09.01.2013 Views

State of Technology Report for Force Main Rehabilitation, Final ...

State of Technology Report for Force Main Rehabilitation, Final ...

State of Technology Report for Force Main Rehabilitation, Final ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

2.5 Redundancy<br />

Many <strong>for</strong>ce mains are located at critical points in sewerage systems. As a result, if they have to be taken<br />

out <strong>of</strong> service due to a failure, then by-pass pumping or the use <strong>of</strong> honey trucks is necessary. One way in<br />

which utilities plan <strong>for</strong> this is to install dual parallel <strong>for</strong>ce mains thus providing redundancy. During an<br />

emergency, such as a failure in one line, the parallel line can be used to maintain a minimal level <strong>of</strong> flow<br />

such that any upstream wetwell does not overflow or sewers become surcharged, or at least the use <strong>of</strong><br />

honey trucks (required to keep the sewage from swamping any lift stations) is minimized. The other<br />

advantage in having a redundant line is the ability to take one line out <strong>of</strong> service <strong>for</strong> an intrusive (internal)<br />

inspection and/or repairs.<br />

Over 45% <strong>of</strong> utilities contacted indicated that they had at least one redundant <strong>for</strong>ce main in their system.<br />

For those reporting in the affirmative, an average <strong>of</strong> 14% <strong>of</strong> the systems had some redundancy built in.<br />

However, some utilities actually reported in the WERF survey having a larger number <strong>of</strong> redundant<br />

systems than total <strong>for</strong>ce mains so this number is suspect. This limited sampling would suggest that<br />

perhaps about 5% <strong>of</strong> the total number <strong>of</strong> <strong>for</strong>ce mains do have some redundancy built in.<br />

Parallel mains to enable one main to be out <strong>of</strong> service are seldom installed. Those utilities that do have<br />

parallel mains generally installed them because extra capacity was needed over and above that available<br />

from an existing main. The parallel main is then installed to provide additional capacity and not the total<br />

capacity. Thus, the opportunity <strong>for</strong> redundancy and operational security is not taken.<br />

Current practice is not to install parallel mains to provide redundancy. Installing alongside existing mains<br />

considered critical is done only very occasionally.<br />

2.6 Cause <strong>of</strong> Failure in <strong>Force</strong> <strong>Main</strong>s<br />

Based on the WERF survey, almost universally, with 92% <strong>of</strong> the responders in the affirmative, utilities<br />

attempt to identify the cause <strong>of</strong> the failure in the <strong>for</strong>ce main. The utilities were asked to identify the most<br />

common factors relating to failures in their <strong>for</strong>ce mains. Various causes are discussed below. It is<br />

important to understand the typical failure modes and mechanisms <strong>of</strong> <strong>for</strong>ce mains in order to select the<br />

most appropriate repair, rehabilitation, and replacement technologies.<br />

2.6.1 Ferrous <strong>Force</strong> <strong>Main</strong>s. Figure 2-6 shows that internal corrosion was rated as being<br />

responsible <strong>for</strong> ferrous <strong>for</strong>ce main failures 26.2% <strong>of</strong> the time, ahead <strong>of</strong> all other known causes. External<br />

corrosion at 19.2% and third-party damage at 19.4% are the next most common causes <strong>of</strong> failures.<br />

Combining internal and external corrosion, corrosion appears responsible <strong>for</strong> failures in <strong>for</strong>ce mains in<br />

nearly 46% <strong>of</strong> cases. After third-party damage, joint leakage at 15.2%, surge pressure at 10.2%, and<br />

insufficient capacity at 9.8% are the next most significant causes <strong>of</strong> <strong>for</strong>ce main failures.<br />

2.6.2 Non-Ferrous <strong>Force</strong> <strong>Main</strong>s. Figure 2-7 shows the most common single cause <strong>of</strong> failure in<br />

non-ferrous <strong>for</strong>ce mains is third-party damage, which accounts <strong>for</strong> 36% <strong>of</strong> failures. Corrosion and<br />

structural failure together account <strong>for</strong> 54% <strong>of</strong> failures. It is considered likely that some <strong>of</strong> the structural<br />

failures reported <strong>for</strong> cementitious pipes (AC, RCP, and PCCP) are due to corrosion. Figure 2-7 is based<br />

on a weighted average <strong>of</strong> failure causes <strong>for</strong> each pipe material. The main causes <strong>of</strong> failure vary<br />

significantly by pipe material. For each pipe material type, the main causes <strong>of</strong> failure are as follows: (1)<br />

PVC – third-party damage, (2) PCCP – corrosion, (3) RCP – corrosion, (4) AC – third-party damage, and<br />

(5) PE – third-party damage.<br />

9

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!