<strong>Technology</strong>/Method<br />

apply)<br />

CIPP/Inversion with Hot Water Cured<br />

II. <strong>Technology</strong> Parameters<br />

Service Application Wastewater, Industrial Cooling Water.<br />

Service Connections Liner stops and starts at connections, which must be reinstated via open cut.<br />

Structural Rating Class IV –Structural – handle all external and internal loading. No bonding to<br />

Claimed<br />

Materials <strong>of</strong><br />

Composition<br />

the original host pipe wall assumed.<br />

A sewn tube consisting <strong>of</strong> two or more layers <strong>of</strong> absorbent non-woven synthetic<br />

fiber combined with glass fiber rein<strong>for</strong>cement. The outside layer <strong>of</strong> the tube is<br />

plastic coated with a translucent flexible material <strong>for</strong> visual inspection during<br />

resin impregnation. A vinyl ester resin, compatible with the inversion and curing<br />

process, is used.<br />

Minimum Physical Properties (25 o C)<br />

Property ASTM Method Value<br />

Initial Flexural Modulus <strong>of</strong> Elasticity D790 250,000 psi<br />

Initial Flexural Strength D790 7,000 psi<br />

Initial Tensile Strength D638 6,000 psi<br />

For internal pressure design, a long-term tensile strength equal to 1/3 rd Diameter Range,<br />

inches<br />

<strong>of</strong> the<br />

initial design value is used. In addition, a factor <strong>of</strong> safety <strong>of</strong> 2 is utilized.<br />

8-72 inches<br />

Thickness Range,<br />

inches<br />

5–26 mm<br />

Pressure Capacity, psi Up to 80 psi, diameter dependent.<br />

Temperature Range,<br />

o<br />

F<br />

120 o F<br />

Renewal Length, feet 200 to 1,000 feet<br />

Other Notes All terminations must be fitted with mechanical end seals.<br />

Product Standards<br />

III. <strong>Technology</strong> Design, Installation, and QA/QC In<strong>for</strong>mation<br />

Not suitable <strong>for</strong> potable water.<br />

Design Standards ASTM F1216, Appendix X1.3.2 <strong>for</strong> the Fully Deteriorated Pressure Pipe<br />

condition.<br />

Design Life Range 50 years<br />

Installation Standards ASTM F1216<br />

Installation<br />

Pipeline is to be cleaned and all debris removed from the interior. The line is to<br />

Methodology be CCTV inspected be<strong>for</strong>e lining. All obstructions, including reducers, line<br />

valves and protruding connections to be removed. The rein<strong>for</strong>ced Insitu<strong>for</strong>m felt<br />

tube is resin saturated either in the factory or on site and prepared <strong>for</strong> installation.<br />

On site, the tube is positioned in the pipeline using water pressure to turn the tube<br />

inside out (inversion). The water pressure <strong>for</strong>ces the tube to a close fit with the<br />

host pipe. After positioned, the resin is cured by circulating hot water through<br />

the tube. Once cured, the pipe is cooled to a maximum <strong>of</strong> 90 o F. The ends are cut<br />

and sealed. Expansion type end seals with expandable stainless steel bands and<br />

elastomeric seals are used <strong>for</strong> this purpose. The pipe may be returned to service<br />

after CCTV inspection and pressure testing.<br />

QA/QC • Prior to insertion <strong>of</strong> tube, CCTV inspection <strong>of</strong> main needed to locate any<br />

obstructions, protrusion, changes in diameter or in-line valves that could<br />

affect liner.<br />

• After insertion and cure, liner inspected again visually with CCTV, and any<br />

abnormalities are noted.<br />

• For each inversion length, one liner sample, suitable in size to yield 5<br />

specimens, is collected either from a section <strong>of</strong> the cured pipe lining<br />

(usually at termination point) or a flat plate sample and subjected to flexural<br />

and tensile testing. Average values should exceed minimums used <strong>for</strong><br />

design.<br />

• Pressure testing to be carried out after liner has reached original ambient<br />

ground temperature. The liner and host pipe subjected to a hydrostatic<br />

A-42