Application Story<br />
Top gas mud density measurement in Nova hut a.s.<br />
ISPAT Nova Hut a.s. is one of the largest metallurgic plants in the Czech Republic.<br />
It is an integrated steelmaking concern <strong>with</strong> a metallurgical production and large<br />
engineering shops. The metallurgical production is of a mass character, the main<br />
products being welded and hot-rolled seamless steel pipes, long products and wire<br />
rod, hot rolled sheets and strips. The engineering production (e.g. steel mining<br />
supports) is geared for batch production. Their coking plant is the largest coke<br />
producer in the Czech Republic.<br />
ISPAT Nova Hut has been using several hundreds of KROHNE magnetic inductive<br />
flowmeters and flow controllers (mainly on water measurements) and additionally<br />
ultrasonic flowmeters (on demineralised water and tar), level radar (blast furnace<br />
stock level, hydrochloric acid level measurement) and mass flowmeters (fuel oil, top<br />
gas and steel sludge measurement). All instruments have been subjected to<br />
demanding operating conditions.<br />
In the blast furnace, during the pig iron production process, a lot of top gas is<br />
generated. The gas (<strong>with</strong> temperature 200 – 500°C) contains from 30 to 100 g/m3 of<br />
dust. The gas is cleaned <strong>with</strong> sprinkling water, which then flows into settling basins.<br />
Here the mud settles and then it is pumped first to thickeners and after thickening to a<br />
separator. For the process control it is necessary to know the density of the mud<br />
pumped from basins to thickeners and from thickeners to the separator.<br />
The customer had been using nucleonic density meters for 10 years. These meters<br />
require special approvals and checks and a lot of maintenance. <strong>More</strong>over they could<br />
not be in operation <strong>with</strong>out product flow. For this reason the customer decided to test<br />
2 KROHNE mass flowmeters Corimass MFM 4085 G+ - 1500 G. After 6 months´<br />
testing, 8 pieces of Optimass T50 mass flowmeters were ordered.<br />