2010 Construction and Material Specifications - Ohio Department of ...
2010 Construction and Material Specifications - Ohio Department of ... 2010 Construction and Material Specifications - Ohio Department of ...
443.07 sample variability with SMA, a larger than usual sample size from which material is obtained for the various tests is required. 443.07 Construction. At least 24 hours prior to beginning a test strip meet with the Engineer and DET and provide a written summary of steps taken to assure mix quality and construction practices account for the special needs of SMA production and placement. Send a copy of the written summary to the Laboratory. A. Test Strips and JMF Adjustment. Do not begin full production of the SMA until receiving authorization from the District. This authorization will be based on the successful construction of one or more test strips. Test strips consist of 50 to 100 tons of SMA produced and placed in accordance with these specifications. Cease SMA production that day unless another test strip is needed. Place test strips in one continuous mat. The test strip will be included in the first lot for determining density for payment. Test strips are incidental to the pay item. During the construction of a test strip, perform 1 set of quality control tests as described above and obtain and test 3 random cores of the compacted pavement. Within 1 working day after a test strip is completed, the District, the Laboratory and the Contractor's Level 3 employee will determine if any changes in the SMA JMF, production, or placement procedures are needed. A redesign of the JMF or another test strip may be required. The Laboratory will notify the District of any JMF adjustments. Do not start production until notified by the District. B. Compaction. Start compaction immediately after the SMA has been placed by the paver. Use only steel wheel rollers. Vibratory rollers in vibratory mode, set at a high frequency and low amplitude, can be used as the breakdown roller only. Always operate the breakdown roller immediately behind the paver. If isolated, small fat spots develop, apply sand immediately during compaction. If continuous and/or large fat spots develop, cease production until resolved. Do not compact SMA that is below 230 ºF (110 ºC). C. Hauling. Do not allow trucks to dump any mix on the project mat after delivering mix to the paver. Provide a suitable place for bed cleaning off of the mat. 443.08 Acceptance. After accepting the test strips, the Department will accept SMA according to 446.05. 443.09 Basis of Payment. The Department will pay for accepted quantities of Stone Matrix Asphalt Concrete, complete in place, including test strip, at the contract price as modified by 446.05, as follows: Item Unit Description 443 Cubic Yard Stone matrix asphalt concrete, (cubic Meter) 12.5mm, PG70-22M, (446) 443 Cubic Yard Stone matrix asphalt concrete, (cubic Meter) 12.5mm, PG76-22M, (446) 246
446.01 Description 446.02 JMF Field Adjustments 446.03 Monitoring 446.04 Reports 446.05 Density Acceptance 446.06 Joints 446.07 Basis of Payment ITEM 446 ASPHALT CONCRETE 247 446.01 446.01 Description. This work consists of constructing a surface course or an intermediate course of aggregate and asphalt binder mixed in a central plant and spread and compacted on a prepared surface. The Department will base acceptance of the compacted mixture in place on the level of density attained as sampled by the Contractor and analyzed by the Department. The requirements of Item 441 apply, except as modified by this specification. 446.02 JMF Field Adjustments. Determine the need for any JMF gradation adjustments, provided for in 441.05, in the first 3 days or first 3000 tons (3000 metric tons) of production, whichever comes last. Give the DET written notice of JMF adjustments no later than the end of the following day’s production. For projects smaller than the above JMF field adjustment period give the DET written notice of any JMF gradation adjustments within 1 workday following the last day of production. 446.03 Monitoring. If there is poor comparison between the Department’s comparison samples and the Contractor’s quality control tests, the Monitoring Team may at any time disallow production to continue under Item 446. In this case, conform to Items 448 and 446. The Department will notify the Contractor in writing to stop production. 446.04 Reports. Submit the Quality Control Report according to 441.11 on the workday following the production day of the material represented by the report. 446.05 Density Acceptance. The requirements of 401.13 do not apply. However, rollers must fully and satisfactorily provide the required compaction, be mechanically sound, and meet Hot Mix Asphalt industry standards. The Department retains the right to reject the use of rollers which are not in good repair, or are not designed to do the work required. A three-wheel roller per 401.17 is not required. Obtain 10 cores for the Department to test to determine the in-place density of the compacted mixture as a percentage of the average Maximum Specific Gravity (MSG) for the production day the material was placed. Compact shoulders using the same equipment and procedures as used on the mainline pavement. The requirements of 401.16, except for the last four paragraphs, are waived. Payment for compaction of the completed mainline pavement and ramps is by Lot, based upon the degree to which density is attained. Payment for shoulders depends on the degree to which the density is obtained on the adjacent mainline
- Page 201 and 202: 195 403.07 the acceptance. While wo
- Page 203 and 204: 197 403.08 Table 403.08-1, but fall
- Page 205 and 206: 199 407.06 407.06 Application of As
- Page 207 and 208: 201 408.08 rate of application, tem
- Page 209 and 210: 203 409.05 409.05 Basis of Payment.
- Page 211 and 212: ITEM 411 STABILIZED CRUSHED AGGREGA
- Page 213 and 214: 207 421.02 Ensure that the Binder h
- Page 215 and 216: A. Source of each individual materi
- Page 217 and 218: 211 421.10 If the microsurfacing is
- Page 219 and 220: Item Unit Description 421 Square Ya
- Page 221 and 222: 215 422.04 oversized material, revo
- Page 223 and 224: 422.09 Before rolling, correct defi
- Page 225 and 226: Reject aggregate that does not meet
- Page 227 and 228: 422 Square Yard Double Chip Seal (S
- Page 229 and 230: 223 423.08 or spalling. Do not seal
- Page 231 and 232: 225 424.04 submittal. For medium mi
- Page 233 and 234: 227 441.02 If the F/A ratio using t
- Page 235 and 236: TABLE 441.02-1 (CONTINUED) Course T
- Page 237 and 238: TABLE 441.02-1 (CONTINUED) Course T
- Page 239 and 240: 233 441.06 Limit adjustments of the
- Page 241 and 242: 235 441.09 When the F-T value is sp
- Page 243 and 244: 237 441.11 holding a Level 3 Asphal
- Page 245 and 246: TABLE 442.02-1 GYRATION LEVEL AND M
- Page 247 and 248: 241 442.06 442.06 Compaction. Cease
- Page 249 and 250: TABLE 443.03-2 MIX PROPERTIES 243 4
- Page 251: 2. Shot content (ASTM C612) Passing
- Page 255 and 256: 249 446.05 Fill core holes by the n
- Page 257 and 258: 448.01 Description 448.02 JMF Field
- Page 259 and 260: 450 RIGID PAVEMENT ITEM 451 REINFOR
- Page 261 and 262: 255 451.04 track speed, and the fre
- Page 263 and 264: 257 451.07 finishing the freshly pl
- Page 265 and 266: 451.08 Immediately before paving, r
- Page 267 and 268: 451.09 oil. Use an adequate bulkhea
- Page 269 and 270: 263 451.15 self propelled machines
- Page 271 and 272: 265 451.18 When zones of deficient
- Page 273 and 274: 267 452.04 directs in writing. The
- Page 275 and 276: 269 499.03 C. Concrete Classes. Usi
- Page 277 and 278: TABLE 499.03-4 CLASS HP CONCRETE 27
- Page 279 and 280: 273 499.04 However, do not change t
- Page 281 and 282: TABLE 499.04-2 OPTION 2 CONCRETE (C
- Page 283 and 284: 277 499.06 rigid pavement removal a
- Page 285 and 286: TABLE 499.08-1 EVERY BATCH TICKET N
- Page 287 and 288: 281 499.09 When approved by the Eng
- Page 289 and 290: 283 501.04 Prepare the shop drawing
- Page 291 and 292: 285 501.05 drawing at least 24 hour
- Page 293 and 294: 287 501.05 ii. Erection sequence fo
- Page 295 and 296: 289 502.01 Accompany all certified
- Page 297 and 298: 291 503.01 503.01 Description. This
- Page 299 and 300: 293 503.08 503.08 Backfill. Backfil
- Page 301 and 302: 295 504.01 provide the minimum cove
446.01 Description<br />
446.02 JMF Field Adjustments<br />
446.03 Monitoring<br />
446.04 Reports<br />
446.05 Density Acceptance<br />
446.06 Joints<br />
446.07 Basis <strong>of</strong> Payment<br />
ITEM 446 ASPHALT CONCRETE<br />
247<br />
446.01<br />
446.01 Description. This work consists <strong>of</strong> constructing a surface course or an<br />
intermediate course <strong>of</strong> aggregate <strong>and</strong> asphalt binder mixed in a central plant <strong>and</strong><br />
spread <strong>and</strong> compacted on a prepared surface. The <strong>Department</strong> will base acceptance<br />
<strong>of</strong> the compacted mixture in place on the level <strong>of</strong> density attained as sampled by<br />
the Contractor <strong>and</strong> analyzed by the <strong>Department</strong>.<br />
The requirements <strong>of</strong> Item 441 apply, except as modified by this specification.<br />
446.02 JMF Field Adjustments. Determine the need for any JMF gradation<br />
adjustments, provided for in 441.05, in the first 3 days or first 3000 tons (3000<br />
metric tons) <strong>of</strong> production, whichever comes last. Give the DET written notice <strong>of</strong><br />
JMF adjustments no later than the end <strong>of</strong> the following day’s production.<br />
For projects smaller than the above JMF field adjustment period give the DET<br />
written notice <strong>of</strong> any JMF gradation adjustments within 1 workday following the<br />
last day <strong>of</strong> production.<br />
446.03 Monitoring. If there is poor comparison between the <strong>Department</strong>’s<br />
comparison samples <strong>and</strong> the Contractor’s quality control tests, the Monitoring<br />
Team may at any time disallow production to continue under Item 446. In this<br />
case, conform to Items 448 <strong>and</strong> 446. The <strong>Department</strong> will notify the Contractor in<br />
writing to stop production.<br />
446.04 Reports. Submit the Quality Control Report according to 441.11 on<br />
the workday following the production day <strong>of</strong> the material represented by the<br />
report.<br />
446.05 Density Acceptance. The requirements <strong>of</strong> 401.13 do not apply.<br />
However, rollers must fully <strong>and</strong> satisfactorily provide the required compaction, be<br />
mechanically sound, <strong>and</strong> meet Hot Mix Asphalt industry st<strong>and</strong>ards. The<br />
<strong>Department</strong> retains the right to reject the use <strong>of</strong> rollers which are not in good<br />
repair, or are not designed to do the work required. A three-wheel roller per<br />
401.17 is not required.<br />
Obtain 10 cores for the <strong>Department</strong> to test to determine the in-place density <strong>of</strong><br />
the compacted mixture as a percentage <strong>of</strong> the average Maximum Specific Gravity<br />
(MSG) for the production day the material was placed. Compact shoulders using<br />
the same equipment <strong>and</strong> procedures as used on the mainline pavement. The<br />
requirements <strong>of</strong> 401.16, except for the last four paragraphs, are waived.<br />
Payment for compaction <strong>of</strong> the completed mainline pavement <strong>and</strong> ramps is by<br />
Lot, based upon the degree to which density is attained. Payment for shoulders<br />
depends on the degree to which the density is obtained on the adjacent mainline