05.01.2013 Views

2010 Construction and Material Specifications - Ohio Department of ...

2010 Construction and Material Specifications - Ohio Department of ...

2010 Construction and Material Specifications - Ohio Department of ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

505.01<br />

Item Unit Description<br />

504 Square Foot Steel Sheet Piling Left In Place [Minimum<br />

(Square Meter) Section Modulus <strong>of</strong>____ cubic inches<br />

per foot (____ mm 3 /m)] <strong>of</strong> Wall<br />

ITEM 505 PILE DRIVING EQUIPMENT MOBILIZATION<br />

505.01 Description<br />

505.02 Basis <strong>of</strong> Payment<br />

505.01 Description. This work consists <strong>of</strong> mobilizing pile driving equipment<br />

to <strong>and</strong> from the project site <strong>and</strong>, as necessary, to install the required piling.<br />

This work includes the fixed costs that are related to the installation <strong>of</strong> the<br />

required piling.<br />

505.02 Basis <strong>of</strong> Payment. The <strong>Department</strong> will pay for accepted quantities,<br />

after the first service pile is installed, at the contract price as follows:<br />

Item Unit Description<br />

505 Lump Sum Pile Driving Equipment Mobilization<br />

506.01 Description<br />

506.02 General<br />

506.03 Application <strong>of</strong> Load<br />

506.04 Basis <strong>of</strong> Payment<br />

ITEM 506 STATIC LOAD TEST<br />

506.01 Description. This work consists <strong>of</strong> applying a static load to a driven<br />

pile <strong>and</strong> furnishing instruments <strong>and</strong> facilities to obtain load-settlement data<br />

required to determine the ultimate bearing value <strong>of</strong> the pile. When subsequent<br />

static load tests are specified, the Office <strong>of</strong> Structural Engineering will determine<br />

whether subsequent static load tests are to be performed <strong>and</strong> the location <strong>of</strong> all<br />

piles to be tested.<br />

506.02 General. Use the hammer selected for driving the test pile to drive all<br />

piles represented by the test. If the Contractor finds it necessary to use a different<br />

hammer, the Office <strong>of</strong> Structural Engineering will determine if an additional static<br />

load test is necessary.<br />

If using anchor piles to apply the load to the test pile, locate the anchor piles not<br />

closer than 7 feet (2.1 m) center-to-center from the test pile. If possible, install<br />

anchor piles parallel to the axis <strong>of</strong> the test pile. The Contractor may use battered<br />

piles as anchor piles; provided the horizontal forces in the anchor system are<br />

balanced <strong>and</strong> excessive bending stresses are not induced in the piles. The<br />

Contractor may also use bearing piles meeting these requirements as anchor piles.<br />

After the test has been completed, remove or cut <strong>of</strong>f at least 1 foot (0.3 m) below<br />

the bottom <strong>of</strong> the footing or finished surface <strong>of</strong> the ground all anchor piles outside<br />

the limits <strong>of</strong> the footing. Cut <strong>of</strong>f anchor piles, other than bearing piles, within the<br />

296

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!