2003 February<br />

TABLE OF CONTENTS<br />

SECTION PAGE<br />

8.1.1 Degree of Prefabrication/Modularization........................................................ 22<br />

8.1.2 Open Top <strong>Construction</strong> ................................................................................... 22<br />

8.1.3 Information Technology <strong>and</strong> Engineering Tools............................................. 23<br />

8.1.4 <strong>Project</strong> Management........................................................................................ 25<br />

8.1.5 <strong>Construction</strong> Photographs ............................................................................... 26<br />

9. METHOD TO SUBCONTRACT MATERIAL AND<br />

CONSTRUCTION WORKS................................................................................. 27<br />

10. RESOURCES AND QUANTITIES ..................................................................... 29<br />

10.1 Manhours............................................................................................................... 29<br />

10.2 Cubic Metres of Concrete <strong>and</strong> Nuclear Piping...................................................... 29<br />

11. MATERIAL MANAGEMENT............................................................................. 35<br />

12. SITE INFRASTRUCTURE AND MANAGEMENT........................................... 36<br />

12.1 Infrastructure ......................................................................................................... 36<br />

12.2 Warehouses ........................................................................................................... 36<br />

12.3 Offices <strong>and</strong> Archives............................................................................................. 36<br />

12.4 Accommodations................................................................................................... 37<br />

12.5 Personnel on Site................................................................................................... 37<br />

13. Commissioning Organization Including Measures to Reduce the<br />

Commissioning Period .......................................................................................... 38<br />

13.1 Function................................................................................................................. 38<br />

13.2 Division of Responsibilities .................................................................................. 38<br />

13.3 Commissioning Organization <strong>and</strong> Staffing........................................................... 39<br />

13.4 Measures to Reduce the Commissioning Schedule............................................... 40<br />

13.4.1 Appointment of System Engineers.................................................................. 40<br />

13.4.2 Establishment of Control Points...................................................................... 40<br />

13.4.3 Establishment of Commissioning Documentation.......................................... 41<br />

13.4.4 Close Interface with Engineering .................................................................... 42<br />

13.4.5 Close Interface with <strong>Construction</strong>................................................................... 42<br />

13.4.6 Optimization of Commissioning Schedule ..................................................... 43<br />

13.4.7 Improvements in Future Commissioning Programs........................................ 44<br />

14. AECL STUDY: LESSONS LEARNED ON QINSHAN 3 TO<br />

REDUCE THE SCHEDULE ON FUTURE REPLICATED<br />

PROJECTS............................................................................................................ 53<br />

14.1 Planning <strong>and</strong> Control............................................................................................. 53<br />

ii