2010 Construction and Material Specifications - Ohio Department of ...
2010 Construction and Material Specifications - Ohio Department of ... 2010 Construction and Material Specifications - Ohio Department of ...
402.08 6. Tons per hour (metric tons per hour) of reclaimed pavement measured by a belt scale. C. Drum Mix Plants. In addition to the requirements of 402.07.A, print the information every 5 minutes during production. Ensure printouts contain the following additional information: 1. Tons per hour (metric tons per hour) of virgin asphalt binder. 2. Tons per hour (metric tons per hour) of virgin aggregate. 3. Tons per hour (metric tons per hour) of reclaimed pavement. 4. Moisture content of the virgin aggregate. 402.08 Polymer Binders. If an asphalt binder is modified by SBR polymer at an asphalt concrete mixing plant, equip the plant with an SBR polymer flow meter and monitoring system. Obtain the Laboratory’s approval of the system before operating. Demonstrate the system calibration to the District. If the District waives the demonstration, provide a letter documenting calibration data for the flow system to the DET for each project. For drum mix plants, introduce the SBR polymer directly into the asphalt binder line through means of an in-line motionless blender able to provide a homogeneous blend. Locate a sampling valve between the in-line blender and the plant drum. For batch plants, add the SBR polymer after the aggregate has been completely coated with asphalt binder. Continue mixing for a minimum of 20 seconds after SBR polymer is added and long enough to provide a uniform mixture. Use a 1-inch (25 mm) magnetic flow meter that employs balanced electrode plane technology. Ensure that the flow meter has two grounding electrodes located in the same measurement plane as the sensing electrodes. The flow meter does not require grounding rings if installed in nonmetallic piping. No straight run is required in piping before or after the flow meter to maintain accuracy, except if located downstream of a pump or modulating valve. Ensure that the totalizer displays a total volume measured and rate indication in any standard engineering units. Ensure that accuracy is ±2.0 percent over flow range from 0.8 to 47.5 gallons per minute (3 to 180 L/min). Install the flow meter in the piping downstream of all recirculation lines. Provide a lockable sample valve downstream of the flow meter for calibration purposes. Interface the flow meter with a data logging flow computer. The flow computer shall produce printouts of the logged data every 5 minutes for a drum mix plant or every batch for a batch plant. Include time, date, flow rate, and flow total in the logged data. Flow rate is not necessary for batch plant production. Balling or wadding of SBR polymer or uncoated aggregate indicates improper mixing. Cease production immediately and until corrected to District satisfaction. 402.09 Water Injection System for Warm Mix Asphalt. When allowed by specification use a Department approved water injection system for the purpose of foaming the asphalt binder and lowering the mixture temperature. Only use equipment that has been proven stable and effective thru 186
187 403.01 project use on non-ODOT projects. Ensure equipment for water injection meets the following requirements: 1. Injection equipment computer controls are in the plant control room and are tied to the plant computer metering. 2. Injection equipment has variable water injection control controlled by the plant operation rate and the water injection can never exceed 1.8% by weight of asphalt binder. 3. Water injection rate cannot be manually overridden by the plant operator once in the computer. 4. Injection equipment stops water flow when a control or equipment failure in the injection system occurs. 5. The water injects into the asphalt binder flow before the asphalt binder spray hits aggregate. Do not allow water to touch aggregate before the binder spray. 6. Injection equipment includes water storage and pump control tied to the injection computer controls. 7. Water storage low water alarm installed in the control room. 8. Provide a PG binder sampling valve between the last piping tee on the tank side of the line and the injection equipment to sample PG binder before water is injected. 9. Provide a PG Binder sampling valve at the injection equipment to sample binder prior to spray. ITEM 403 ASPHALT CONCRETE QUALITY CONTROL AND ACCEPTANCE 403.01 Description 403.02 General 403.03 Quality Control Program (QCP) 403.04 Plant Calibration 403.05 Quality Control Tests 403.06 Verification Acceptance (VA) 403.07 Unconditional Acceptance 403.08 Acceptance Tables for 448 Mixes 403.01 Description. This specification outlines the Contractor requirements for controlling asphalt concrete, asphalt concrete base, or other asphalt mixtures as specified. 403.02 General. The Department will determine acceptance by Department Verification Acceptance (VA) tests and monitoring reviews as specified. If the Contractor fails to operate according to its Quality Control Program (QCP), the Department will accept asphalt mixtures by Unconditional Acceptance.
- Page 141 and 142: 135 208.21 B. Report of Loss. If a
- Page 143 and 144: 137 209.01 209.01 Description. This
- Page 145 and 146: 250 PAVEMENT REPAIRS ITEM 251 PARTI
- Page 147 and 148: 141 252.05 If the Contract does not
- Page 149 and 150: Item Unit Description 253 Square Ya
- Page 151 and 152: 255.10 Basis of Payment 145 255.01
- Page 153 and 154: 147 255.07 Apply the liquid membran
- Page 155 and 156: 149 256.03 256.03 Equipment. Use a
- Page 157 and 158: 151 256.10 irrespective of the dept
- Page 159 and 160: 153 257.05 of the pavement is unifo
- Page 161 and 162: 155 258.03 the 1/2 -inch (12.5 mm)
- Page 163 and 164: 300 BASES ITEM 301 ASPHALT CONCRETE
- Page 165 and 166: 159 302.02 The Contractor may use r
- Page 167 and 168: 161 304.03 304.03 Before Spreading.
- Page 169 and 170: 163 304.08 Where variable depth is
- Page 171 and 172: 165 320.04 If using a resonant freq
- Page 173 and 174: 167 321.04 quality by cracking at l
- Page 175 and 176: 169 401.02 401.02 Mix Design and Qu
- Page 177 and 178: Asphalt Mix Application Heavy Traff
- Page 179 and 180: 173 401.05 Test blended RAP stockpi
- Page 181 and 182: 175 401.11 401.11 Hauling. Use truc
- Page 183 and 184: TABLE 401.13-3 PNEUMATIC TIRE ROLLE
- Page 185 and 186: 179 401.16 lighting at the beginnin
- Page 187 and 188: 401.18 Form hot longitudinal joints
- Page 189 and 190: TABLE 401.21 Aggregate lb/yd 3 (kg/
- Page 191: 185 402.06 402.06 Calibration. Cali
- Page 195 and 196: 189 403.03 D. Copies of worksheets,
- Page 197 and 198: 191 403.06 A. Sampling. The Departm
- Page 199 and 200: 193 403.06 District lab on its own
- Page 201 and 202: 195 403.07 the acceptance. While wo
- Page 203 and 204: 197 403.08 Table 403.08-1, but fall
- Page 205 and 206: 199 407.06 407.06 Application of As
- Page 207 and 208: 201 408.08 rate of application, tem
- Page 209 and 210: 203 409.05 409.05 Basis of Payment.
- Page 211 and 212: ITEM 411 STABILIZED CRUSHED AGGREGA
- Page 213 and 214: 207 421.02 Ensure that the Binder h
- Page 215 and 216: A. Source of each individual materi
- Page 217 and 218: 211 421.10 If the microsurfacing is
- Page 219 and 220: Item Unit Description 421 Square Ya
- Page 221 and 222: 215 422.04 oversized material, revo
- Page 223 and 224: 422.09 Before rolling, correct defi
- Page 225 and 226: Reject aggregate that does not meet
- Page 227 and 228: 422 Square Yard Double Chip Seal (S
- Page 229 and 230: 223 423.08 or spalling. Do not seal
- Page 231 and 232: 225 424.04 submittal. For medium mi
- Page 233 and 234: 227 441.02 If the F/A ratio using t
- Page 235 and 236: TABLE 441.02-1 (CONTINUED) Course T
- Page 237 and 238: TABLE 441.02-1 (CONTINUED) Course T
- Page 239 and 240: 233 441.06 Limit adjustments of the
- Page 241 and 242: 235 441.09 When the F-T value is sp
187<br />
403.01<br />
project use on non-ODOT projects. Ensure equipment for water injection meets the<br />
following requirements:<br />
1. Injection equipment computer controls are in the plant control room <strong>and</strong><br />
are tied to the plant computer metering.<br />
2. Injection equipment has variable water injection control controlled by the<br />
plant operation rate <strong>and</strong> the water injection can never exceed 1.8% by weight <strong>of</strong><br />
asphalt binder.<br />
3. Water injection rate cannot be manually overridden by the plant operator<br />
once in the computer.<br />
4. Injection equipment stops water flow when a control or equipment failure<br />
in the injection system occurs.<br />
5. The water injects into the asphalt binder flow before the asphalt binder<br />
spray hits aggregate. Do not allow water to touch aggregate before the binder<br />
spray.<br />
6. Injection equipment includes water storage <strong>and</strong> pump control tied to the<br />
injection computer controls.<br />
7. Water storage low water alarm installed in the control room.<br />
8. Provide a PG binder sampling valve between the last piping tee on the<br />
tank side <strong>of</strong> the line <strong>and</strong> the injection equipment to sample PG binder before water<br />
is injected.<br />
9. Provide a PG Binder sampling valve at the injection equipment to sample<br />
binder prior to spray.<br />
ITEM 403 ASPHALT CONCRETE QUALITY CONTROL AND<br />
ACCEPTANCE<br />
403.01 Description<br />
403.02 General<br />
403.03 Quality Control Program (QCP)<br />
403.04 Plant Calibration<br />
403.05 Quality Control Tests<br />
403.06 Verification Acceptance (VA)<br />
403.07 Unconditional Acceptance<br />
403.08 Acceptance Tables for 448 Mixes<br />
403.01 Description. This specification outlines the Contractor requirements<br />
for controlling asphalt concrete, asphalt concrete base, or other asphalt mixtures as<br />
specified.<br />
403.02 General. The <strong>Department</strong> will determine acceptance by <strong>Department</strong><br />
Verification Acceptance (VA) tests <strong>and</strong> monitoring reviews as specified. If the<br />
Contractor fails to operate according to its Quality Control Program (QCP), the<br />
<strong>Department</strong> will accept asphalt mixtures by Unconditional Acceptance.