511.15 minimum cure period of 5 days, reduce the concrete surface temperature at a rate not to exceed 20 °F (11 °C) in 24 hours until the concrete surface temperature is within 20 °F (11 °C) of atmospheric temperature. Install sufficient high-low thermometers to readily determine the concrete surface temperature. For deck slabs, install high-low thermometers to measure deck bottom surfaces, deck fascia surfaces, and deck top surfaces. Maintain the concrete curing temperature using a heated enclosure, insulated forms, or by flooding, except cure deck slabs less than 10 inches (250 mm) thick using more than just insulated forms. Remove falsework and open cold weather concrete to traffic according to 511.17. A. Heated Enclosure. Construct the heated enclosure to surround the top, sides, and bottom of the concrete. Construct strong and wind proof enclosures that contain adequate space to allow free circulation of air around the forms and concrete. Before placing concrete, construct the enclosure and heating devices to the extent allowed by the concrete operation. As the concreting operation progresses and as soon as possible after placing concrete, complete construction of the enclosures and apply heat. Supply heat by a method that continuously maintains a reasonably uniform temperature throughout the enclosures and does not discolor the concrete. Vent combustion-type heating devices outside the enclosure. If dry heat, other than free steam, maintains the enclosure temperature, immediately cover exposed concrete with two thicknesses of burlap. Continuously wet the burlap and, except for required rubbing of the concrete, do not remove the burlap during the heating period. If wood forms without liners are left in place more than 2 days after the placing of concrete, thoroughly wet the forms at least once each day for the remainder of the heating period. If forms are removed during the heating period, thoroughly drench the concrete with water and, for the remainder of the heating period, cover and wet the concrete with burlap as specified above. B. Insulation. Install sufficient thermometers to readily determine the concrete surface temperature. If the surface temperature approaches 100 °F (38 °C), loosen or otherwise vent the forms or insulation to keep the surface temperature within the limits specified above. If insulation does not maintain the minimum required temperature, promptly enclose the concrete as specified in 511.15.A or flood the concrete as specified in 511.15.C. Use a wind and water resistant insulating material. Ensure edges, corners, and other points of extreme exposure are adequately insulated. Place a tarpaulin or other Engineer approved waterproof cover over the insulation to protect the concrete top surface. C. Flooding with Water. The Contractor may flood the concrete with water provided flooding does not damage the concrete. Heat the water to a temperature 320
321 511.16 from 50 to 100 °F (10 to 38 °C). The Contractor may stop using heated water after 48 hours if the concrete remains flooded to a depth of 1 foot (0.3 m) above its highest elevation for at least the next 120 hours. 511.16 Removal of Forms. To facilitate finishing, remove forms from vertical surfaces that receive a rubbed surface finish as soon as the concrete has hardened sufficiently that rubbing will not damage it. 511.17 Curing and Loading. Remove falsework and open structures to traffic after the concrete has cured for the time specified by Table 511.17-1. Removing Falsework TABLE 511.17-1 Age of Concrete in Days Span[1] No Beam Beam Test [2] Over 10 feet (3 m) Test 14 5 10 feet (3 m) or less and all pier caps 7 3 Traffic [3] Any 14 7 [1] Span is defined as the horizontal distance between faces of the supporting elements when measured parallel to the primary reinforcement. [2] Applicable only when the average modulus of rupture for two tests is not less than 650 psi (4.5 MPa). [3] When placing Class HP concrete for a superstructure between October 15 and March 15, open the deck to traffic no sooner than 30 days after placement. If the air temperature surrounding the concrete is maintained between 32 and 50 °F (0 and 10 °C), and if the provisions of 511.15 do not apply, maintain the concrete above 32 °F (0 °C) for 7 days or until a successful beam test, except this time shall not be less than 5 days. If a beam test is not performed, maintain the air temperature surrounding the concrete above 50 °F (10 °C) for 7 days. Extend the 7-day period and the times for removing falsework and opening to traffic one hour for each hour the temperature of the air surrounding the concrete is below 50 °F (10 °C) and until the concrete has experienced 7 days, or 168 hours, of temperature above 50 °F (10 °C). Cure concrete as follows: Location Curing Method [1] Superstructure concrete Method A Concrete to which sealer is applied Method A Construction joints Method A Top surface of Class HP concrete deck superstructure concrete Method A followed by Method B Concrete with waterproofing Method A or Method B All other concrete Method A or Method B [1] Method A is water curing. Method B is membrane curing. If using Method B on areas to be waterproofed, remove the curing membrane. Do not install compression rings on pier columns or similar items of construction for supporting falsework or subsequent construction until after a 72hour curing period.
- Page 275 and 276: 269 499.03 C. Concrete Classes. Usi
- Page 277 and 278: TABLE 499.03-4 CLASS HP CONCRETE 27
- Page 279 and 280: 273 499.04 However, do not change t
- Page 281 and 282: TABLE 499.04-2 OPTION 2 CONCRETE (C
- Page 283 and 284: 277 499.06 rigid pavement removal a
- Page 285 and 286: TABLE 499.08-1 EVERY BATCH TICKET N
- Page 287 and 288: 281 499.09 When approved by the Eng
- Page 289 and 290: 283 501.04 Prepare the shop drawing
- Page 291 and 292: 285 501.05 drawing at least 24 hour
- Page 293 and 294: 287 501.05 ii. Erection sequence fo
- Page 295 and 296: 289 502.01 Accompany all certified
- Page 297 and 298: 291 503.01 503.01 Description. This
- Page 299 and 300: 293 503.08 503.08 Backfill. Backfil
- Page 301 and 302: 295 504.01 provide the minimum cove
- Page 303 and 304: 297 506.03 limits of the footing 3
- Page 305 and 306: 299 506.04 506.04 Basis of Payment.
- Page 307 and 308: 507.05 Do not use a follower unless
- Page 309 and 310: 303 507.11 (75 mm) above the elevat
- Page 311 and 312: 305 508.03 To compensate for falsew
- Page 313 and 314: 509.09 Epoxy Coated Reinforcing Ste
- Page 315 and 316: TABLE 509.05-1M STANDARD BENDS Dime
- Page 317 and 318: 311 509.10 If repair is required, c
- Page 319 and 320: 511.03 Proportions 511.04 Mix Optio
- Page 321 and 322: 511.09 511.09 Slump. Within the slu
- Page 323 and 324: FIGURE 1 ACI 308-81 511.11 Slipform
- Page 325: 319 511.13 of principal stress and
- Page 329 and 330: 323 511.19 corners or edges, and ot
- Page 331 and 332: 325 511.21 expansion joints. Saw gr
- Page 333 and 334: 327 511.25 511.25 Basis of Payment.
- Page 335 and 336: 329 512.03 Do not mix or apply the
- Page 337 and 338: 2. Non-epoxy sealer. 331 512.03 a.
- Page 339 and 340: 333 512.04 markings according to Se
- Page 341 and 342: 335 512.06 Engineer with written in
- Page 343 and 344: 337 512.07 200 psi (1400kPa) max.,
- Page 345 and 346: 339 512.08 applying the waterproofi
- Page 347 and 348: 341 512.09 512.09 Method of Measure
- Page 349 and 350: 343 513.03 The Office of Materials
- Page 351 and 352: 345 513.05 513.05 Fabricator Docume
- Page 353 and 354: 347 513.12 before assembly. During
- Page 355 and 356: 349 513.18 for up to 5-inch (127 mm
- Page 357 and 358: TABLE 513.20-1M Bolt Size (mm) To d
- Page 359 and 360: TABLE 513.20-2M 353 513.20 Bolt Siz
- Page 361 and 362: 355 513.23 each workday, when weldi
- Page 363 and 364: 357 513.25 A. Radiographic Inspecti
- Page 365 and 366: 359 513.26 The fabrication quality
- Page 367 and 368: 361 513.30 The Department will not
- Page 369 and 370: 363 514.04 The quality control spec
- Page 371 and 372: 365 514.05 inspection identifies a
- Page 373 and 374: 367 514.07 continuously and uniform
- Page 375 and 376: 369 514.11 supporting 250 pounds (1
511.15<br />
minimum cure period <strong>of</strong> 5 days, reduce the concrete surface temperature at a rate<br />
not to exceed 20 °F (11 °C) in 24 hours until the concrete surface temperature is<br />
within 20 °F (11 °C) <strong>of</strong> atmospheric temperature.<br />
Install sufficient high-low thermometers to readily determine the concrete<br />
surface temperature. For deck slabs, install high-low thermometers to measure<br />
deck bottom surfaces, deck fascia surfaces, <strong>and</strong> deck top surfaces.<br />
Maintain the concrete curing temperature using a heated enclosure, insulated<br />
forms, or by flooding, except cure deck slabs less than 10 inches (250 mm) thick<br />
using more than just insulated forms.<br />
Remove falsework <strong>and</strong> open cold weather concrete to traffic according to<br />
511.17.<br />
A. Heated Enclosure. Construct the heated enclosure to surround the top,<br />
sides, <strong>and</strong> bottom <strong>of</strong> the concrete. Construct strong <strong>and</strong> wind pro<strong>of</strong> enclosures that<br />
contain adequate space to allow free circulation <strong>of</strong> air around the forms <strong>and</strong><br />
concrete.<br />
Before placing concrete, construct the enclosure <strong>and</strong> heating devices to the<br />
extent allowed by the concrete operation. As the concreting operation progresses<br />
<strong>and</strong> as soon as possible after placing concrete, complete construction <strong>of</strong> the<br />
enclosures <strong>and</strong> apply heat. Supply heat by a method that continuously maintains a<br />
reasonably uniform temperature throughout the enclosures <strong>and</strong> does not discolor<br />
the concrete.<br />
Vent combustion-type heating devices outside the enclosure.<br />
If dry heat, other than free steam, maintains the enclosure temperature,<br />
immediately cover exposed concrete with two thicknesses <strong>of</strong> burlap. Continuously<br />
wet the burlap <strong>and</strong>, except for required rubbing <strong>of</strong> the concrete, do not remove the<br />
burlap during the heating period.<br />
If wood forms without liners are left in place more than 2 days after the<br />
placing <strong>of</strong> concrete, thoroughly wet the forms at least once each day for the<br />
remainder <strong>of</strong> the heating period. If forms are removed during the heating period,<br />
thoroughly drench the concrete with water <strong>and</strong>, for the remainder <strong>of</strong> the heating<br />
period, cover <strong>and</strong> wet the concrete with burlap as specified above.<br />
B. Insulation. Install sufficient thermometers to readily determine the concrete<br />
surface temperature. If the surface temperature approaches 100 °F (38 °C), loosen<br />
or otherwise vent the forms or insulation to keep the surface temperature within<br />
the limits specified above. If insulation does not maintain the minimum required<br />
temperature, promptly enclose the concrete as specified in 511.15.A or flood the<br />
concrete as specified in 511.15.C.<br />
Use a wind <strong>and</strong> water resistant insulating material. Ensure edges, corners,<br />
<strong>and</strong> other points <strong>of</strong> extreme exposure are adequately insulated. Place a tarpaulin or<br />
other Engineer approved waterpro<strong>of</strong> cover over the insulation to protect the<br />
concrete top surface.<br />
C. Flooding with Water. The Contractor may flood the concrete with water<br />
provided flooding does not damage the concrete. Heat the water to a temperature<br />
320