2003 February<br />

• Equipment <strong>and</strong> materials met all specified requirements<br />

• Packaging <strong>and</strong> marking were correct <strong>and</strong> meet <strong>Project</strong> requirements.<br />

• Equipment <strong>and</strong> materials were released.<br />

B.3 Quality Assessments<br />

B.3.1 Quality Assessment for <strong>Construction</strong><br />

<strong>Construction</strong> contractors’ QA programs improved dramatically during the course of the <strong>Qinshan</strong><br />

Phase III <strong>Project</strong>. Initial efforts were directed toward documenting the QA programs (QA<br />

Manual plus procedures). Once documented, the QA programs were “tested” to determine the<br />

extent of application. This required extensive efforts on the part of SPMO <strong>and</strong> the construction<br />

contractors. One of the most difficult challenges was in instituting international quality practices,<br />

such as documenting non-conformances. This became much easier once the benefit of these<br />

practices was acknowledged by the contractors. The lessons learned on <strong>Qinshan</strong> Phase III can<br />

now be applied to other projects both in China <strong>and</strong> abroad.<br />

Improvements were also made from the construction of Unit 1 to that of Unit 2. The following<br />

are some examples:<br />

• Build Clean program – a more comprehensive program was developed for Unit 2,<br />

resulting in much fewer incidences of foreign materials in the piping system.<br />

• Cleanliness levels were significantly improved on Unit 2, particularly the dust levels in<br />

panels <strong>and</strong> other sensitive electronic components. This required significant interface<br />

management, since all contractors were involved.<br />

• Assembly of cable penetration seals was improved on Unit 2. Additional field<br />

engineering, verification <strong>and</strong> construction supervision activities were undertaken. These<br />

efforts resulted in a significant reduction to the Reactor Building leak rate for Unit 2.<br />

The contractors’ QC function was strengthened, resulting in earlier problem definition <strong>and</strong><br />

quicker corrective action.<br />

B.3.2 Quality Assessment for Commissioning<br />

When commissioning activities began, many of the staff were young <strong>and</strong> inexperienced.<br />

Although the AECL staff had extensive experience gained during the commissioning of previous<br />

<strong>CANDU</strong> plants, their numbers were quite low, representing about 5% of the entire<br />

Commissioning Team. There was some indication in the beginning that procedures were not<br />

being followed <strong>and</strong> processes were not well documented.<br />

However, TQNPC staff learned quickly <strong>and</strong> endeavoured to follow procedures. Significant<br />

inroads were made as the commissioning work proceeded. This was aided to a large extent by<br />

the Quality Monitoring activities of TQNPC <strong>and</strong> SPMO staff.<br />

As a result of the continuous Quality Monitoring activities, Commissioning Team staff became<br />

diligent in following procedures <strong>and</strong> in completing the necessary records. This, in turn, resulted<br />

in less damage during commissioning <strong>and</strong> better control of the commissioning process. Since<br />