ITEM<br />
RISK AREAS<br />
7 CONVEYING<br />
SYSTEMS<br />
(ELEVATORS)<br />
7.1 Sound<br />
Transmission<br />
REQUIREMENT FOR TOTAL NUMBER OF VISITS<br />
Documentation review PLUS<br />
1 visit for inspection of finishes<br />
Review design document, sound transmission class rating of party walls,<br />
partitions, floor/ceiling. Material; thickness; arrangement of components;<br />
continuity; acoustic caulking/seals. Flanking transmission path(s); schedule<br />
of partitions/suites/units to be subject to field testing by qualified<br />
consultants.<br />
TYPICAL BUILDING<br />
EXAMPLE<br />
Page 46 of 70<br />
10 STY 20 STY 30 STY<br />
1 1 1<br />
1 1 1<br />
ITEM RISK AREAS REQUIREMENT FOR TOTAL NUMBER OF VISITS TYPICAL BUILDING<br />
EXAMPLE<br />
8 MECHANICAL 10 STY 20 STY 30 STY<br />
Heating;<br />
Documentation review PLUS<br />
4 8 12<br />
8.1 ventilation; air 1 visit per parkade and 1 visit per every 4 floors to confirm<br />
8.2 conditioning Placement of labeling<br />
8.3<br />
8.4<br />
8.5<br />
Plumbing –<br />
supply<br />
Plumbing –<br />
drainage<br />
Waste disposal<br />
Insulation<br />
8.6 Mechanical noise<br />
vibration<br />
Central HVAC equipment noise/vibrations and unit/suite equipment<br />
impacts on the building and respective suites; pumps; garbage<br />
compaction; plumbing stacks; acoustic insulation materials; garbage<br />
chutes; acoustic planes; acoustic louvers; acoustic enclosures; (all in<br />
accordance with OBC/ASHRAE)<br />
Labelling; installation; clearances; materials; thickness; degree of<br />
isolation/flexibility specified.<br />
4 5 6<br />
ITEM RISK AREAS REQUIREMENT FOR TOTAL NUMBER OF VISITS TYPICAL BUILDING EXAMPLE<br />
9 ELECTRICAL 10 STY 20 STY 30 STY<br />
9.1 Distribution Documentation review PLUS<br />
4 8 12<br />
systems<br />
1 visit per parkade and 1 visit per every 4 floors to confirm<br />
Placement of labeling<br />
9.2<br />
9.3<br />
9.4<br />
9.5<br />
Lighting<br />
Emergency<br />
power<br />
Intercom and<br />
security systems<br />
Insulation<br />
9.6 Noise Rating of<br />
transformers<br />
Acoustic treatment/finishes of generator room building components;<br />
acoustic louvers; silencers; mufflers (all in accordance with<br />
OBC/ASHRAE)<br />
4 5 6