form) as approved by the municipality; such plan to<br />
show the grading, layout and dimensions of lots,<br />
sidewalks and curbs, and the location of all other<br />
utilities and other underground structures.<br />
• Install lot boundary pins or markers in the area under<br />
development prior to the start of trenching for the URD.<br />
• Notify the <strong>Company</strong> of the completion of rough grade,<br />
installation of other facilities at grades below URD and<br />
the schedule of desired electric service connections so<br />
that the <strong>Company</strong> will have adequate time to install its<br />
facilities.<br />
• Provide trenching<br />
and conduit or conduit systems as<br />
required. See paragraph 901 for a list of such<br />
requirements and paragraph 910 for conduit<br />
requirements/specifications.<br />
908. PADMOUNT TRANSFORMERS<br />
Installation of padmount transformers is limited to cases<br />
meeting<br />
the following specifications:<br />
1. Single-phase three-wire services, (a) operating at<br />
120/240 volts and requiring transformer capacity of not<br />
more than 167 kVA, or (b) operating at 240/480 volts and<br />
requiring transformer capacity of not more than 50 KVA;<br />
or<br />
2. Three-phase four-wire services operating at 120/208<br />
volts or 277/480 volts Wye and requiring transformer<br />
capacity of not more than 2500 KVA. (Larger units may be<br />
available by special arrangement.)<br />
75<br />
75