05.01.2013 Views

2010 Construction and Material Specifications - Ohio Department of ...

2010 Construction and Material Specifications - Ohio Department of ...

2010 Construction and Material Specifications - Ohio Department of ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

625.18<br />

prevent the weight <strong>of</strong> the vertical run from abrading the wire insulation or cable<br />

jacket where the wire or cable passes into or from the pole.<br />

Identify all wires <strong>and</strong> cables, except bare ground bonding cables, as to circuit<br />

<strong>and</strong> function with tags or b<strong>and</strong>s in the base <strong>of</strong> each light pole or light tower, each<br />

junction box or pull box, each apparatus cabinet, <strong>and</strong> other similar locations.<br />

Pay out each wire, cable <strong>and</strong> duct cable by “unwinding” it from the shipping<br />

reel, spool or coils <strong>and</strong> not allow the wire cable or duct-cable to “spiral” from <strong>of</strong>f<br />

the side <strong>of</strong> the spool reel or coil. In addition when wire cable or duct cable is<br />

being placed in trench, move the reel spool or coil along the side <strong>of</strong> the trench to<br />

allow the wire or cable to pay out into the trench as directly as practical. Seal the<br />

ends <strong>of</strong> each run <strong>of</strong> duct cable in the same manner as conduit as each run is<br />

installed.<br />

Do not install duct cable when the temperature <strong>of</strong> the duct-cable cannot be kept<br />

above 32° F (0° C) except with the permission <strong>of</strong> the Engineer.<br />

If the end <strong>of</strong> a wire or cable or duct must st<strong>and</strong> exposed to the elements or<br />

construction activities, protect said exposed end by enclosing it in a plastic bag or<br />

wrapping it with tape until the termination or connection can be made.<br />

625.18 Connections. Make each wire <strong>and</strong> cable connection above grade (i.e.<br />

bases <strong>of</strong> light poles or light towers, junction boxes on structure or in concrete<br />

barrier medians, etc.) with an approved cable connector kit. Use quick disconnect<br />

type kits in the base <strong>of</strong> each light pole with a fused type in each line or phase<br />

conductor. Plug unused line side wire opening in each connector kit installed in<br />

the base <strong>of</strong> the light pole at the outer end <strong>of</strong> a circuit.<br />

Make each cable connection below grade (i.e. pull boxes, junction boxes in<br />

retaining walls, etc.) with a cable splicing kit.<br />

Protect partially assembled connections from damage <strong>and</strong> the elements.<br />

625.19 Testing <strong>of</strong> Installations. Furnish equipment <strong>and</strong> personnel to perform<br />

each test as an incidental to the construction <strong>of</strong> the lighting installation. The<br />

Engineer shall witness each test <strong>and</strong> judge the results.<br />

A. Equipment Calibration. Submit to the Engineer the types, styles, or catalog<br />

numbers <strong>of</strong> all testing equipment to be used for such tests. Include a current<br />

Certificate <strong>of</strong> Calibration for each instrument showing that the instrument is in<br />

current calibration using st<strong>and</strong>ards traceable to The National Institute <strong>of</strong> St<strong>and</strong>ards<br />

in accordance with the manufacturer's recommended process by a service center<br />

authorized by the manufacturer to calibrate the instrument. Certify <strong>and</strong><br />

demonstrate to the satisfaction <strong>of</strong> the Engineer that the instrument has remained<br />

sealed since the calibration, <strong>and</strong> that the manufacturer's recommended process for<br />

ensuring that the instrument is in working order <strong>and</strong> producing valid results has<br />

been followed in conducting the test.<br />

B. Grounding Electrodes <strong>and</strong> Grounding Systems. Furnish two certified<br />

copies <strong>of</strong> the completed test records to the Engineer on test reporting forms<br />

supplied to the Contractor by the Engineer or on alternate forms approved by the<br />

Engineer.<br />

512

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!