05.01.2013 Views

2010 Construction and Material Specifications - Ohio Department of ...

2010 Construction and Material Specifications - Ohio Department of ...

2010 Construction and Material Specifications - Ohio Department of ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

461<br />

609.04<br />

portions <strong>of</strong> adjacent sections <strong>of</strong> curbing with 1/8-inch (3 mm) thick expansion joint<br />

material. Trim expansion joint material flush with the curbing on all edges.<br />

If placing s<strong>and</strong>stone curb after placing pavement, fill remaining joints with dry<br />

s<strong>and</strong> to within 2 inches (50 mm) <strong>of</strong> the surface <strong>of</strong> the pavement, <strong>and</strong> fill to the<br />

pavement surface with asphalt concrete. Take care in filling this joint so that no<br />

asphalt concrete comes in contact with the exposed surface <strong>of</strong> the curb.<br />

D. Reusing Existing as New Curb. If specifically allowed by the plans, <strong>and</strong> to<br />

the extent available, use acceptable stone curb sections removed under Item 202<br />

instead <strong>of</strong> furnishing new stone curb. Use salvaged curb at locations designated by<br />

the Engineer. Place all salvaged sections <strong>of</strong> curb continuously without<br />

interspersing salvaged <strong>and</strong> new curb sections. Haul <strong>and</strong> store salvaged curb as<br />

necessary. Cut, dress, set, <strong>and</strong> install joints in salvaged curbs according to the<br />

requirements for new curbs.<br />

609.04 Cast-in-Place Concrete Curb <strong>and</strong> Combination Curb <strong>and</strong> Gutter.<br />

A. Forms <strong>and</strong> Joints. Use approved steel forms for curbs. Securely brace <strong>and</strong><br />

hold forms to the line <strong>and</strong> grade shown on the plans. The Contractor may use<br />

approved flexible forms <strong>of</strong> steel or wood to construct the radius <strong>of</strong> a circular curb<br />

200 feet (60 m) or less. Immediately before placing concrete, clean the inner<br />

surface <strong>of</strong> the forms, <strong>and</strong> coat this surface with a form release agent.<br />

Where curb <strong>and</strong> combination curb <strong>and</strong> gutter is not constructed integral with,<br />

or tied to, the base or pavement, construct 1/4-inch (6 mm) wide contraction joints<br />

at 10-foot (3 m) intervals using steel separator plates, a grooving tool, or a saw<br />

according to Item 451. For combination curb <strong>and</strong> gutter, construct the joint to an<br />

average depth <strong>of</strong> 2 inches (50 mm) or more. For curb, construct the joint to an<br />

average depth <strong>of</strong> one-fifth or more <strong>of</strong> the curb height. Where expansion joints<br />

occur in the abutting pavement, separate the section being placed with 1-inch (25<br />

mm) 705.03 preformed filler.<br />

Where the curb is integral with, or tied to, the base or pavement, construct<br />

the same type <strong>of</strong> joints as used in the pavement. Space joints identically with the<br />

joints in the base or pavement.<br />

Leave curb forms in place until their removal will not crack, shatter, or<br />

otherwise injure the concrete. Do not seal transverse joints in cast-in-place<br />

concrete curb <strong>and</strong> combination curb <strong>and</strong> gutter.<br />

If curbs are to later serve as a support for a finishing machine in the placing<br />

<strong>of</strong> a surface course, align supporting edges so that the distance between the curbs<br />

is within 1/2 inch (13 mm) from that specified.<br />

B. Placing. Place concrete in forms prepared as described above, <strong>and</strong> vibrate<br />

the concrete to eliminate all voids.<br />

Place concrete for curb that is integral with the concrete base or pavement<br />

while the base or pavement concrete is plastic. Where the presence <strong>of</strong> the<br />

finishing equipment on the forms at the end <strong>of</strong> the day’s run prevents completing<br />

the curb, install No. 5 (No. 16M) tie bars vertically in the pavement at 1-foot (0.3<br />

m) intervals <strong>and</strong> in a line 3 inches (75 mm) inside <strong>of</strong> <strong>and</strong> parallel to the pavement<br />

edge. Install these tie bars to within 1 1/2 inches (38 mm) <strong>of</strong> the subgrade or

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!