2010 Construction and Material Specifications - Ohio Department of ...
2010 Construction and Material Specifications - Ohio Department of ... 2010 Construction and Material Specifications - Ohio Department of ...
515.02 515.02 Fabricator Approval Procedure. Select fabricators that are prequalified and evaluated by the Office of Materials Management (OMM) according to Supplement 1079 and listed by the Department before the Contract letting Date. 515.03 Levels of Fabricator Qualification. There are three levels of fabricator qualification. The Laboratory will classify each fabricator at the highest level of fabrication it is qualified to perform. Level Description of Capabilities 1 Straight strand prestressed box beam members 2 Straight strand prestressed I-beam members 3 Draped strand prestressed I-beam members 515.04 General. Produce all members according to Item 511, except as otherwise specified herein. 515.05 Fabricator Documentation Responsibility. The fabricator shall keep and maintain records for each project bid line number concerning: A. Fabricator plant approval. B. Shop drawing approval. C. Material test reports. D. Welding qualifications. E. Quality Control Plan (QCP) per Supplement 1079. The fabricator shall provide access to the above records for audit, inspection, and copying. Provide a copy of the complete records at the completion and final shipment of the work. The Fabricator shall retain all documentation for at least 5 years from the date of final shipment from the fabrication shop. The fabricator shall document all Quality Control (QC) activities to verify the fabrication conforms to the specification requirements. QC activities include material quality checks, dimensional checks, weld inspections, strand tensioning procedures, release procedures, post-pour inspections, concrete strengths at release of strand and final strength of concrete before shipment, cleaning operations, coating applications, final QC inspections, repairs and all other QC procedures required to provide a prestress concrete member conforming to the specifications. Supplement 1079 defines the quality control plan evaluation process and quality control plan enhancement process The Department will perform a quality assurance (QA) evaluation of the fabricator’s quality control performance using forms in Supplement 1079 and will include both validation of the fabricator’s actual records of inspection and Department inspection. 515.06 Shop Drawings. Provide shop drawings conforming to 501.04 and the following requirements. Include all details, dimensions, dimensional tolerances, size of materials, lifting devices, inserts, reinforcing steel supports, fabricator incorporated reinforcing, piece mark diagrams for field connection and erection of any steel and all prestress 384
385 515.07 members, and all other information necessary for the complete fabrication and erection of the prestressed members. Show all items that will be incorporated into each prestressed member. Provide the detensioning procedure and pattern conforming to 515.16. 515.07 Pre-Fabrication Meeting. At least 7 days after the Department receives shop drawings, conduct a pre-fabrication meeting at the fabricator’s facilities, or another location agreed to by all parties. As part of the pre-fabrication meeting request, provide a initial fabrication schedule for the prestressed beam project including: A. Start date for fabrication of the project B. Expected phasing of fabrication, if any C. Number of workdays for the project and length of work day D. Quality control final inspection date The fabricator’s production manager, quality control specialists (QCS) for the project, the Department’s inspector, and the Contractor, or its designated representative, shall attend the meeting. The meeting is to review fabrication issues, including information on shop drawings, previous QC/QA inspection issues, QC and Quality Assurance inspection hold points, unique and special fabrication items, and special processes. The QCS will conduct the meeting and record and distribute meeting minutes that document all issues discusses. Begin fabrication when all meeting issues have been resolved. Office of Material Management may waive the pre-fabrication meeting if accepted by the Fabricator and the Contractor. If Contractor submitted shop drawings do not comply with the requirements of 515.06, no pre-fabrication meeting can be scheduled or waived. 515.08 Materials. Furnish materials conforming to: Reinforcing steel .......................................................... 509 Concrete .................................................................. 515.15 Portland cement ................................... 701.01 thru 701.09 Aggregate*.............................................................. 703.02 Air-entraining admixture ........................................ 705.10 Chemical admixtures for concrete .......................... 705.12 Prestressing steel ..................................................... 711.27 Transverse tie rods .................................................. 711.01 * For fine aggregate, use natural sand for members without a separate wearing course. Modify coarse aggregate as follows: Do not allow more than 0.4 percent deleterious materials. For gradation, use No. 57, 6, 67, 68, 7, 78, or 8 size coarse aggregate. 515.09 Materials Approval. The fabricator shall control, test, and validate material requirements for all materials either incorporated into the prestressed fabricated item or supplied under Item 515 as component parts to the fabricated
- Page 339 and 340: 333 512.04 markings according to Se
- Page 341 and 342: 335 512.06 Engineer with written in
- Page 343 and 344: 337 512.07 200 psi (1400kPa) max.,
- Page 345 and 346: 339 512.08 applying the waterproofi
- Page 347 and 348: 341 512.09 512.09 Method of Measure
- Page 349 and 350: 343 513.03 The Office of Materials
- Page 351 and 352: 345 513.05 513.05 Fabricator Docume
- Page 353 and 354: 347 513.12 before assembly. During
- Page 355 and 356: 349 513.18 for up to 5-inch (127 mm
- Page 357 and 358: TABLE 513.20-1M Bolt Size (mm) To d
- Page 359 and 360: TABLE 513.20-2M 353 513.20 Bolt Siz
- Page 361 and 362: 355 513.23 each workday, when weldi
- Page 363 and 364: 357 513.25 A. Radiographic Inspecti
- Page 365 and 366: 359 513.26 The fabrication quality
- Page 367 and 368: 361 513.30 The Department will not
- Page 369 and 370: 363 514.04 The quality control spec
- Page 371 and 372: 365 514.05 inspection identifies a
- Page 373 and 374: 367 514.07 continuously and uniform
- Page 375 and 376: 369 514.11 supporting 250 pounds (1
- Page 377 and 378: 371 514.13 1. For an automated blas
- Page 379 and 380: SW 846 Regulatory Concentration Ana
- Page 381 and 382: 375 514.17 Except for primer, mix p
- Page 383 and 384: 377 514.18 If mud cracking occurs,
- Page 385 and 386: 514.20 F. Measure other areas or re
- Page 387 and 388: 514.23 immediately before applying
- Page 389: Item Unit Description 514 Square Fo
- Page 393 and 394: 515.13 according to a method accept
- Page 395 and 396: 515.15 production. When using admix
- Page 397 and 398: 391 515.17 BEAM DIMENSIONAL TOLERAN
- Page 399 and 400: 393 515.20 support locations. Durin
- Page 401 and 402: 395 516.04 516.03 Coating. Coat exp
- Page 403 and 404: 397 516.09 feet (meters) horizontal
- Page 405 and 406: Scuppers, structural steel and cast
- Page 407 and 408: 401 518.10 518.10 Basis of Payment.
- Page 409 and 410: 519.08 columns, the Department will
- Page 411 and 412: 405 520.05 and two times the weight
- Page 413 and 414: 407 520.11 520.11 Inspection and Te
- Page 415 and 416: Concrete footings will be paid for
- Page 417 and 418: 411 524.02 plan requirements, with
- Page 419 and 420: 413 524.05 groundwater must be cont
- Page 421 and 422: 415 524.08 Determine density, visco
- Page 423 and 424: 417 524.13 parts, do not allow thes
- Page 425 and 426: ITEM 526 APPROACH SLABS 526.01 Desc
- Page 427 and 428: 600 INCIDENTALS ITEM 601 SLOPE AND
- Page 429 and 430: 423 601.05 Stretchers are bags plac
- Page 431 and 432: 425 601.12 mm) wide at the surface;
- Page 433 and 434: 427 602.03 602.03 Construction Requ
- Page 435 and 436: Soil and granular embankment ......
- Page 437 and 438: paved invert ......................
- Page 439 and 440: Polyvinyl chloride sanitary pipe ..
515.02<br />
515.02 Fabricator Approval Procedure. Select fabricators that are prequalified<br />
<strong>and</strong> evaluated by the Office <strong>of</strong> <strong>Material</strong>s Management (OMM) according<br />
to Supplement 1079 <strong>and</strong> listed by the <strong>Department</strong> before the Contract letting Date.<br />
515.03 Levels <strong>of</strong> Fabricator Qualification. There are three levels <strong>of</strong><br />
fabricator qualification. The Laboratory will classify each fabricator at the highest<br />
level <strong>of</strong> fabrication it is qualified to perform.<br />
Level Description <strong>of</strong> Capabilities<br />
1 Straight str<strong>and</strong> prestressed box beam members<br />
2 Straight str<strong>and</strong> prestressed I-beam members<br />
3 Draped str<strong>and</strong> prestressed I-beam members<br />
515.04 General. Produce all members according to Item 511, except as<br />
otherwise specified herein.<br />
515.05 Fabricator Documentation Responsibility. The fabricator shall keep<br />
<strong>and</strong> maintain records for each project bid line number concerning:<br />
A. Fabricator plant approval.<br />
B. Shop drawing approval.<br />
C. <strong>Material</strong> test reports.<br />
D. Welding qualifications.<br />
E. Quality Control Plan (QCP) per Supplement 1079.<br />
The fabricator shall provide access to the above records for audit, inspection, <strong>and</strong><br />
copying. Provide a copy <strong>of</strong> the complete records at the completion <strong>and</strong> final<br />
shipment <strong>of</strong> the work. The Fabricator shall retain all documentation for at least 5<br />
years from the date <strong>of</strong> final shipment from the fabrication shop.<br />
The fabricator shall document all Quality Control (QC) activities to verify the<br />
fabrication conforms to the specification requirements. QC activities include<br />
material quality checks, dimensional checks, weld inspections, str<strong>and</strong> tensioning<br />
procedures, release procedures, post-pour inspections, concrete strengths at release<br />
<strong>of</strong> str<strong>and</strong> <strong>and</strong> final strength <strong>of</strong> concrete before shipment, cleaning operations,<br />
coating applications, final QC inspections, repairs <strong>and</strong> all other QC procedures<br />
required to provide a prestress concrete member conforming to the specifications.<br />
Supplement 1079 defines the quality control plan evaluation process <strong>and</strong> quality<br />
control plan enhancement process<br />
The <strong>Department</strong> will perform a quality assurance (QA) evaluation <strong>of</strong> the<br />
fabricator’s quality control performance using forms in Supplement 1079 <strong>and</strong> will<br />
include both validation <strong>of</strong> the fabricator’s actual records <strong>of</strong> inspection <strong>and</strong><br />
<strong>Department</strong> inspection.<br />
515.06 Shop Drawings. Provide shop drawings conforming to 501.04 <strong>and</strong> the<br />
following requirements.<br />
Include all details, dimensions, dimensional tolerances, size <strong>of</strong> materials, lifting<br />
devices, inserts, reinforcing steel supports, fabricator incorporated reinforcing,<br />
piece mark diagrams for field connection <strong>and</strong> erection <strong>of</strong> any steel <strong>and</strong> all prestress<br />
384