Qinshan CANDU Project Construction Experiences and Lessons

Qinshan CANDU Project Construction Experiences and Lessons Qinshan CANDU Project Construction Experiences and Lessons

12.01.2013 Views

2003 February 5. CONSTRUCTION SCHEDULE AND MAJOR MILESTONES Qinshan Unit 1 was based on a 72-month schedule, followed 9 months later by Qinshan Unit 2. It is to be noted that Unit 1 achieved In-Service 43 days ahead of schedule. Figure 5-1 provides major Project milestone data. 14

2003 February Figure 5-1 Major Milestones 15