2010 Construction and Material Specifications - Ohio Department of ...
2010 Construction and Material Specifications - Ohio Department of ... 2010 Construction and Material Specifications - Ohio Department of ...
305.03 acceleration/deceleration lanes, or collector/distributor lanes are not required unless the contraction joint is located within 500 feet (150 m) of a pressure relief joint. Do not place construction joints within 6 feet (1.8 m) of another parallel joint. Modify the curing membrane application rate specified in 451.10 to 200 square feet per gallon (5 m 2 /L) of treated pavement surface. Produce a final surface with a uniform, gritty, longitudinal, or transverse texture using a broom drag in either direction. Ensure that pavement surface variations do not exceed 1/4 inch in 10 feet (6 mm in 3 m). Impressing station numbers into the plastic concrete as specified in 451.09 is not required. 305.03 Method of Measurement. The Department will measure Concrete Base by the number of square yards (square meters) completed and accepted in place. The width equals the base width shown on the typical cross-section of the plans plus additional widening as the Engineer directs in writing. The Department will field measure the length along the centerline of each roadway or ramp. 305.04 Basis of Payment. For base found deficient in thickness, the Department will pay a reduced price according to 451.17. The Department will not make additional payment over the Contract unit price for any base with an average thickness in excess of that shown on the plans. The Department will pay for accepted quantities at the contract price as follows. Item Unit Description 305 Square Yard Concrete Base (Square Meter) 320.01 Description 320.02 Materials 320.03 Equipment 320.04 Construction Details 320.05 Method of Measurement 320.06 Basis of Payment ITEM 320 RUBBLIZE AND ROLL 320.01 Description. This work consists of rubblizing and rolling existing concrete pavement before placing an asphalt concrete pavement. 320.02 Materials. Furnish filler aggregate conforming to Item 304. 320.03 Equipment. Use a self-contained and self-propelled unit of either the resonant frequency type or the multiple head breaker type for rubblizing the exposed concrete pavement. 164
165 320.04 If using a resonant frequency unit, ensure that it is capable of producing low amplitude, 2000-pound-force (8900 N) blows at a rate of not less than 44 blows per second. If using a multiple head breaker unit, ensure that it has the capability of rubblizing the full 12-foot (3.6 m) lane width of the pavement in a single pass. Ensure the breaking head consists of 12 to 16 hammers weighing a total of 1000 to 1500 pounds (450 to 680 kg), mounted laterally in pairs with half the hammers in a forward row and the remainder diagonally offset in a rear row. Attach each hammer to a hydraulic lift cylinder that operates as an independent unit, develops 2000 to 12,000 foot-pounds (2700 to 16,000 J) of energy depending on lift height selected, cycles at a rate of 30 to 35 impacts per minute, and has a maximum lift height of 60 inches (1.5 m). Use a vibratory steel wheel roller having a total weight of not less than 10 tons (9 metric tons). 320.04 Construction Details. Make a full depth saw cut or cut load transfer devices at existing joints on ramps or mainline where the rubblizing abuts concrete pavement or approach slabs that are to remain in place permanently or temporarily for maintenance of traffic. Before the rubblizing operations begin, the Engineer will designate a test section. Rubblize the test section according to this specification. After rubblizing, excavate a test pit, where the Engineer designates, to check for proper particle size throughout the thickness of the concrete. Fill in the test pit using the excavated material and additional filler aggregate as necessary. Compact the test pit as part of the rolling operation. The Engineer may require additional test pits, as necessary, throughout the rubblizing operation. Adjust the rubblizing procedure to maintain the proper particle sizes. Control the operating speed of the rubblizing equipment such that the existing pavement is reduced into particles ranging from sand sized to pieces not exceeding 6 inches (150 mm) in their largest dimension, the majority being a nominal 1 to 2 inches (25 to 50 mm) in size. Reduce the portion of the concrete slab above the reinforcing steel to 1 to 2 inches (25 to 50 mm) in size. Before placing the initial asphalt concrete course, compact the rubblized pavement with two passes of the vibratory roller. Operate the roller in the vibratory mode and at a speed not to exceed 6 feet (1.8 m) per second. Leave steel reinforcement in place in the rubblized pavement. However, cut off any steel reinforcement, exposed at the surface as a result of rubblizing or compaction operations, below the surface and remove it from the site. Fill depressions 1 inch (25 mm) or greater in depth from that of the immediate surrounding area, resulting from the rubblizing, the compactive effort, or the steel reinforcement removal, with the filler aggregate. Strike off excess aggregate level with the surrounding area. Compact filled depressions with the same roller and compactive effort previously described. Do not allow traffic on the rubblized pavement before the initial asphalt concrete base and intermediate courses are in place.
- Page 119 and 120: 206.05 1. Cement or Lime Kiln Dust.
- Page 121 and 122: 115 206.06 Cover the completed chem
- Page 123 and 124: 117 207.03 with construction seed a
- Page 125 and 126: 119 207.04 advance of needing them.
- Page 127 and 128: The Department will measure Inlet P
- Page 129 and 130: 123 208.02 208.02 Regulations on th
- Page 131 and 132: 125 208.07 E. Maintain a stemming d
- Page 133 and 134: 208.09 During the 5-minute delay, t
- Page 135 and 136: 129 208.10 S. Use the same diameter
- Page 137 and 138: 131 208.14 208.14 Pre-Blast Conditi
- Page 139 and 140: 133 208.17 B. The airblast and nois
- Page 141 and 142: 135 208.21 B. Report of Loss. If a
- Page 143 and 144: 137 209.01 209.01 Description. This
- Page 145 and 146: 250 PAVEMENT REPAIRS ITEM 251 PARTI
- Page 147 and 148: 141 252.05 If the Contract does not
- Page 149 and 150: Item Unit Description 253 Square Ya
- Page 151 and 152: 255.10 Basis of Payment 145 255.01
- Page 153 and 154: 147 255.07 Apply the liquid membran
- Page 155 and 156: 149 256.03 256.03 Equipment. Use a
- Page 157 and 158: 151 256.10 irrespective of the dept
- Page 159 and 160: 153 257.05 of the pavement is unifo
- Page 161 and 162: 155 258.03 the 1/2 -inch (12.5 mm)
- Page 163 and 164: 300 BASES ITEM 301 ASPHALT CONCRETE
- Page 165 and 166: 159 302.02 The Contractor may use r
- Page 167 and 168: 161 304.03 304.03 Before Spreading.
- Page 169: 163 304.08 Where variable depth is
- Page 173 and 174: 167 321.04 quality by cracking at l
- Page 175 and 176: 169 401.02 401.02 Mix Design and Qu
- Page 177 and 178: Asphalt Mix Application Heavy Traff
- Page 179 and 180: 173 401.05 Test blended RAP stockpi
- Page 181 and 182: 175 401.11 401.11 Hauling. Use truc
- Page 183 and 184: TABLE 401.13-3 PNEUMATIC TIRE ROLLE
- Page 185 and 186: 179 401.16 lighting at the beginnin
- Page 187 and 188: 401.18 Form hot longitudinal joints
- Page 189 and 190: TABLE 401.21 Aggregate lb/yd 3 (kg/
- Page 191 and 192: 185 402.06 402.06 Calibration. Cali
- Page 193 and 194: 187 403.01 project use on non-ODOT
- Page 195 and 196: 189 403.03 D. Copies of worksheets,
- Page 197 and 198: 191 403.06 A. Sampling. The Departm
- Page 199 and 200: 193 403.06 District lab on its own
- Page 201 and 202: 195 403.07 the acceptance. While wo
- Page 203 and 204: 197 403.08 Table 403.08-1, but fall
- Page 205 and 206: 199 407.06 407.06 Application of As
- Page 207 and 208: 201 408.08 rate of application, tem
- Page 209 and 210: 203 409.05 409.05 Basis of Payment.
- Page 211 and 212: ITEM 411 STABILIZED CRUSHED AGGREGA
- Page 213 and 214: 207 421.02 Ensure that the Binder h
- Page 215 and 216: A. Source of each individual materi
- Page 217 and 218: 211 421.10 If the microsurfacing is
- Page 219 and 220: Item Unit Description 421 Square Ya
305.03<br />
acceleration/deceleration lanes, or collector/distributor lanes are not required<br />
unless the contraction joint is located within 500 feet (150 m) <strong>of</strong> a pressure relief<br />
joint.<br />
Do not place construction joints within 6 feet (1.8 m) <strong>of</strong> another parallel joint.<br />
Modify the curing membrane application rate specified in 451.10 to 200 square<br />
feet per gallon (5 m 2 /L) <strong>of</strong> treated pavement surface.<br />
Produce a final surface with a uniform, gritty, longitudinal, or transverse texture<br />
using a broom drag in either direction.<br />
Ensure that pavement surface variations do not exceed 1/4 inch in 10 feet (6<br />
mm in 3 m).<br />
Impressing station numbers into the plastic concrete as specified in 451.09 is<br />
not required.<br />
305.03 Method <strong>of</strong> Measurement. The <strong>Department</strong> will measure Concrete<br />
Base by the number <strong>of</strong> square yards (square meters) completed <strong>and</strong> accepted in<br />
place. The width equals the base width shown on the typical cross-section <strong>of</strong> the<br />
plans plus additional widening as the Engineer directs in writing. The <strong>Department</strong><br />
will field measure the length along the centerline <strong>of</strong> each roadway or ramp.<br />
305.04 Basis <strong>of</strong> Payment. For base found deficient in thickness, the<br />
<strong>Department</strong> will pay a reduced price according to 451.17.<br />
The <strong>Department</strong> will not make additional payment over the Contract unit price<br />
for any base with an average thickness in excess <strong>of</strong> that shown on the plans.<br />
The <strong>Department</strong> will pay for accepted quantities at the contract price as follows.<br />
Item Unit Description<br />
305 Square Yard Concrete Base<br />
(Square Meter)<br />
320.01 Description<br />
320.02 <strong>Material</strong>s<br />
320.03 Equipment<br />
320.04 <strong>Construction</strong> Details<br />
320.05 Method <strong>of</strong> Measurement<br />
320.06 Basis <strong>of</strong> Payment<br />
ITEM 320 RUBBLIZE AND ROLL<br />
320.01 Description. This work consists <strong>of</strong> rubblizing <strong>and</strong> rolling existing<br />
concrete pavement before placing an asphalt concrete pavement.<br />
320.02 <strong>Material</strong>s. Furnish filler aggregate conforming to Item 304.<br />
320.03 Equipment. Use a self-contained <strong>and</strong> self-propelled unit <strong>of</strong> either the<br />
resonant frequency type or the multiple head breaker type for rubblizing the<br />
exposed concrete pavement.<br />
164