<br />

and each with a single three core 245kV shorelink cable to transmit the power accumulated from the<br />

wind farm to a transition pit located at the landing point onshore. From this transition pit six single


core 245kV cables have been routed to the potential connection point at Chickerell 400kV<br />

substation. The onshore cable route follows the road network as much as possible however there<br />

are a number of obstacles that would need to be crossed along the proposed route. The estimated<br />

cost for directional drilling under these obstacles has been included as part of the overall offshore<br />

connection cost estimate. Due to the total HVAC cable length of this connection, reactive<br />

compensation is required to maintain adequate power transfer levels. This reactive compensation<br />

has been located both on the offshore substations and in an onshore substation compound adjacent<br />

to Chickerell substation along with the associated switchgear and step up transformers which form<br />

part of the offshore transmission assets. Both the offshore and onshore substations have been<br />

designed to comply with the offshore SQSS proposals (see Section 3.4) and are represented in<br />

diagrammatic form in Senergy Econnect drawing 1845 009 (p34). It has been assumed that a two<br />

GIS switchbay extension to Chickerell 400kV substation would be required to connect the West Isle<br />

of Wight OWF.<br />

6.6.2 <strong>Offshore</strong> connection alternatives<br />

Alternative connection points were considered at the existing National Grid 400kV substation at<br />

Mannington, and at a new substation to be created between Chickerell and Mannington on the<br />

existing 400kV overhead line route, however both these options were discounted due to the<br />

extended cable route length (and hence cost), and the difficult terrain and environmental<br />

designations along the coastline between Weymouth and Bournemouth.<br />

6.6.3 Onshore reinforcement<br />

For connections of the West Isle of Wight wind farm, extension of the existing onshore 400kV<br />

substation at Chickerell is recommended. No further infrastructure costs are incurred against the<br />

input assumptions of the scenario.<br />

An alternative option considered connection to Mannington, but this was dismissed due to a<br />

significant increase in the length of both onshore and offshore cabling required along with the<br />

associated increase in costs and minimal change to onshore transmission network requirements.<br />

The onshore transmission network in this area consists of a 400 kV double circuit transmission line<br />

that runs west from Nursling substation near Southampton, via substations at Mannington (inland<br />

from Bournemouth), Chickerell (Weymouth) and Axminster to Exeter. East of Nursling the line<br />

connects with generation sites at Fawley and Marchwood before branching out into the wider system<br />

at Lovedean substation near Portsmouth. The line route is closest to the coast between Chickerell<br />

and Axminster but otherwise lies several kilometres inland. (Fig 26)<br />

West of Exeter, the line continues to Indian Queens in Cornwall and then approximately follows the<br />

North Cornwall and North Devon coast back to Taunton. There it connects with another overhead<br />

line running directly from Exeter and a single double-circuit line then passes through Somerset to<br />

Hinkley Point and onwards to connect to the wider system at Melksham. (Fig. 26 refers)<br />

The transmission system must be designed and operated as required by the GB SQSS so that the<br />

loss of a section of double circuit line causes no overloading or other unacceptable system<br />

performance. Following such an outage on the line to the east of any wind farm connection, the<br />

power from the wind farm would have to flow west to Exeter and then via Hinkley Point to Melksham.<br />

It would therefore combine with the power from generators at Langage, from any wind farms in the<br />

Bristol Channel and from nuclear generation at Hinkley Point. This combined power flow could be<br />

sufficient to trigger a need for significant reinforcements in this area of the network. The extent and<br />

timing of these reinforcements is subject to the number of nuclear units assumed to be connected at<br />

Hinkley Point, the amount of offshore wind generation expected to be connected into the south west<br />

peninsula and the extent to which wind generation is assumed to share capacity with conventional<br />

generation in this area.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 71 of 94


At the time of writing, 3.3GW of nuclear generation (i.e. 2 x1.65GW units) is contracted to connect at<br />

Hinkley Point in 2016. However 1.512GW of offshore wind generation, not involved in either the<br />

<strong>Round</strong> 1 or <strong>Round</strong> 2 leasing process, is also already contracted to connect at Alverdiscott in 2014. In<br />

combination, this level of generation in this area of the South West would trigger the need for a new<br />

40km overhead line route as well as significant uprating of existing routes<br />

This region of the system is illustrated in Figure 26, below.<br />

Figure 26: West Isle of Wight Zone Local Onshore Transmission Network<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 72 of 94


6.7 Bristol Channel<br />

1<br />

2<br />

3<br />

Option<br />

1.5GW AC<br />

to new<br />

substation<br />

on Torridge<br />

estuary<br />

1.5GW AC<br />

to existing<br />

Alverdiscott<br />

substation<br />

1.1 GW DC<br />

to existing<br />

Alverdiscott<br />

substation<br />

Figure 27: Bristol Channel zone AC connection overview (options 1&2)<br />

OWF<br />

<strong>Offshore</strong><br />

Transmission<br />

£M<br />

Onshore Transmission<br />

Substation<br />

Extension<br />

£M<br />

Network<br />

Reinforcemen<br />

t £M<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 73 of 94<br />

Total<br />

£M<br />

EA £345m £37m £48m £430<br />

EA £404m £34m 0 £438<br />

EA £413m 33 0 £446<br />

Table 18: <strong>Connection</strong> cost for Bristol Channel Zone<br />

Comments<br />

- new substation<br />

- new DNO<br />

supply<br />

- Alverdiscott<br />

double busbar<br />

- Alverdiscott<br />

double busbar<br />

- no MITS<br />

without new<br />

nuclear at Hinkley<br />

- Alverdiscott<br />

double busbar<br />

- no MITS<br />

without new<br />

nuclear at Hinkley


6.7.1 <strong>Offshore</strong> connection<br />

Figure 28: Bristol Channel zone DC connection overview (option 3)<br />

The connection of the Bristol Channel zone OWF presents a number of options. The nominal<br />

capacity of this zone (1.5GW) exceeds the nominal capacity of a single HVDC VSC converter<br />

pair/bipole (1100MVA) while for an HVAC connection five 245kV three core subsea cables are<br />

required to transmit this power output ashore. The accumulation of 1.5GW from the wind farm array<br />

itself also requires an additional 33/245kV offshore substation to be installed with the wind farm<br />

effectively split into three sections. In addition there are two possible connection points onshore, the<br />

existing National Grid 400kV substation at Alverdiscott, and a potential new 400kV substation to be<br />

established on the bank of the Torridge estuary.<br />

Option 1 in Table18 considers an HVAC connection for the full 1.5GW to this new substation.<br />

<strong>Offshore</strong> the OWF connection designs are based on three 33/245kV offshore substations each<br />

consisting of three 160MVA 33/245kV transformers with associated GIS switchgear. From the<br />

Northern offshore substation, one 245kV three core cable is routed directly to the landing point on<br />

the Torridge estuary, while the other 245kV three core cable is connected to the 245kV busbar at the<br />

Western offshore substation. The Western and Eastern offshore substations both have a further two<br />

245kV three core cables connecting them directly to the landing point on the Torridge estuary,<br />

providing a total of five shorelink HVAC cables and one platform HVAC interconnection cable<br />

(between the Northern and Western substations). These cables are then routed to a 245kV busbar in<br />

a compound adjacent to the new National Grid substation, the voltage is then stepped up to 400kV<br />

via two 750MVA transformers for input into the National Grid via two GIS 400kV double busbar<br />

switchbays. As this new substation could potentially be on or very close to the bank of the estuary no<br />

transition to single core underground cables has been deemed necessary.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 74 of 94


Option 2 considers the same HVAC design offshore but this time with the existing substation at<br />

Alverdiscott as the connection point, which extends the offshore cable route length and also requires<br />

transition to fifteen separate 245kV single core underground cables for the 5km of onshore route<br />

between the landfall point and Alverdiscott substation.<br />

Option 3 considers the HVDC VSC option and follows the same design as used for the Dogger Bank,<br />

Hornsea, and Norfolk zones. As a result the installed capacity of the wind farm has been dropped<br />

from 1.5GW to just over 1.2GW (which also means only two 33/245kV offshore substations are<br />

required) to allow one 1110MVA HVDC VSC converter pair/bipole to be utilised.<br />

6.7.2 <strong>Offshore</strong> connection alternatives<br />

Option 4 shown in table 19 provides the alternative HVDC solution which utilises the extra power<br />

transfer capacity of a CSC converter pair/bipole link to transmit the full 1.5GW from the Bristol<br />

Channel zone. <strong>Offshore</strong> this solution required the three 33/245kV offshore substations of option 1 but<br />

here the exporting 245kV cables are connected to a 245kV busbar on the offshore CSC HVDC<br />

converter platform with the power being transmitted through a pair of HVDC Mass Impregnated<br />

cables with integrated return conductor (which has the advantage of allowing for 50% operation for<br />

the loss of one cable) to an identical CSC converter onshore in a compound adjacent to Alverdiscott<br />

substation where the power is converted back into AC for input into the National Grid through two<br />

400kV AIS double busbar switchbays. The onshore impact of this alternative solution has not been<br />

investigated in detail.<br />

4<br />

Option<br />

1.5 GW to existing<br />

Alverdiscott substation<br />

utilising CSC HVDC<br />

OWF<br />

6.7.3 Onshore reinforcement<br />

<strong>Connection</strong><br />

Substation<br />

<strong>Offshore</strong> Transmission<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 75 of 94<br />

Cost<br />

£M<br />

Cost<br />

per MW<br />

£k<br />

EA Alverdiscott £590m £393k<br />

Table 19: Alternative connection costs for Bristol Channel Zone<br />

Cost per MW<br />

comparison<br />

£<br />

1.5GW (AC) to<br />

Alverdiscott<br />

£292k<br />

For either of the AC or DC offshore connection options a new 400kV substation is to be added at the<br />

existing Alverdiscott 400/132kV substation site. Currently the 400kV equipment is simply Teeconnected<br />

to the overhead line route, but a full double busbar 400kV substation will be required for<br />

the connection of 1.5GW.<br />

With the AC connection, an option is to seek to construct a new 400kV overhead line from<br />

Alverdiscott towards the coast. This would effectively replace an existing 132kV line over this portion<br />

of the route and create a new connection point for the wind farm with a new 400/132kV substation.<br />

This additional network extension is estimated at £48m.<br />

The generation scenario described in Section 5.2 assumes the closure of Hinkley Point B (1.26 GW)<br />

and the commissioning of one 1.6 GW European Pressurised Water Reactor (EPR) at Hinkley Point<br />

in the timescales considered. As explained in Section 6.6.3, all generation developments in the<br />

South West interact and, in combination, may drive a need for reinforcement. If a further 1.6 GW unit<br />

were to materialise at Hinkley Point, major reinforcement would be required. This could potentially<br />

include the need for a 40 km overhead line route as well as significant uprating of existing routes.


At the time of writing, 3.3GW of nuclear generation (i.e. 2 x1.65GW units) is contracted to connect at<br />

Hinkley Point in 2016. However 1.512GW of offshore wind generation, not involved in either the<br />

<strong>Round</strong> 1 or <strong>Round</strong> 2 leasing process, is also already contracted to connect at Alverdiscott in 2014<br />

This region of the system is illustrated in Figure 29, below.<br />

Figure 29: Bristol Channel Zone DC Local Onshore Transmission Network<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 76 of 94


6.8 Irish Sea<br />

1<br />

2<br />

Option<br />

1.1GW<br />

at Wylfa<br />

2.2GW<br />

at<br />

Deeside<br />

1.1GW<br />

at<br />

Stanah<br />

1.1GW<br />

at Wylfa<br />

2.2GW<br />

at Pentir<br />

1.1GW<br />

at<br />

Stanah<br />

OWF<br />

<strong>Offshore</strong> Transmission £M<br />

<strong>Connection</strong><br />

Substation<br />

IA Deeside<br />

Cost<br />

£M<br />

£416m<br />

(DC)<br />

LA Deeside £420m<br />

Onshore Transmission<br />

Substation Extension £M<br />

Network Reinforcement £M<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 77 of 94<br />

£86m<br />

JA Wylfa £266m (AC) £7m<br />

NA Stanah £407m £30m<br />

IA<br />

LA<br />

JA<br />

NA<br />

Pentir £379m (AC)<br />

Pentir<br />

Wylfa<br />

Stanah<br />

6.8.1 <strong>Offshore</strong> connection<br />

£401m<br />

(DC)<br />

£266m<br />

(AC)<br />

£6m<br />

£7m<br />

£407m £30m<br />

Table 20: <strong>Connection</strong> cost for Irish Sea Zone<br />

Total<br />

£M<br />

£0m £1,632<br />

£186m £1,682<br />

Comments<br />

Possible land<br />

restrictions at<br />

Deeside if CSC-<br />

HVDC link is<br />

used for<br />

Hunterston to<br />

Deeside Link.<br />

The<br />

establishment of<br />

a second circuit<br />

on the existing<br />

route from Pentir<br />

to Trawsfynydd<br />

would be<br />

required to<br />

deliver this<br />

option.<br />

Again due to the proximity of the OWF IA and JA in the Irish Sea zone to their potential respective<br />

connection points at Pentir and Wylfa, cost estimates for both an HVAC and HVDC solution were<br />

derived. However due to their distance offshore, AC solutions for OWF LA and NA were not deemed<br />

pragmatic and hence only HVDC connection solutions have been assessed for these two wind<br />

farms.


Figure 30: Irish Sea zone connection overview<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 78 of 94


The HVDC and HVAC connection designs for these wind farms are the same as those discussed in<br />

the previous sections (and shown diagrammatically in Senergy Econnect drawings 1845-010 (p35)<br />

and 1845-011 (p36)) and hence are not re-iterated here. The options for connecting wind farm IA to<br />

either the existing National Grid 400kV substation at Pentir or via a longer route to the existing<br />

National Grid 400kV substation at Deeside has been shown due to the impact of each connection on<br />

the wider onshore transmission reinforcements required. The respective reinforcements are<br />

discussed in more detail in Section 6.8.3.<br />

6.8.2 <strong>Offshore</strong> connection alternatives<br />

With the relatively short cable distances between OWF IA and the substation at Pentir, and OWF JA<br />

and the substation at Wylfa, it is the HVDC solutions for these wind farms that are more expensive<br />

than the HVAC alternatives, again due to the cost of providing the HVDC converters, and associated<br />

extra platform and switchgear. However for the connection of OWF LA (option 5) the longer cable<br />

route length makes the HVDC solution more cost effective.<br />

Option 6 looks at the use of HVDC CSC technology to transmit the power generated in polygon IA,<br />

expanded to an installed capacity of 1680MW to the connection substation at Deeside. The design<br />

would follow the same principles as that discussed for the Bristol Channel zone option 4 in Section<br />

6.7.2.<br />

3<br />

4<br />

5<br />

6<br />

Option<br />

OWF IA connected to Pentir<br />

using HVDC VSC<br />

OWF JA connected to<br />

Wylfa using HVDC VSC<br />

OWF LA connected to<br />

Pentir using HVAC<br />

OWF IA enlarged to<br />

1680MW installed and<br />

connected via HVDC CSC<br />

to Deeside<br />

OWF<br />

<strong>Connection</strong><br />

Substation<br />

<strong>Offshore</strong> Transmission<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 79 of 94<br />

Cost<br />

£M<br />

Cost<br />

per MW<br />

£k<br />

IA (DC) Pentir £395m £319k<br />

JA (DC) Wylfa £354m £286k<br />

LA (AC) Pentir £454m £366k<br />

IA<br />

Deeside<br />

£723m £430k<br />

Table 21: Alternative connection costs for Irish Sea Zone<br />

Cost per MW<br />

comparison<br />

£<br />

IA (AC) to<br />

Pentir<br />

£306k<br />

JA (AC) Wylfa<br />

£215k<br />

LA (DC) Pentir<br />

£323k<br />

IA (DC)<br />

Deeside<br />

£336k


6.8.3 Onshore reinforcement<br />

For the Irish Sea zone, connections to the onshore transmission system were considered in the<br />

North Mersey area to the existing substations of Heysham and Stanah for a total of 1.1GW. Due to<br />

severe land restrictions at Heysham and similar offshore cable lengths for both, Stanah was<br />

considered to be the best interface point with the onshore transmission system. The standard<br />

substation extensions associated switchgear will be required at Stanah in order to provide the<br />

interface with the offshore network.<br />

Due to the location of the wind farms and zone polygons, it was most economic to connect the<br />

remaining 3.3GW into the North Wales area. <strong>Connection</strong> into the existing substations at Wylfa, Pentir<br />

and Deeside were considered.<br />

The optimum solution for the Irish Sea OWF connecting into North Wales is also influenced by the<br />

possibility of undertaking onshore transmission reinforcement in advance of financial commitment<br />

from users being in place to do so.<br />

The limiting section of the network in this region is the single circuit between Pentir and Trawsfynydd<br />

substations. The scenario analysed assumes that the existing nuclear generator at Wylfa is closed<br />

and that no new nuclear is connected in the timescales considered. Should nuclear replanting occur<br />

at Wylfa, there is a definite need to reinforce this section of the network with a second circuit along<br />

the existing route.<br />

From an offshore transmission system perspective, the most economic solution is the connection of<br />

the entire 3.3GW of Irish Sea OWF into Wylfa and Pentir. An alternative solution, in order to avoid<br />

significant onshore reinforcement is to still connect 1.1GW into Wylfa, but to take the remaining<br />

2.2GW into Deeside. There is a risk with this solution that sufficient land may not be available at<br />

Deeside, as these connections would interact with the potential development of an HVDC link from<br />

Hunterston into Deeside, which could be either a CSC or VSC HVDC link depending on the<br />

requirements identified.<br />

Therefore, if onshore reinforcement of the Pentir – Trawsfynydd route (highlighted in green on Figure<br />

26.1) was undertaken strategically, in advance of connections coming forward, this would help in<br />

connecting both offshore wind and/or any nuclear generation in this region. This solution has the<br />

potential to reduce the cost of the offshore network.<br />

This region of the system is illustrated in Figure 31, below.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 80 of 94


Figure 31: Irish Sea Zone Local Onshore Transmission Network and Location of Potential Onshore<br />

Transmission Reinforcement<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 81 of 94


7 Delivery Issues<br />

7.1 <strong>Offshore</strong> Installation & Manufacturing resource<br />

From the connection designs presented in the earlier sections of this report it is apparent that<br />

significant quantities of HVAC and HVDC equipment will be required to complete the connection of<br />

the <strong>Round</strong> 3 offshore wind farms. Senergy Econnect is aware of anecdotal evidence of problems<br />

being faced by developers currently in sourcing major items of plant including wind turbines,<br />

transformers, switchgear and cables, and hence development of the <strong>Round</strong> 3 projects may well be<br />

constrained by the ability of developers to procure (and manufacturers to provide) the physical<br />

assets required to create their wind farms. The installed capacity and timetable proposed for <strong>Round</strong><br />

3 may also make the availability of offshore installation vessels a potential bottleneck in the<br />

construction phase.<br />

This section of the report investigates these issues in more detail. Specifically, it reviews the latest<br />

industry major publication assessing supply chain issues and documents the outcomes of<br />

communications with major suppliers in order to arrive at a more thorough assessment of supply<br />

chain issues facing the development of offshore wind projects.<br />

The suite of documentation supporting the Government UK Renewable Energy Strategy<br />

Consultation document [20], and the BERR Publication, “Quantification of Constraints on the Growth<br />

of UK Renewable Generating Capacity”, Sinclair Knight Merz, June 2008 (The BERR Report) [18]<br />

has been used in this assessment.<br />

7.1.1 HVAC and HVDC subsea cables<br />

The supply chain associated with high voltage alternating current (HVAC) and high voltage direct<br />

current (HVDC) subsea cables is a significant constraint to growth. HVAC and HVDC cables are<br />

required to connect offshore wind farms to the onshore electricity infrastructure.<br />

From the analysis undertaken in this report, Senergy Econnect estimate that about 1200km of HVAC<br />

three core and single core cable and 5,200km of HVDC underground / subsea cable will be required<br />

for <strong>Round</strong> 3 projects. The UK does not have a high voltage subsea cable manufacturing capability<br />

and there are only three suppliers of HVAC and HVDC subsea cables in Europe (i.e. ABB, Nexans<br />

and Prysmian) with lead times of between two and three years depending on the type of cable<br />

required.<br />

The technology associated with the manufacture of high voltage cable is vested with the existing<br />

cable suppliers and it is unlikely that a new entrant could get the product to market within several<br />

years, if at all, because of the research needed to overcome the technological barriers. Accordingly if<br />

high voltage subsea cables are to be manufactured in the UK it will be necessary to encourage one<br />

or more of the existing European suppliers to set up a manufacturing facility in the UK at a suitable<br />

port location to facilitate loading onto specialist cable laying vessels. Setting up such a facility is<br />

estimated to cost about £35 million and would take about three years [18] to reach production.<br />

Senergy Econnect are aware that the lead times in HV cables has increased to 18 -24 months over<br />

the past year due to the large demand from other sectors such as utility infrastructure, and oil and<br />

gas.<br />

However a number of existing suppliers do see the future potential capacity requirements of the<br />

offshore wind as well as other sectors and have firm plans to increase their capacity through<br />

investment in facilities, although the delay from investment to first supply from new production lines is<br />

of the order of two years.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 82 of 94


7.1.2 HVDC converter equipment<br />

Although not presently a supply chain constraint, the demand for HVDC converter equipment that will<br />

be needed to connect offshore wind farms located more than 60km from the onshore connection<br />

point is likely to increase significantly as the more distant offshore wind farm sites are developed in<br />

the North Sea. It will be at least five years before these distant sites are constructed, therefore as<br />

these projects become committed the HVDC converter suppliers are confident that there is sufficient<br />

time to increase manufacturing capacity to meet demand if they have sufficient assurance that these<br />

projects will go ahead. However Senergy Econnect have anecdotal evidence that one manufacturer<br />

is revising downwards their short to medium term forecasts for supplying the offshore market in the<br />

UK because of the delays in progressing offshore projects through the GB planning, consenting, and<br />

regulatory process .<br />

With each HVDC VSC converter taking approximately nine months to manufacture, a number of<br />

converters would have to be manufactured concurrently in order to meet the timetable for <strong>Round</strong> 3<br />

assuming all the zones are developed simultaneously. It should be noted that the offshore<br />

programmes of other countries and an increase in HVDC projects around the world will coincide with<br />

the <strong>Round</strong> 3 build programme, and hence <strong>Round</strong> 3 developers or their <strong>Offshore</strong> Transmission<br />

Owners may potentially need to commit to production slots up to three or more years in advance to<br />

avoid the converters becoming a constraint. In order for the HVDC suppliers to have the confidence<br />

to increase their manufacturing capability, they will require an order book to be in place, which in turn<br />

means that the <strong>Offshore</strong> Transmission Owner regime needs to ensure that procurement of<br />

equipment is triggered as early as possible in the process so that these lead times can be managed<br />

and reduced.<br />

7.1.3 Balance of plant equipment (e.g. transformers, switchgear, etc)<br />

Although there are significantly more suppliers of balance of plant equipment than HV cable<br />

suppliers, the worldwide demand for this type of equipment is forcing up prices and prolonging<br />

delivery times. The lead time for transformers, a key long-lead element of the offshore substations,<br />

has increased to around 36 months over the past year. Currently the lead time for switchgear can<br />

take up to 12 months for switchgear rated at 132kV and above and up to six months for switchgear<br />

rated at 33kV and below.<br />

In reality the lead time from placement of order on an offshore project to energisation of the on and<br />

offshore substations is in the order of three years, once the preparatory design work, installation and<br />

commissioning is taken into account.<br />

7.1.4 Assessment of the availability and cost of cable installation vessels<br />

The view from suppliers is that they can meet the near-term capacity requirements and although it<br />

will take significant investment, they can increase capacity fairly quickly to meet future requirements,<br />

and there is a willingness to do so within the right frameworks. With a global pool of more than<br />

twenty suitable vessels, cable installation is not expected by those involved to present a bottleneck.<br />

Installation vessel availability is a significant issue but generally higher cost solutions are likely to<br />

remain available, though this may price some projects out of the market. The following Table<br />

illustrates the cost, capability and availability of the vessels owned and operated by one cable laying<br />

company: -<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 83 of 94


Item Capability<br />

Number of Vessels Seven under ownership at various locations<br />

worldwide<br />

Number of vessels allocated specifically for offshore<br />

wind industry<br />

Three to Four vessels<br />

Typical lead time Two to three months<br />

Cost<br />

132kV cable laying @£80k /day<br />

5km per day ploughing typical<br />

33kV cable laying @£60k per day<br />

Vessel Operating limits 1.25 – 1.5m height of swell<br />

12m/s wind speed<br />

7+sec swell period<br />

Table 22: Cable Installation Vessel parameters<br />

(Courtesy of Global Marine Systems)<br />

7.2 Onshore transmission network delivery programme<br />

To construct the onshore transmission system proposed in this study under the present regulatory<br />

regime National Grid would require to receive applications for connections for each of the zones that<br />

sought connection capacity for the total capacity of that zone.<br />

It has been assumed that the new Planning Act would apply to the overhead line works required.<br />

Under this regime, for moderate overhead line works the minimum timescale that is envisaged to<br />

undertake the required studies, environmental impact assessments and obtain consent is<br />

approximately four years from approval to commence work. Following this period it is necessary to<br />

add the time required to enter into commitment to obtain the required materials, undertake the<br />

installation activities then obtain system access to commence the connection process. This leads to<br />

an overall time period from approval to connection of around seven years. Where new transmission<br />

transformers are required, allowance has to be made for delivery periods for these, which are<br />

presently around 36 months.<br />

Where new 400kV overhead lines are required, particularly reasonably long routes, then the time<br />

periods to undertake the required assessments, consultation and consenting process may take<br />

considerably longer<br />

Obtaining access to the system to undertake the required connections (i.e. taking outages of<br />

equipment) will have to compete with other demands such as maintenance and outages to<br />

undertake works for other users, and commitments. With the level of uncertainty around which year<br />

connections will be undertaken arising from the issues above, it is not possible to accurately identify<br />

if system access constraints would seriously impact on the delivery programme. As National Grid<br />

presently has commitments to provide connections for users that are not present in the study<br />

background the existing system access plans do not provide a reliable basis to work against. It is<br />

however, reasonable to assume for the east coast connections particularly, that available system<br />

access will be a major constraint on the ability to deliver the required work. Any location that has<br />

programmes of delivery that approach those for new Nuclear or other generation connections will<br />

also face system access competition. If reinforcement was able to take place before financial<br />

commitment from users is in place, it may be possible to optimise the system outages required and<br />

spread these out over a longer time period.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 84 of 94


8 Conclusions<br />

8.1 Methodology and Assumptions<br />

The aim of this study was to identify the extent and costs of the works necessary to provide<br />

optimised transmission connections for all of the <strong>Round</strong> 3 offshore polygons. The methodology and<br />

assumptions used to assess the required works are set out in Sections 2 and 3.<br />

Key among these assumptions is the view that the offshore transmission assets should be designed<br />

to achieve a high utilisation, both to optimise the capital investment and also demonstrate an<br />

economic and efficient solution to the regulator. Such a consideration will be likely to form part of<br />

Ofgem’s decision making criteria in the granting of an offshore transmission licence.<br />

Factors such as the variability of the wind resource and the operational availability of offshore wind<br />

turbines dictate that the <strong>Round</strong> 3 wind farms will rarely be generating to the full extent of their<br />

installed capacity, which would adversely impact the utilisation of a connection solution that was<br />

rated to transmit total installed capacity. In light of these considerations a high level analysis was<br />

therefore undertaken to ascertain the optimal ratio between the installed generating capacity offshore<br />

and the transmission capacity of the offshore transmission assets. This optimal utilisation ratio (given<br />

by the formula below) was determined to be 112% (see Appendix 1): -<br />

Utilisation ratio = <strong>Offshore</strong> transmission asset capacity<br />

Installed generating capacity<br />

In practice the offshore transmission asset designs provided in this report have a range of utilisation<br />

ratios from 81% to 112% because of the zonal capacities identified by The Crown Estate and the<br />

modular nature of the transmission assets themselves (with each additional cable providing a fixed<br />

increase in transmission capacity). National Grid are in the process of leading a review of the<br />

security standards for offshore generation connections to include projects of the size and distance<br />

form shore associated with <strong>Round</strong> 3, at the request of Ofgem. This review will culminate in a set of<br />

security recommendations including offshore transmission circuit capacity, which will be consulted<br />

upon and incorporated as revised text in the GB SQSS.<br />

8.2 Cost of Connecting <strong>Round</strong> 3 <strong>Offshore</strong> <strong>Wind</strong> <strong>Farm</strong>s<br />

A summary of the optimal connection costs broken down by zone is set out in Table22 below.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 85 of 94


ZONE OWF<br />

Total<br />

Installed<br />

Capacity<br />

(MW)<br />

<strong>Connection</strong><br />

technologies<br />

Moray Firth C 500MW AC<br />

<strong>Connection</strong><br />

Point (s)<br />

New substation<br />

on coast<br />

TOTAL<br />

COST (£m)<br />

TOTAL<br />

COST<br />

Per MW<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 86 of 94<br />

(£k)<br />

£193m* £386k<br />

Firth of Forth G 500MW AC Torness £150m* £300k<br />

Dogger Bank<br />

Hornsea<br />

Norfolk<br />

(without<br />

Sizewell C)<br />

H1 1237.5MW DC Creyke Beck<br />

H3 1237.5MW DC Creyke Beck<br />

J 1240MW DC Creyke Beck<br />

H2 1237.5MW DC Keadby<br />

H4 1237.5MW DC Keadby<br />

H5 1237.5MW DC Killingholme<br />

I1 1240MW DC Killingholme<br />

I2 1240MW DC Killingholme<br />

M 1237.5MW DC New substation<br />

on Lincolnshire<br />

coast<br />

N 1240MW DC New substation<br />

on Lincolnshire<br />

coast<br />

T 1240MW AC Sizewell<br />

Z2 1240MW DC Sizewell<br />

U 1237.5MW DC Norwich<br />

Z1 1237.5MW DC Norwich<br />

£5,910m £477k<br />

£1,728m £349k<br />

Hastings AA 500MW AC Bolney £184m £368k<br />

West Isle of<br />

Wight<br />

Bristol<br />

Channel<br />

Irish Sea<br />

DA 500MW AC Chickerell £175m £350k<br />

EA 1500MW AC New substation<br />

on Torridge<br />

Estuary<br />

IA 1237.5MW DC Deeside<br />

LA 1240MW DC Deeside<br />

JA 1237.5MW AC Wylfa<br />

NA 1240MW DC Stanah<br />

£430m £287k<br />

£1,632m £329k<br />

TOTALS 25,795MW £10,402m £403k<br />

Table 23: Optimal <strong>Connection</strong> Costs broken down by Zone<br />

*Total reinforcement costs dependent on GB transmission owner study currently in progress<br />

The total cost for connecting the <strong>Round</strong> 3 wind farm projects, assuming no inclusion of Sizewell C,<br />

and the optimal design solutions identified in this report is £10,402 million. Note that this Figure is<br />

based on 2008 price levels for the equipment required and does not allow for the additional


equipment such as Static Var Compensation that may need to be installed at the onshore connection<br />

point of the HVAC connection solutions in order for the <strong>Offshore</strong> Transmission Owners to meet the<br />

reactive capability requirement of the System Operator/Transmission Owner code (e.g. an SVC<br />

sufficient to provide dynamic reactive capability for a 300MW wind farm would cost in the order of<br />

£12m) . Sensitivities were also investigated in some areas where new nuclear developments could<br />

occur in the same region and within the same timescales as the <strong>Round</strong> 3 development. If<br />

transmission reinforcement was not undertaken in an optimised manner on a strategic basis then<br />

offshore transmission asset costs could increase as a result of having to find alternative more distant<br />

connection points. An example of this is the Norfolk zone where the inclusion of Sizewell C increases<br />

the offshore transmission asset cost by £245m. As a function of these designs, the total installed<br />

generating capacity connected for <strong>Round</strong> 3 is 25,295MW (with a connection capacity of 22,980MW)<br />

with a £/MW cost ranging from £287k to £477k.<br />

8.3 Individual Versus Aggregated <strong>Connection</strong>s<br />

The power transfer capabilities of the HVAC and HVDC technologies available coupled with the<br />

potential installed capacity of the <strong>Round</strong> 3 OWF have to a large part dictated the offshore<br />

transmission designs presented in this report and have determined that in the primary solution each<br />

OWF is connected directly to an onshore connection point, with no interconnection between the<br />

OWF in a particular zone.<br />

The economies of using either HVAC or HVDC for these offshore transmission solutions have been<br />

further explored within the report. Applying an HVAC and HVDC solution to the same OWF has<br />

indicated that the choice of technologies used for the offshore transmission designs will be dictated<br />

by the transmission distance and that the cable route length at which HVDC Voltage Source<br />

Converter solutions become economic relative to an equivalent HVAC solution is between 60km and<br />

80km.<br />

Aggregated solutions, where multiple OWF are connected using ‘power corridor’ technologies such<br />

as Gas Insulated Lines and HVDC Current Source Converters have been considered and costed,<br />

although these solutions do not compare favourably with the individual offshore transmission designs<br />

for the same OWFs in terms of cost per MW installed, except where solutions have been considered<br />

that utilise dual bipole HVDC overhead lines as opposed to underground cable to traverse the long<br />

distance overland routes from the coast to Norwich and Drax substations. Such designs also do not<br />

necessarily permit the connection of higher levels of generating capacity relative to the approach of<br />

allocating a dedicated connection per wind farm.<br />

This is not to say that consideration of aggregated connections should not pursued further as there<br />

are likely to be benefits associated with this approach that are not considered in this report, for<br />

example there will be environmental and planning benefits of consenting a single connection cable<br />

route compared to multiple cable routes. However, it would indicate that, in terms of the physical<br />

plant required to connect the <strong>Round</strong> 3 wind farms alone, there would appear to be little to be gained<br />

by aggregating these OWFs through single connections. The option of connecting the <strong>Round</strong> 3 wind<br />

farms to continental Europe has not been considered within this report, however such connections<br />

would face the same power transfer capacity constraints highlighted in Section 6.2.2.<br />

8.4 Deliverability of <strong>Round</strong> 3 <strong>Connection</strong>s<br />

<strong>Offshore</strong> infrastructure projects on the scale considered within this report would set a global<br />

precedent, with unparalleled volumes of offshore HVAC and HVDC plant required to facilitate the<br />

connections. The challenges posed in delivering the <strong>Round</strong> 3 offshore connections, regardless of the<br />

design pursued, will therefore be significant. Investment will be required by existing suppliers in<br />

expanding manufacturing facilities for HV cables, and in particular subsea cables. The HVDC VSC<br />

market is still at an embryonic stage, with the converter/bipole ratings used in this report yet to be<br />

deployed in the field. Hence there will be a technology risk as well as cost premium to be borne by<br />

the ‘first comer’ offshore transmission owner to specify this technology.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 87 of 94


Again it is likely that manufacturing facilities would need to be expanded to accommodate demand<br />

for these technologies should <strong>Round</strong> 3 be developed in the timescales desired. Assuming the supply<br />

chain can be sufficiently stimulated; prices should drop as competition increases and with economies<br />

of scale. The HVDC converter manufacturers are confident that they can increase manufacturing<br />

capability to meet demand should they have sufficient assurance that projects will place orders.<br />

However Senergy Econnect have anecdotal evidence that one manufacturer is revising downwards<br />

their short to medium term forecasts for supplying the offshore market in the UK because of the<br />

delays in progressing offshore projects through the GB planning, consenting, and regulatory process,<br />

and the ability of the process to deliver the offshore wind farm capacity in the timescales desired.<br />

It should be noted that the offshore programmes of other countries and an increase in HVDC<br />

projects around the world will coincide with the <strong>Round</strong> 3 build programme, and hence <strong>Round</strong> 3<br />

developers or their <strong>Offshore</strong> Transmission Owners may potentially need to commit to production<br />

slots up to three or more years in advance to avoid the HVDC converters becoming a constraint.<br />

In order for the HVDC suppliers to have the confidence to increase their manufacturing capability,<br />

they will require an order book to be in place, which in turn means that the <strong>Offshore</strong> Transmission<br />

Owner regime needs to ensure that the procurement of equipment is triggered as early as possible in<br />

the process so that these lead times can be managed and reduced.<br />

Suppliers of the installation vessels necessary to install the cables and offshore platforms are<br />

currently confident in their ability to quickly ramp up capacity to meet the demands of <strong>Round</strong> 3,<br />

although they acknowledge that to make the investment required in the timescales necessary they<br />

will need the security of retainer agreements or firm orders in place.<br />

An offshore infrastructure program on this scale may present significant commercial opportunity for<br />

UK plc in the medium to long term, however it would also present significant development cost in the<br />

short term. Such development costs are likely to be exacerbated by the shortage of engineering skills<br />

within the UK as identified in the BERR report [18].<br />

Establishing the large new compounds onshore to accommodate assets such as the multiple HVDC<br />

converter stations, extending National Grid’s existing substations and creating the new substations<br />

and overhead line routes necessary to integrate <strong>Round</strong> 3 into the existing onshore transmission<br />

network will all require an efficient transition through the planning process if the desired timescales<br />

are to be achieved. The passing into law of the recent planning bill which is the first step in the<br />

creation of an Infrastructure Planning Commission to determine nationally significant projects should<br />

therefore be welcomed.<br />

8.5 Benefits of a co-ordinated approach<br />

The design and costing process has considered a “total solution” capable of handling the entire 25<br />

GW of <strong>Round</strong> 3 offshore wind. This assumes that the collective requirements for all the wind farms in<br />

a zone are required and that the overall onshore transmission system changes will all occur in a<br />

coordinated manner at any one location. Should piecemeal developments be undertaken, wind farmby-wind<br />

farm, and/or wind generation capacity change incrementally over a period of years, the<br />

staggered timing of the works would result in multiple site/circuit extensions and this will increase the<br />

overall onshore costs and environmental impact. In order to avoid this extensive stakeholder<br />

engagement, coordination and collaboration is required.<br />

By considering the connection requirements of zones as a whole, and by balancing the requirements<br />

and crucially the costs of the offshore and onshore transmission assets, this report has sought to<br />

indicate the optimal solutions for the connection of the <strong>Round</strong> 3 OWF projects, from an impartial<br />

perspective. While individual OWF or even individual zones may be able to achieve a more<br />

economically favourable connection in isolation, such an approach may lead to additional cost and/or<br />

additional delays in the connection of <strong>Round</strong> 3 as a whole.<br />

To mitigate this, the ongoing development of the offshore transmission regulatory regime should<br />

carefully consider how the connection application process will work in practice to provide the co-<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 88 of 94


ordination necessary to deliver the optimum solution. Detailed investigations should also be<br />

undertaken into ‘no-regret’ onshore transmission reinforcements that can be taken forward<br />

immediately to deliver the network capacity required.<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 89 of 94


9 Recommendations<br />

This report has identified the optimum outline connection designs in light of target generating<br />

capacities and high level environmental constraints. This report has also identified some of the likely<br />

challenges to be overcome in delivering the <strong>Round</strong> 3 connection designs. In order to further explore<br />

the feasibility, costs and environmental issues surrounding <strong>Round</strong> 3 it is recommended that further<br />

more detailed investigations be carried out into;<br />

• The environmental and planning constraints that may affect connection solutions for each<br />

zone<br />

• The extent of constraints on supply chain that may impact delivery of the <strong>Round</strong> 3<br />

connections<br />

• Raising the power transfer capacity of the HVAC and HVDC technologies to improve<br />

economies of scale<br />

• Putting in place a process to effectively manage the <strong>Round</strong> 3 grid connection applications<br />

and coordinate the on and offshore transmission works<br />

• ‘No regret’ onshore reinforcement options that can be progressed immediately to provide the<br />

necessary transmission capacity in a timely manner<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 90 of 94


10 References<br />

1. East Coast Transmission Network, Technical Feasibility Study, Project 1845 v1.0 dated<br />

March 2007.<br />

2. www.windpower.org Danish <strong>Wind</strong> Industry Association 2003<br />

3. "Rating cables in J-Tubes" by M. Coates of Engineering Materials Division, Era<br />

Technology Ltd<br />

4. Table 41 Attachment to XLPE Cable systems – User’s Guide ABB<br />

5. Gas Insulated Lines –reliable power transmission towards new worldwide challenges in<br />

hydro and wind power generation H.Koch, D.Kunze, S.Pohler, L.Hofmann, C.Rathke,<br />

A.Mueller, CIGRE study committee B3, 2008 session<br />

6. GIL – Gas Insulated Transmission Line reference list - Siemens Power Transmission &<br />

Distribution (28/05/08).<br />

7. Superconductor Power Cables – American Superconductor 2008<br />

8. Cost benefit methodology for optimal design of offshore transmission systems, P. Djapic,<br />

G Strabac, SEDG July 2008<br />

9. Report on the recommendations arising from additional cost benefit analysis<br />

10. http://eosweb.larc.nasa.gov NASA atmospheric science and data center, surface<br />

meteorology and solar energy tables for Latitude 55 0 Longitude 2 0<br />

11. North Hoyle <strong>Offshore</strong> <strong>Wind</strong> farm annual report, URN no. 08/P47 BERR<br />

12. GB Security and Quality of Supply Standard<br />

13. Terms of Reference for GB Security and Quality of Supply Standard Review Group: via<br />

National Grid Electricity website: http://www.nationalgrid.com/NR/rdonlyres/67B20E95-61EF-<br />

4532-8557-659F7CD6D12A/15792/120207GBSQSSReviewGroupToR_FINAL_.pdf<br />

14. GB Seven Year Statement 2008, Chapter 7: GB Transmission System Performance –<br />

Modelling of the Planned Transfer Condition<br />

15. http://www.nationalgrid.com/uk/Electricity/Codes/gbsqsscode/reviews/<br />

Review GSR001<br />

GB SQSS<br />

16. http://www.ofgem.gov.uk/Networks/Trans/<strong>Offshore</strong>/ConsultationDecisionsResponses/Pag<br />

es/ConsultationDecisionsResponses.aspx<br />

Joint Ofgem/BERR Regulatory Policy Update<br />

<strong>Offshore</strong> Electricity Transmission – A<br />

17. Djapic, P & Strbac, G (2008) Cost Benefit Methodology for Optimal Design of <strong>Offshore</strong><br />

Transmission Systems, BERR Centre for Sustainable Electricity & Distributed Generation,<br />

July 2008.<br />

18. http://renewableconsultation.berr.gov.uk/related_documents, “Quantification of<br />

Constraints on the Growth of UK Renewable Generating Capacity”, Sinclair Knight Merz.,<br />

June 2008.<br />

19. The ABC’s of HVDC Transmission Technology IEEE Power & Energy magazine March<br />

/April 2007 Vol 5 No2<br />

20. UK Renewable Energy Strategy Consultation document BERR June 2008<br />

(http://renewableconsultation.berr.gov.uk/consultation/consultation_summary)<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 91 of 94


11 List of Appendices<br />

Appendix 1 <strong>Offshore</strong> wind farm installed capacity / connection capacity study<br />

Appendix 2 HVAC cable reactive compensation methodology<br />

Appendix 3 Moray Firth C KEITH detailed costing<br />

Appendix 4 Moray Firth C NEW SUBSTATION detailed costing<br />

Appendix 5 Firth of Forth G TORNESS detailed costing<br />

Appendix 6 Firth of Forth G EAST COAST IC detailed costing<br />

Appendix 7 Dogger Bank H1 THORNTON detailed costing<br />

Appendix 8 Dogger Bank H1 CREYKE BECK detailed costing<br />

Appendix 9 Dogger Bank H2 DRAX detailed costing<br />

Appendix 10 Dogger Bank H2 KEADBY detailed costing<br />

Appendix 11 Dogger Bank H3 DRAX detailed costing<br />

Appendix 12 Dogger Bank H3 KEADBY detailed costing<br />

Appendix 13 Dogger Bank H3 CREYKE BECK detailed costing<br />

Appendix 14 Dogger Bank H4 CREYKE BECK detailed costing<br />

Appendix 15 Dogger Bank H4 KILLINGHOLME detailed costing<br />

Appendix 16 Dogger Bank H4 KEADBY detailed costing<br />

Appendix 17 Dogger Bank H5 CREYKE BECK detailed costing<br />

Appendix 18 Dogger Bank H5 KILLINGHOLME detailed costing<br />

Appendix 19 Dogger Bank I1 KEADBY detailed costing<br />

Appendix 20 Dogger Bank I1 KILLINGHOLME detailed costing<br />

Appendix 21 Dogger Bank I2 KEADBY detailed costing<br />

Appendix 22 Dogger Bank I2 KILLINGHOLME detailed costing<br />

Appendix 23 Dogger Bank J THORNTON detailed costing<br />

Appendix 24 Dogger Bank J CREYKE BECK detailed costing<br />

Appendix 25 Dogger Bank I+ CSC KILLINGHOLME detailed costing<br />

Appendix 26 Dogger Bank I+ GIL KILLINGHOLME detailed costing<br />

Appendix 27 Dogger Bank H2 & H3 DC OHL DRAX detailed costing<br />

Appendix 28 Hornsea M SOUTH HUMBER BANK detailed costing<br />

Appendix 29 Hornsea M GRIMSBY detailed costing<br />

Appendix 30 Hornsea M LINCOLNSHIRE COASTAL SUBSTATION detailed costing<br />

Appendix 31 Hornsea N SOUTH HUMBER BANK detailed costing<br />

Appendix 32 Hornsea N GRIMSBY detailed costing<br />

Appendix 33 Hornsea N LINCOLNSHIRE COASTAL SUBSTATION detailed costing<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 92 of 94


Appendix 34 Norfolk T AC SIZEWELL detailed costing<br />

Appendix 35 Norfolk T DC SIZEWELL detailed costing<br />

Appendix 36 Norfolk U AC NORWICH detailed costing<br />

Appendix 37 Norfolk U DC NORWICH detailed costing<br />

Appendix 38 Norfolk Z1 NORWICH detailed costing<br />

Appendix 39 Norfolk Z1 RAYLEIGH detailed costing<br />

Appendix 40 Norfolk Z2 SIZEWELL detailed costing<br />

Appendix 41 Norfolk Z2 RAYLEIGH detailed costing<br />

Appendix 42 Norfolk U & Z1 DC OHL NORWICH detailed costing<br />

Appendix 43 Norfolk Z+ CSC RAYLEIGH detailed costing<br />

Appendix 44 Hastings AA BOLNEY detailed costing<br />

Appendix 45 West Isle of Wight DA CHICKERELL detailed costing<br />

Appendix 46 Bristol Channel EA AC NEW ESTUARY SUBSTATION detailed costing<br />

Appendix 47 Bristol Channel EA AC ALVERDISCOTT detailed costing<br />

Appendix 48 Bristol Channel EA DC ALVERDISCOTT detailed costing<br />

Appendix 49 Bristol Channel EA CSC DC ALVERDISCOTT detailed costing<br />

Appendix 50 Irish Sea IA DC DEESIDE detailed costing<br />

Appendix 51 Irish Sea IA DC PENTIR detailed costing<br />

Appendix 52 Irish Sea IA AC PENTIR detailed costing<br />

Appendix 53 Irish Sea JA DC WYLFA detailed costing<br />

Appendix 54 Irish Sea JA AC WYLFA detailed costing<br />

Appendix 55 Irish Sea LA DC DEESIDE detailed costing<br />

Appendix 56 Irish Sea LA DC PENTIR detailed costing<br />

Appendix 57 Irish Sea LA AC PENTIR detailed costing<br />

Appendix 58 Irish Sea NA STANAH detailed costing<br />

Appendix 59 Irish Sea IA+ CSC DC DEESIDE detailed costing<br />

1845 Crown Estate <strong>Round</strong> 3 OWF connection study v1.0 (FINAL).doc Page 93 of 94


Appendix 1: <strong>Offshore</strong> <strong>Wind</strong> <strong>Farm</strong> installed capacity/connection capacity<br />

study<br />

1 Introduction<br />

To date the connection of both on and offshore wind farms is calculated on enabling export of full<br />

capacity despite the fact that the majority of the time the wind farm is not generating at full power.<br />

The development of wind farms with a maximum output that exceeds the available grid capacity is<br />

not common practice as it requires the wind farm to be constrained, as such, revenue during<br />

periods of peak generation, however brief, is lost.<br />

As the cost of connection for offshore wind farms is significantly higher than those experienced<br />

onshore, and the uncertainty surrounding weather and tidal conditions to perform maintenance<br />

functions may result in lower availability for offshore turbines, it may make sense to install a higher<br />

installed generating capability than the connection capacity will allow. Such an approach could<br />

result in better overall economics for the development despite being constrained at generation<br />

peaks.<br />

While wind farm developments are often considered in terms of costs per MW installed this is a<br />

view that takes no account of the capacity factor (ratio of energy generated to maximum possible<br />

energy output). Therefore, it could be argued that, from a financial perspective, a more appropriate<br />

measure of costs would be cost per MWh generated over the lifetime of the wind farm.<br />

From the perspectives of grid connection and economics, the question is - for a given scenario<br />

which size is optimum?<br />

To answer this question the economic drivers and associated sensitivities for an <strong>Offshore</strong> <strong>Wind</strong><br />

<strong>Farm</strong> need to be understood. This report provides an overview of a model developed to address<br />

this question and provides conclusions to this analysis which have been used to determine<br />

installed capacities for the <strong>Round</strong> 3 offshore wind farms identified within the main report.<br />

2 Objectives<br />

The objective of the <strong>Wind</strong> <strong>Farm</strong> Sizing model is to ascertain, at a high level, the optimum size of an<br />

<strong>Offshore</strong> <strong>Wind</strong> <strong>Farm</strong> for a given connection capacity to assess the lowest ratio of cost per MWh<br />

generated over the lifetime of a wind farm project, as shown in Figure A1.1<br />

1845 Appendix 01 OWF installed-connection capacity study v1-0.doc Page 1 of 13


Figure A1.1. Trend of Capex/lifetime energy generation (£/MWh) as installed capacity increases as a<br />

percentage of connection capacity<br />

3 The Model and Method<br />

3.1 Assumptions<br />

For an offshore location, measured wind speeds throughout a year are characterised by moderate<br />

to fresh winds (5-10m/s), while winds that are strong gale force and above (>20 m/s), where<br />

energy levels are maximised, are relatively uncommon. The wind variation for a standard site is<br />

typically described using the Weibull distribution, such as that shown in Figure A1.2.<br />

Figure A1.2. Weibull distribution [1]<br />

1845 Appendix 01 OWF installed-connection capacity study v1-0.doc Page 2 of 13


The black line in figure A1.2 is the average wind speed and separates the curve into two equal<br />

areas.<br />

Based on this curve it can be assumed that every site can be defined by a shape factor (which, as<br />

the name suggests, defines the shape of the curve) and an average speed (which defines the<br />

curve’s axis) that can be applied to mathematically model the wind profile at a site.<br />

A shape factor of 2 is known as a Rayleigh distribution. In this study a shape factor of 2, which is<br />

the most common in Europe, is applied alongside the average wind speed from real or implied data<br />

for the North Sea. [2]<br />

3.2 Constraints<br />

The amount by which the installed generation capacity may be greater than a specified grid<br />

connection capacity will depend upon the availability of the wind turbine generator (WTG) and the<br />

balance between the cost of installing a WTG relative to the cost of connection.<br />

3.2.1 Availability of the WTG<br />

A WTG is considered unavailable when it is not capable of operating in productive conditions. This<br />

may be as a consequence of a number of different aspects, for example, maintenance, fault<br />

conditions, etc.<br />

It is well documented that the availability of onshore WTGs is in the order of 97 – 98% [1];<br />

however, in the offshore environment, due to the challenges of vessel availability and weather and<br />

tidal windows, in particular, it is realistic to expect availability to be lower, for example, the<br />

availability of North Hoyle <strong>Round</strong> 1 offshore wind farm is reported at 84.7% [3].<br />

Understanding the wind speed distribution is crucial in determining the energy utilisation of the<br />

connection assets and the energy lost by constraint. For a low wind speed site, more WTGs can be<br />

installed above a nominal connection capacity without an equivalent increase in constraint costs.<br />

Such ‘over-development’ could represent an economic advantage for the wind farm.<br />

3.2.2 Cost of installed WTG vs. cost of connection.<br />

It is estimated that the typical cost per MW installed (including grid connection) for offshore wind<br />

farms is presently in the range £1.8m - £2.3m [4]. As the grid connection increasingly represents a<br />

significant proportion of these costs, especially as these offshore wind farms are located further<br />

from their points of connection, then minimising these costs has more influence on the project<br />

financial model.<br />

Conversely, should the cost of the WTG increase relative to the connection costs then it may be<br />

anticipated that there would be little or no advantage to increasing the installed capacity beyond<br />

the available connection capacity.<br />

3.3 Model Set-up and Analysis Methodology<br />

3.3.1 WTG Technology<br />

Different WTG technologies have different power curves. The turbines used in this analysis are as<br />

follows; Siemens 3.6MW, Repower 5MW and Multibrid 5MW. The power curves for these WTG<br />

have been used to calculate the number of turbines required for the best case scenario and hence<br />

determine the ideal wind farm size.<br />

1845 Appendix 01 OWF installed-connection capacity study v1-0.doc Page 3 of 13


The engine of the model is based upon the power curve of the selected WTG. As the wind farm is<br />

‘enlarged’ beyond the connection capacity the amount of constraint on the wind farm increases.<br />

This is simulated in the model by reducing the maximum power that each WTG can generate. As<br />

more WTGs are installed the level of constraint is increased and the subsequent total wind farm<br />

power that can be generated is reduced due to the electrical constraint of the connection capacity.<br />

This is shown in Figure A1.3.<br />

3.3.2 <strong>Connection</strong> Costs<br />

Figure A1.3. Power curve constraint<br />

This input variable is at the discretion of the model user, typical costs of connection applied here<br />

are approximated at £0.7m per MW [4] 1 .<br />

3.3.3 WTG Costs<br />

This input variable is at the discretion of the model user and constitutes all costs other than<br />

connection costs, the majority of which is the cost of the WTG. Typical costs applied are<br />

approximated at £1.5m per MW [4]<br />

3.3.4 Average <strong>Wind</strong> Speed<br />

This input variable is at the discretion of the model user. For offshore wind farms in the UK this has<br />

been approximated at 9m/s, as shown in Figure A1.4 [5].<br />

1 The actual connection costs identified within the report range between £287k and £477k per MW based on<br />

a 112% utilisation factor or £287k and £532k per MW based on a 100% utilisation factor which would<br />

weaken the financial case for over installing capacity offshore, however it could also be surmised that for<br />

<strong>Round</strong> 3 the WTG installed costs per MW may also reduce below £1.5m per MW which would in turn<br />

strengthen the financial case for over-installing. Sensitivity to these variables has been assessed within this<br />

analysis.<br />

1845 Appendix 01 OWF installed-connection capacity study v1-0.doc Page 4 of 13


3.3.5 WTG Availability<br />

Figure A1.4. Annual mean wind speed in UK [5]<br />

This input variable is at the discretion of the model user. Turbine availability is approximated at<br />

90% based upon data from existing offshore wind farms [3].<br />

3.4 Sensitivity Analysis<br />

The aim of the sensitivity analysis is to gain an understanding of the limitations to the scale of<br />

overdevelopment of the wind farms in relation to changes in the different constraint variables<br />

identified in section 3.3.<br />

The sensitivity analyses pertain to; ratio of connection costs to WTG costs, average wind speed,<br />

and WTG availability.<br />

3.4.1 Ratio of connection costs to installed WTG costs<br />

This ratio is calculated on a per MW basis. The cost of installed MW includes costs associated with<br />

the WTG machine, transportation and installation. The cost of connection includes the offshore<br />

transmission assets and the substations both on and off shore. The ratio of installed WTG costs to<br />

connection costs is stepped in the sensitivity analysis from 0.5 to 2.5.<br />

3.4.2 Average <strong>Wind</strong> Speed<br />

As the mean wind speed varies year on year, an analysis of the sensitivity to mean wind speed is<br />

an important element. It should be noted that the energy production of the WTG is directly<br />

1845 Appendix 01 OWF installed-connection capacity study v1-0.doc Page 5 of 13


proportional to the average wind speed; as average wind speed increases the energy production of<br />

an operational WTG increases; which will increase revenue and, therefore, reduce the cost per<br />

MWh generated.<br />

Typically, at an average wind speed of 6m/s, depending upon the WTG selected, the WTG is<br />

generating at 10-25% of its maximum MWh output, while at wind speeds above16m/s the WTG is<br />

generating at 100% of the maximum available MWh output. The energy produced by a wind farm<br />

over the course of a year as a proportion of the total energy that the wind farm could possibly have<br />

generated had the wind speed been constantly above 16m/s for example is given by the term<br />

‘capacity factor’ (CF). Capacity factors tend to be higher for offshore wind farms than those<br />

onshore due to higher average wind speeds and less turbulence in the air flow; however it should<br />

be noted that CFs of 50% or more are exceptional.<br />

It should also be noted that a WTG must cut out at wind speeds in excess of, typically, 25m/s,<br />

depending upon turbine type.<br />

In the sensitivity analysis the average wind speed is stepped from 6m/s to 16m/s.<br />

3.4.3 WTG Availability<br />

WTG availability is described in detail in Section 3.2.2. In the sensitivity analysis the availability is<br />

stepped between 84% and 100%.<br />

4 Results<br />

The results below are based on the typical wind farm parameters used as a basis for the <strong>Round</strong> 3<br />

offshore wind farm connection study main report (v1.0)<br />

4.1 Example wind farm base parameters<br />

The base model set-up for this example is as follows:<br />

WTG<br />

Technology<br />

<strong>Wind</strong> <strong>Farm</strong><br />

Size (MW)<br />

<strong>Connection</strong><br />

Cost per MW<br />

(£k)<br />

Installed WTG<br />

Cost per MW<br />

(£k)<br />

Average <strong>Wind</strong><br />

Speed (m/s)<br />

1845 Appendix 01 OWF installed-connection capacity study v1-0.doc Page 6 of 13<br />

WTG<br />

Availability (%)<br />

Repower 5MW 1110 700 1,500 9.0 90<br />

4.2 Example wind farm base results<br />

Table A1.1. Base model set-up<br />

For these input values, the optimal installed given is 112% of the connection capacity, as shown in<br />

Table A1.2. This is based on the total WTG installed cost increasing for the extra WTG’s but the<br />

total connection cost remaining at the 1110MW x £700k value. The revenue generated is<br />

increased due to the additional wind turbines operating at low wind speeds. (Note: at high wind<br />

speeds the additional WTGs will result in each WTG being slightly more constrained; this is<br />

allowed for in the model).


Size (%) 100% 112%<br />

Total CAPEX (£m) 2442 2642<br />

Lifetime Revenue (£m) 6,874 7,680<br />

CAPEX/Lifetime Energy Generation (£/MWh) 29.84 28.89<br />

WTG (units) 222 249<br />

Capacity Factor (%) 44.18% 44.08%<br />

Table A1.2. Size results comparison<br />

As shown Table A1.2, using 249 WTG at a total cost of £2,642m instead of 222 WTG with a total<br />

cost £2,442m, generates revenue of £7,680m against £6,874m. It is evident that the capacity factor<br />

is only slightly reduced by the loss in energy for the electrical constraint (assuming 90% WTG<br />

availability in each case). However, installing generation capacity up to 112 % of the connection<br />

capacity results in a better CAPEX/Lifetime Energy Generation Figure of £28.89 per MWh against<br />

£29.84 per MWh produced were 100% connection capacity installed.<br />

This CAPEX/Lifetime Energy Generation Figure can be used to assess how project variables affect<br />

an investment in order to determine the economically optimised model, and hence should not be<br />

used in isolation.<br />

It can be seen in Figure A1.5, the red line representing the CAPEX/Lifetime Energy Generation<br />

Figure has a minimum value at 112 % of the connection capacity.<br />

Figure A1.5. Trend of CAPEX/Lifetime Energy Generation Figure as installed capacity increases as a<br />

percentage of connection capacity<br />

1845 Appendix 01 OWF installed-connection capacity study v1-0.doc Page 7 of 13


4.3 Sensitivity Analysis<br />

For this analysis each of the parameters in Table A1.1 was varied in turn.<br />

4.3.1 Ratio of <strong>Connection</strong> Costs to Installed WTG Costs (Cost Ratio)<br />

Table A1.3 shows the analysis results for a range of cost ratios with the wind speed and WTG<br />

availability remaining at the base set-up given in Table A1.1.<br />

It is evident that as the installed cost of the WTG reduces against a fixed connection cost, the<br />

CAPEX/Lifetime Energy Generation Figure also reduces assuming a significant overbuild is<br />

desirable. For a cost of £0.35m per MW installed WTG and £0.7m per MW connection cost, 333<br />

WTG (150% of connection capacity) can be installed instead of the 222 provided in Table A1.2 for<br />

100% connection capacity.<br />

However, as is evident from both Table and Figure A1.6, as the cost ratio increases there is an<br />

asymptotic trend for the optimum size of the wind farm toward 111%.<br />

WTG cost/connection cost ratio 0.5 1 1.5 2 2.5<br />

Size (%) 150% 122% 113% 112% 111%<br />

Total CAPEX (£m) 1360 1725 2094 2517 2933<br />

Lifetime Revenue (£m) 8933 8080 7725 7680 7630<br />

CAPEX/ Lifetime Energy Generation (£/MWh) 12.18 17.08 21.68 26.22 30.75<br />

WTG (units) 333 271 251 249 246<br />

Capacity Factor (%) 38% 43% 44% 44% 44.<br />

Table A1.3. WTG installed cost sensitivity sample results.<br />

In Figure A1.6, each line represents the CAPEX/Lifetime Energy Generation Figure for different<br />

cost ratios between the installed WTG cost per MW and a fixed connection cost per MW of £0.7m.<br />

Figure A1.6. CAPEX /Lifetime energy figure & installed capacity sensitivity to WTG installed costs<br />

1845 Appendix 01 OWF installed-connection capacity study v1-0.doc Page 8 of 13


4.3.2 Average <strong>Wind</strong> Speed<br />

Table A1.4 shows the sensitivity analysis results for a range of average wind speeds with the WTG<br />

installed cost and WTG availability parameters remaining at the base set-up given in Table A1.1.<br />

As provided in Table A1.4, the possible percentage of installed power against connection capacity<br />

ranges asymptotically from 147% at low average wind speeds (6m/s) to 111% at high wind speeds<br />

(16m/s). Given that the typical mean wind speed for the North Sea is 9m/s, these results suggest<br />

that the optimum size wind farm installed capacity is 112% of the available connection capacity. In<br />

the scenario presented here, the recommendation would be that the number of turbines used for<br />

the development should be 249 rather than 222 (100% of connection capacity). As the average<br />

wind speed increases there is little change in the optimum size. If the mean wind speed is less<br />

than 9m/s then the optimum size increases in order to maximise the utilisation of the available<br />

connection capacity.<br />

<strong>Wind</strong> speed<br />

(m/s)<br />

6 7 8 9 10 11 12 13 14 15 16<br />

Size (%) 147 126 114 112 111 111 111 111 111 111 111<br />

Total CAPEX<br />

(£m)<br />

Lifetime<br />

Revenue<br />

(£m)<br />

CAPEX /<br />

Lifetime<br />

Energy<br />

Generation<br />

(£/MWh)<br />

3225 2875 2675 2642 2625 2625 2625 2625 2625 2625 2625<br />

4325 5395 6444 7680 8795 9801 10651 11347 11900 12302 12574<br />

59.65 42.63 33.21 27.52 23.88 21.43 19.72 18.51 17.65 17.07 16.70<br />

WTG (units) 326 280 253 249 246 246 246 246 246 246 246<br />

Capacity<br />

Factor (%)<br />

19% 28% 36% 44% 50% 57% 62% 66% 69% 71% 73%<br />

Table A1.4. Average wind speed sensitivity<br />

It should be noted that the average wind speed is a characteristic of the site chosen for the wind<br />

farm development; however, this model can be used to ascertain the level of enhanced installation<br />

above the connection capacity required to maximise the economic benefit given the site<br />

constraints.<br />

1845 Appendix 01 OWF installed-connection capacity study v1-0.doc Page 9 of 13


Figure A1.7. Sensitivity of CAPEX/Lifetime Energy Generation Figure & installed capacity to average wind<br />

speed<br />

4.3.3 WTG Availability<br />

Table A1.5 shows the analysis results for a range of WTG availabilities with the WTG installed cost<br />

and Average wind speed remaining at the base set-up given in Table A1.1.<br />

Availability (%) 84% 86% 88% 90% 92% 94% 96% 98% 100%<br />

Size (%) 119 117 114 112 109 107 105 103 101<br />

Total CAPEX (£m) 2758 2725 2675 2642 2592 2559 2525 2492 2459<br />

Lifetime Revenue<br />

(£m) 8180 8028 7829 7680 7487 7343 7200 7060 6922<br />

CAPEX/Lifetime<br />

Energy Generation<br />

(£/MWh) 26.98 27.16 27.33 27.52 27.70 27.88 28.06 28.24 28.42<br />

WTG (units) 264 260 253 249 242 238 233 229 224<br />

Capacity Factor (%) 44% 44% 44% 44% 44% 44% 44% 44% 44%<br />

Table A1.5. CAPEX/Annual Energy figure & installed capacity sensitivity to average wind speed<br />

The results in Table A1.5 show that as WTG availability decreases, the percentage of installed<br />

power for a given connection capacity needs to increase to maintain similar CAPEX/Lifetime<br />

Energy Generation Figures. However, for a 90% WTG availability, an installed capacity of 112%<br />

provides the optimum CAPEX/Lifetime energy figure, as shown in Figure A1.8.<br />

1845 Appendix 01 OWF installed-connection capacity study v1-0.doc Page 10 of 13


Figure A1.8. CAPEX/Lifetime Energy Generation Figure against installed capacity for<br />

various WTG availabilities<br />

1845 Appendix 01 OWF installed-connection capacity study v1-0.doc Page 11 of 13


5 Recommendations<br />

This high level analysis presented here suggests that the optimum installed capacity for a fixed<br />

connection capacity in terms of a CAPEX/Lifetime Energy Generation Figure appears to be around<br />

112%.<br />

It is therefore recommended that the installed capacity for the <strong>Round</strong> 3 wind farms used in this<br />

report be set at 112% of the total power transfer capacity of the technology elements used in the<br />

connection design.<br />

1845 Appendix 01 OWF installed-connection capacity study v1-0.doc Page 12 of 13


6 References<br />

[1] Danish wind industry association, www.windpower.com.<br />

[2] NOABL and NCIC wind speed data<br />

[3] North Hoyle <strong>Offshore</strong> <strong>Wind</strong> farm annual report, URN no. 08/P47, BERR<br />

[4] CERA: <strong>Offshore</strong> <strong>Wind</strong> Power Capital Costs Will Continue To Rise, Creating New<br />

Challenges for European Renewable Energy Targets, CERA (Cambridge Energy<br />

Research Associates), Press Release 28 May 2008,<br />

www.cera.com/aspx/cda/public1/news/pressReleases/pressReleaseDetails.aspx?CID=9512<br />

[5] Atlas of UK Marine Renewable Energy Resources: Technical Report,<br />

www.berr.gov.uk/files/file27763.pdf, Dec 2004.<br />

1845 Appendix 01 OWF installed-connection capacity study v1-0.doc Page 13 of 13


Appendix 2 : HVAC cable reactive compensation analysis methodology<br />

A power systems model of a nominal 275kV offshore-onshore alternating current (AC) grid interconnection<br />

from a proposed 330MW (derived from the manufacturer’s maximum power rating) point<br />

of supply (POS) to the onshore point off common coupling (PCC) was developed in PSS/SINCAL<br />

V5.4. This model was used to assess at a high level the maximum feasible length of three-core<br />

subsea AC cable that could be deployed before the combined issues of active power losses and<br />

reactive power charging capacitance reduced the collector cables useful power carrying capacity to<br />

zero. Figure A2.1 illustrates the power system model.<br />

100.00 %<br />

0.00 °<br />

112.41 %<br />

2.43 °<br />

115.10 %<br />

5.16 °<br />

I61<br />

-316.82 MW<br />

-765.35 MVAr<br />

316.82 MW<br />

1<br />

765.35 MVAr<br />

-327.71 MW<br />

-455.05 MVAr<br />

2327.71 MW<br />

328.69 MVAr<br />

-330.00 MW<br />

108.00 MVAr<br />

LO57<br />

330.00 MW<br />

-108.00 MVAr<br />

Figure A2.1: PSS/SINCAL power systems model<br />

The following assumptions have been made regarding the model:<br />

• The collector cables from the offshore POS to the landfall transition pit and from the landfall<br />

transition pit to the PCC are equal in length<br />

• Import of reactive power is defined as inductive and export of reactive power is defined as<br />

capacitive where 0.95 power factor equates to the import or export of 108MVAr of reactive<br />

power<br />

• The offshore wind farm is capable of importing 108MVAr of reactive power at the POS during<br />

maximum active power export to partially offset the cable charging current<br />

• The PCC is controlled to a nominal voltage (275kV)<br />

• The maximum permissible variation of voltage from nominal is ±10% of nominal voltage<br />

1845 Appendix 02 HVAC cable reactive compensation methodology v1.0.doc Page 1 of 2


• The grid at the proposed PCC is strong, i.e. the fault level from the grid is 10 times the fault in<br />

feed from the proposed 330MW infeed, in order to minimise voltage variations<br />

The reactive power compensation (RPC) to compensate for cable charging capacitance was<br />

assessed under the following conditions:<br />

• No additional RPC<br />

• RPC of equal quantity installed at the PCC and POS (50/50 split)<br />

• RPC of equal quantity installed at the PCC, landfall transition pit and POS (33/33/33 split)<br />

Initial approximate sizing of the RPC requirement was determined from Equation 1 where Qreq is<br />

reactive power, C is the cable capacitance (µF) per km, l is the cable length in km’s, V is the<br />

operating voltage of 275kV and ω is the angular frequency of the supply in radians. It is important to<br />

note that this does not consider the presence of voltage drop due to resistive losses and also series<br />

inductance of the cable. Further optimisation of the RPC was performed manually to produce near<br />

zero reactive power transfer to the PCC.<br />

Equation 1: Sizing of RPC<br />

Q req<br />

= ωClV<br />

2<br />

The cables average current flow (kA) and apparent power capacity (MVA) were applied as<br />

constraints to determine the cables useable capacity. These are defined as follows:<br />

• Average current flow – The current carrying capacity of the conductors’ cross-sectional area<br />

is the limiting factor. If this is exceeded the heat produced over a prolonged period of time<br />

would cause damage to the conductor insulation possibly causing a total dielectric failure.<br />

Figures are shown as an average of the current flows observed at different points in the<br />

cable. Indication has been given in Table 4 of the main report to cases where peak current<br />

flow exceeds the cables current capacity<br />

• Apparent power capacity - This considers the conductors current carrying capacity with<br />

respect to transmission voltage. If the transmission voltage exceeds the design withstand<br />

voltage of the cables dielectric for a significant period of time it will cause the dielectric<br />

breakdown causing possible short circuits in the dielectric or intermittent breakdown of the<br />

dielectric due to charging current producing transient interference<br />

The results of this analysis are presented in Table 4 of The <strong>Round</strong> 3 <strong>Offshore</strong> <strong>Wind</strong> farm <strong>Connection</strong><br />

Study main report (v1.0).<br />

1845 Appendix 02 HVAC cable reactive compensation methodology v1.0.doc Page 2 of 2

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!