2010 Construction and Material Specifications - Ohio Department of ...
2010 Construction and Material Specifications - Ohio Department of ... 2010 Construction and Material Specifications - Ohio Department of ...
208.13 E. Use appropriate blast hole patterns, detonation systems, and stemming to prevent venting of blasts and to minimize airblast and noise levels produced by the blasting operations. F. Carry out the trial blasts according to the blasting test section requirements of 208.07. G. Report the vibrations (velocity and frequency) and airblasts on both seismographs before the next blast. This report shall denote whether or not these numbers exceeded the allowable set by the vibration specialist. H. Modify 208.12.A through 208.12.F above as required to limit ground vibrations and airblast to the levels established by the vibration specialist, and the airblast and noise control specialist. I. Coordinate and review the blast hole layout and drilling operations. The blaster, blasting contractor, or the contractor shall obtain insurance as specified in 107.12. Present a certificate of insurance 10 days before the blasting operations begin. 208.13 Blasting Consultant. If specified in the Contract, retain an experienced and recognized blasting consultant to assist in the blast design. The blasting consultant shall assist in the design of both the controlled and production blasting. Retain a blasting consultant with at least 5 years of proven experience in heavy construction or highway rock blasting design and with a sufficient amount of proven experience of the type of highway rock blasting design required by the Contract. The Contractor shall not use a blasting consultant that is an employee of the Contractor, explosives manufacturer, or explosives distributor. Before or at the preconstruction conference, submit a resume of the credentials of the proposed blasting consultant. Include in the resume a list of at least five heavy construction or highway rock blasting projects on which the blasting consultant was responsibly in charge of the rock blasting design. List a description of the projects, with details of the blast plans and modifications made during the project. List the names and telephone numbers of project owners with sufficient knowledge of the projects to verify the submitted information. Obtain approval of the blasting consultant before beginning any drilling and blasting work. Allow 30 days for the review of this documentation. The blasting consultant shall observe the loading, drilling, or blasting operations for at least 8 hours per week if these operations are in progress for 40 or more hours per week. The blasting consultant shall witness the drilling, loading and blasting of the first shot in each major cut. At a minimum, the blasting consultant shall witness the drilling, loading and blasting of every 20 th shot on the project. The blasting consultant shall write a written report to the Engineer at least once a month detailing the blasting operations. The time spent writing this report is not considered part of the time required to observe the loading, drilling, and blasting operations. The Contractor shall coordinate the blasting consultant’s hours with the Engineer. 130
131 208.14 208.14 Pre-Blast Condition Survey. If specified in the Contract, conduct a pre-blast survey of any buildings, structures, or utilities within 1500 feet (460 m) or to the nearest structure up to 1/2-mile (0.8 km) radius of the blasting operations. Use a greater radius if the structures are potentially at risk from blasting damage. The Contractor shall use a survey method acceptable to its insurance company. The Contractor is responsible for any damage resulting from blasting. If owners or occupants fail to allow access to the property for the pre-blast survey, send a certified letter to the owner or occupant. Make the notification effort and the certified letter part of the pre-blast survey records. Submit a copy of the pre-blast survey records to the Engineer before beginning the blasting operations at the critical blasting locations. Notify occupants of local buildings before the commencement of blasting. 208.15 Vibration Control and Monitoring. If specified in the Contract, use vibration control and monitoring if blasting near buildings, structures, or utilities that may be subject to damage from blast induced ground vibrations. The vibration specialist interprets the seismograph records to ensure that the seismograph data is effective in the control of the blasting operations with respect to the existing structures. Retain an experienced vibration specialist to establish the safe vibration limits. Use a vibration specialist with at least 5 years of proven experience in monitoring vibrations on heavy construction or highway rock blasting projects and with a sufficient amount of proven experience of the type of highway rock blasting vibration monitoring required by the Contract. Use a vibration specialist that is an expert in the interpretation of the vibration data. The Contractor shall not use a vibration specialist that is an employee of the Contractor, explosives manufacturer, or explosives distributor. Before or at the preconstruction conference, submit a resume of the credentials of the proposed vibration specialist. Include in the resume a list of at least five heavy construction or highway rock blasting projects on which the vibration specialist was responsibly in charge of monitoring the rock blasting vibrations. List a description of the projects, with details of the vibration interpretations made on the project. List the names and telephone numbers of project owners with sufficient knowledge of the projects to verify the submitted information. Obtain approval of the vibration specialist before beginning any drilling and blasting work. Allow 30 days for the review of this documentation. The vibration specialist shall perform the following: A. Monitor each blast with an approved seismograph located between the blast area and the closest structure subject to blast damage. B. Use a seismograph capable of recording particle velocity for three mutually perpendicular components of vibration in the range generally found with controlled blasting. C. Furnish the data recorded for each shot before the next blast and include the following:
- Page 85 and 86: 79 109.06 If the original material
- Page 87 and 88: 81 109.12 complete. Final Inspectio
- Page 89 and 90: 200 EARTHWORK ITEM 201 CLEARING AND
- Page 91 and 92: 202.01 Description 202.02 General C
- Page 93 and 94: 87 202.04 Where alteration of an ex
- Page 95 and 96: 89 202.08 ground surface. Break up
- Page 97 and 98: 91 202.14 removal or excavation, an
- Page 99 and 100: 93 203.03 F. Excavation. The excava
- Page 101 and 102: 95 203.04 c. Perform the tests on e
- Page 103 and 104: 97 203.06 granular material in a un
- Page 105 and 106: 99 203.07 6. Construct the other em
- Page 107 and 108: 101 203.09 the bottom of the ditch,
- Page 109 and 110: 103 203.10 If during excavation the
- Page 111 and 112: 105 204.03 Furnish geotextile fabri
- Page 113 and 114: 107 204.07 Operate equipment at a s
- Page 115 and 116: ITEM 205 CHEMICALLY STABILIZED EMBA
- Page 117 and 118: 111 205.06 205.06 Method of Measure
- Page 119 and 120: 206.05 1. Cement or Lime Kiln Dust.
- Page 121 and 122: 115 206.06 Cover the completed chem
- Page 123 and 124: 117 207.03 with construction seed a
- Page 125 and 126: 119 207.04 advance of needing them.
- Page 127 and 128: The Department will measure Inlet P
- Page 129 and 130: 123 208.02 208.02 Regulations on th
- Page 131 and 132: 125 208.07 E. Maintain a stemming d
- Page 133 and 134: 208.09 During the 5-minute delay, t
- Page 135: 129 208.10 S. Use the same diameter
- Page 139 and 140: 133 208.17 B. The airblast and nois
- Page 141 and 142: 135 208.21 B. Report of Loss. If a
- Page 143 and 144: 137 209.01 209.01 Description. This
- Page 145 and 146: 250 PAVEMENT REPAIRS ITEM 251 PARTI
- Page 147 and 148: 141 252.05 If the Contract does not
- Page 149 and 150: Item Unit Description 253 Square Ya
- Page 151 and 152: 255.10 Basis of Payment 145 255.01
- Page 153 and 154: 147 255.07 Apply the liquid membran
- Page 155 and 156: 149 256.03 256.03 Equipment. Use a
- Page 157 and 158: 151 256.10 irrespective of the dept
- Page 159 and 160: 153 257.05 of the pavement is unifo
- Page 161 and 162: 155 258.03 the 1/2 -inch (12.5 mm)
- Page 163 and 164: 300 BASES ITEM 301 ASPHALT CONCRETE
- Page 165 and 166: 159 302.02 The Contractor may use r
- Page 167 and 168: 161 304.03 304.03 Before Spreading.
- Page 169 and 170: 163 304.08 Where variable depth is
- Page 171 and 172: 165 320.04 If using a resonant freq
- Page 173 and 174: 167 321.04 quality by cracking at l
- Page 175 and 176: 169 401.02 401.02 Mix Design and Qu
- Page 177 and 178: Asphalt Mix Application Heavy Traff
- Page 179 and 180: 173 401.05 Test blended RAP stockpi
- Page 181 and 182: 175 401.11 401.11 Hauling. Use truc
- Page 183 and 184: TABLE 401.13-3 PNEUMATIC TIRE ROLLE
- Page 185 and 186: 179 401.16 lighting at the beginnin
131<br />
208.14<br />
208.14 Pre-Blast Condition Survey. If specified in the Contract, conduct a<br />
pre-blast survey <strong>of</strong> any buildings, structures, or utilities within 1500 feet (460 m)<br />
or to the nearest structure up to 1/2-mile (0.8 km) radius <strong>of</strong> the blasting operations.<br />
Use a greater radius if the structures are potentially at risk from blasting damage.<br />
The Contractor shall use a survey method acceptable to its insurance company.<br />
The Contractor is responsible for any damage resulting from blasting.<br />
If owners or occupants fail to allow access to the property for the pre-blast<br />
survey, send a certified letter to the owner or occupant. Make the notification<br />
effort <strong>and</strong> the certified letter part <strong>of</strong> the pre-blast survey records.<br />
Submit a copy <strong>of</strong> the pre-blast survey records to the Engineer before beginning<br />
the blasting operations at the critical blasting locations.<br />
Notify occupants <strong>of</strong> local buildings before the commencement <strong>of</strong> blasting.<br />
208.15 Vibration Control <strong>and</strong> Monitoring. If specified in the Contract, use<br />
vibration control <strong>and</strong> monitoring if blasting near buildings, structures, or utilities<br />
that may be subject to damage from blast induced ground vibrations. The<br />
vibration specialist interprets the seismograph records to ensure that the<br />
seismograph data is effective in the control <strong>of</strong> the blasting operations with respect<br />
to the existing structures.<br />
Retain an experienced vibration specialist to establish the safe vibration limits.<br />
Use a vibration specialist with at least 5 years <strong>of</strong> proven experience in monitoring<br />
vibrations on heavy construction or highway rock blasting projects <strong>and</strong> with a<br />
sufficient amount <strong>of</strong> proven experience <strong>of</strong> the type <strong>of</strong> highway rock blasting<br />
vibration monitoring required by the Contract.<br />
Use a vibration specialist that is an expert in the interpretation <strong>of</strong> the vibration<br />
data. The Contractor shall not use a vibration specialist that is an employee <strong>of</strong> the<br />
Contractor, explosives manufacturer, or explosives distributor.<br />
Before or at the preconstruction conference, submit a resume <strong>of</strong> the credentials<br />
<strong>of</strong> the proposed vibration specialist. Include in the resume a list <strong>of</strong> at least five<br />
heavy construction or highway rock blasting projects on which the vibration<br />
specialist was responsibly in charge <strong>of</strong> monitoring the rock blasting vibrations.<br />
List a description <strong>of</strong> the projects, with details <strong>of</strong> the vibration interpretations made<br />
on the project. List the names <strong>and</strong> telephone numbers <strong>of</strong> project owners with<br />
sufficient knowledge <strong>of</strong> the projects to verify the submitted information. Obtain<br />
approval <strong>of</strong> the vibration specialist before beginning any drilling <strong>and</strong> blasting<br />
work. Allow 30 days for the review <strong>of</strong> this documentation.<br />
The vibration specialist shall perform the following:<br />
A. Monitor each blast with an approved seismograph located between the blast<br />
area <strong>and</strong> the closest structure subject to blast damage.<br />
B. Use a seismograph capable <strong>of</strong> recording particle velocity for three mutually<br />
perpendicular components <strong>of</strong> vibration in the range generally found with<br />
controlled blasting.<br />
C. Furnish the data recorded for each shot before the next blast <strong>and</strong> include the<br />
following: