2010 Construction and Material Specifications - Ohio Department of ...
2010 Construction and Material Specifications - Ohio Department of ... 2010 Construction and Material Specifications - Ohio Department of ...
622.06 A. Contraction Joints. The Contractor may construct unsealed contraction joints by either sawing, using metal inserts inside the forms, using a grooving tool, or using full-width 3/4-inch (19 mm) thick preformed joint filler conforming to 705.03. Make joints that are sawed, tooled, or formed by inserts a minimum of 1/8 inch (3 mm) wide and 3 inches (75 mm) deep. Saw joints as soon as curing allows sawing to the required depth with minimal spalling of the concrete surface. B. Expansion Joints. Use 3/4-inch (19 mm) preformed joint filler conforming to 705.03 to construct expansion joints at the centerline of and around each bridge pier column and on either side of each sign support foundation. C. Horizontal Construction Joints. If and as shown on the plans, the Contractor may place horizontal construction joints. 622.06 Finish. Immediately following removal of fixed forms or slip-form construction, check the surface of the barrier with a straightedge and correct all irregularities of more than 1/4 inch in 10 feet (6 mm in 3 m). Finish and make corrections to the barrier surface according to 511.18. 622.07 Curing. Cure concrete according to 511.17, Method B and the following additional requirements. Apply the curing compound using an approved mechanical sprayer equipped with a shield to protect the spray from wind. For small areas, the Engineer will allow the use of other acceptable methods. Do not apply any load or conduct any work that will damage newly placed concrete. Allow a minimum of 36 hours of cure time to elapse on any concrete placed first at a horizontal construction joint. The Contractor may cure precast sections according to 515.15. With the Engineer’s approval, the Contractor may also use radiant heated forms for curing. The Contractor may use 511.17, Method A for curing of short sections of barrier (leave-outs); however, before the curing is completed for any leave-outs, apply material conforming to 705.07, Type 2 at the normal rate specified in 511.17, Method B. The Contractor may cure horizontal construction joints between the foundation and the upper portion of the barrier, and between portions of the upper barrier placed separately according to 511.17, Method A or B. Do not remove the membrane before placing the next portion of the concrete barrier. 622.08 Method of Measurement. The Department will measure Concrete Barrier by the number of feet (meters) along the centerline of the top of the barrier, including all transitions, end terminals, and bridge pier sections as specified, complete in place. The Department will measure Portable Concrete Barrier and Portable Concrete Barrier, Bridge Mounted by the number of feet (meters) for each application of the barrier placed according to the plans. The Department will measure each re-use of barrier sections at a different location required by the plans separately. The Department will not measure repaired or replacement barrier sections damaged during handling or by traffic. 500
622.09 622.09 Basis of Payment. The cost of all inserts, sleeves, fittings, connectors, reinforcement, dowels, preformed filler, excavation, and backfill is incidental to these items. The Department will pay for accepted quantities at the contract prices as follows: Item Unit Description 622 Foot (Meter) Concrete Barrier, Type ___ 622 Foot (Meter) Portable Concrete Barrier, ___" (___ mm) 622 Foot (Meter) Portable Concrete Barrier, ___" (___ mm) Bridge Mounted ITEM 623 CONSTRUCTION LAYOUT STAKES 623.01 Description 623.02 General 623.03 Basis of Payment 623.01 Description. This work consists of furnishing, placing, and maintaining construction layout stakes necessary for the proper prosecution of the work under the contract and removing all stakes at the completion of the project. 623.02 General. The Department will locate and reference to either strategically placed Project Control Monuments and Project Geometric Layout Coordinate data or Centerline of Construction points with 3 point reference ties as shown in the plans. The Department will establish benchmarks along the line of the improvement outside construction limits. The Department will establish one benchmark for use at each structure with a span greater than 20 feet (6.1 m). The Department will not locate the centerline of short street intersection returns. Locating and referencing the centerline consists of locating and referencing control points such as point of curve, point of tangent, and sufficient points on tangent to provide a line of sight. Establish reference points outside the construction limits in such a manner that they will be available to reestablish the control points at any time during the course of the work. The Engineer will identify to the Contractor control points set by the Department and will keep the field notes in the field office. Furnish field forces and set all additional stakes for the project, including interchanges, that are needed to establish offset stakes, reference points, slope stakes, pavement and curb line and grade, stakes for bridges, culverts, sewers and drainage structures, paved gutters, walls, monuments, fence, Right-of-Way lines, and any other horizontal or vertical controls, including supplementary benchmarks, necessary to secure a correct layout of the work. Determine the location of slope stakes for grading work by a calculation method, and make a copy of these calculations available to the Engineer for the project records. Set stakes for the line and grade of pavement and curb at sufficient station intervals but not exceeding 50 feet (20 m) to ensure conformance to plan line and grade. Staking of Right-of-Way lines consists of placing tall stakes, properly identified and readily discernible, at points of change in width or direction of the Right-of-Way line and 501
- Page 455 and 456: 449 605.03 If the size of the under
- Page 457 and 458: 605.07 Construct the underdrains ou
- Page 459 and 460: 453 606.04 Space Type 5A guardrail
- Page 461 and 462: 607.05 Horizontal Deflection 607.06
- Page 463 and 464: 457 607.10 607.10 Basis of Payment.
- Page 465 and 466: 608.09 The Department will measure
- Page 467 and 468: 461 609.04 portions of adjacent sec
- Page 469 and 470: 463 609.07 Where medians and traffi
- Page 471 and 472: 465 610.04 Use metal sheets with a
- Page 473 and 474: 467 610.09 610.09 Basis of Payment.
- Page 475 and 476: 469 613.06 The Contractor may use f
- Page 477 and 478: 614.03 B. When the highway under co
- Page 479 and 480: 473 614.06 614.055 Surface Conditio
- Page 481 and 482: 475 614.11 A. Acceptability and Exp
- Page 483 and 484: 614.11 Apply Class I work zone mark
- Page 485 and 486: 479 614.11 passing zone and places
- Page 487 and 488: 481 614.12 approximately 4 inches (
- Page 489 and 490: Line Type Normal Spacing Feet (Mete
- Page 491 and 492: B. Work zone signal, pole, or contr
- Page 493 and 494: 615.05 specified in Item 606, excep
- Page 495 and 496: 489 616.01 616.01 Description. This
- Page 497 and 498: TABLE 617.06-1 Material Conversion
- Page 499 and 500: 493 619.02 Furnish neat, sanitary,
- Page 501 and 502: 495 620.03 620.03 Layout. Lay out a
- Page 503 and 504: 497 621.05 When a casting is insert
- Page 505: 499 621.10 The Department will meas
- Page 509 and 510: 624.03 Method of Measurement 624.04
- Page 511 and 512: 505 625.01 625.01 Description. This
- Page 513 and 514: 625.10 Ensure that the grounding co
- Page 515 and 516: 509 625.13 grounding conductor that
- Page 517 and 518: 511 625.16 625.16 Grounding. Connec
- Page 519 and 520: 513 625.19 Measure the earth resist
- Page 521 and 522: Pull boxes include the aggregate fo
- Page 523 and 524: 517 625.23 except for a power servi
- Page 525 and 526: 519 626.04 The Contractor may vary
- Page 527 and 528: Concrete, Class C..................
- Page 529 and 530: 523 630.04 panels to achieve the si
- Page 531 and 532: 525 630.06 galvanize steel structur
- Page 533 and 534: 527 630.07 Provide for the attachme
- Page 535 and 536: Remove temporary overlay signs so a
- Page 537 and 538: 630.15 The Department will measure
- Page 539 and 540: 631.08 Controls 631.09 Electrical S
- Page 541 and 542: 535 631.07 install the nipple. Ensu
- Page 543 and 544: Item Unit Description 631 Each Sign
- Page 545 and 546: 539 632.04 Ensure that major items
- Page 547 and 548: 541 632.06 Upon acceptance of the p
- Page 549 and 550: 543 632.15 against undisturbed soil
- Page 551 and 552: 545 632.23 Support cables installed
- Page 553 and 554: 547 632.28 complete test records, t
- Page 555 and 556: 549 632.30 include excavation, dewa
622.06<br />
A. Contraction Joints. The Contractor may construct unsealed contraction<br />
joints by either sawing, using metal inserts inside the forms, using a grooving tool,<br />
or using full-width 3/4-inch (19 mm) thick preformed joint filler conforming to<br />
705.03. Make joints that are sawed, tooled, or formed by inserts a minimum <strong>of</strong> 1/8<br />
inch (3 mm) wide <strong>and</strong> 3 inches (75 mm) deep. Saw joints as soon as curing allows<br />
sawing to the required depth with minimal spalling <strong>of</strong> the concrete surface.<br />
B. Expansion Joints. Use 3/4-inch (19 mm) preformed joint filler conforming<br />
to 705.03 to construct expansion joints at the centerline <strong>of</strong> <strong>and</strong> around each bridge<br />
pier column <strong>and</strong> on either side <strong>of</strong> each sign support foundation.<br />
C. Horizontal <strong>Construction</strong> Joints. If <strong>and</strong> as shown on the plans, the<br />
Contractor may place horizontal construction joints.<br />
622.06 Finish. Immediately following removal <strong>of</strong> fixed forms or slip-form<br />
construction, check the surface <strong>of</strong> the barrier with a straightedge <strong>and</strong> correct all<br />
irregularities <strong>of</strong> more than 1/4 inch in 10 feet (6 mm in 3 m). Finish <strong>and</strong> make<br />
corrections to the barrier surface according to 511.18.<br />
622.07 Curing. Cure concrete according to 511.17, Method B <strong>and</strong> the<br />
following additional requirements. Apply the curing compound using an approved<br />
mechanical sprayer equipped with a shield to protect the spray from wind. For<br />
small areas, the Engineer will allow the use <strong>of</strong> other acceptable methods.<br />
Do not apply any load or conduct any work that will damage newly placed<br />
concrete. Allow a minimum <strong>of</strong> 36 hours <strong>of</strong> cure time to elapse on any concrete<br />
placed first at a horizontal construction joint. The Contractor may cure precast<br />
sections according to 515.15. With the Engineer’s approval, the Contractor may<br />
also use radiant heated forms for curing.<br />
The Contractor may use 511.17, Method A for curing <strong>of</strong> short sections <strong>of</strong><br />
barrier (leave-outs); however, before the curing is completed for any leave-outs,<br />
apply material conforming to 705.07, Type 2 at the normal rate specified in<br />
511.17, Method B.<br />
The Contractor may cure horizontal construction joints between the foundation<br />
<strong>and</strong> the upper portion <strong>of</strong> the barrier, <strong>and</strong> between portions <strong>of</strong> the upper barrier<br />
placed separately according to 511.17, Method A or B. Do not remove the<br />
membrane before placing the next portion <strong>of</strong> the concrete barrier.<br />
622.08 Method <strong>of</strong> Measurement. The <strong>Department</strong> will measure Concrete<br />
Barrier by the number <strong>of</strong> feet (meters) along the centerline <strong>of</strong> the top <strong>of</strong> the barrier,<br />
including all transitions, end terminals, <strong>and</strong> bridge pier sections as specified,<br />
complete in place.<br />
The <strong>Department</strong> will measure Portable Concrete Barrier <strong>and</strong> Portable Concrete<br />
Barrier, Bridge Mounted by the number <strong>of</strong> feet (meters) for each application <strong>of</strong> the<br />
barrier placed according to the plans. The <strong>Department</strong> will measure each re-use <strong>of</strong><br />
barrier sections at a different location required by the plans separately.<br />
The <strong>Department</strong> will not measure repaired or replacement barrier sections<br />
damaged during h<strong>and</strong>ling or by traffic.<br />
500