IX.<br />
UNDERGROUND SERVICE<br />
900. GENERAL<br />
The <strong>Company</strong> will, subject to the availability of material<br />
and transformers, and in compliance with certain special<br />
requirements hereinafter described, provide underground service<br />
directly from its distribution lines.<br />
For added protection and ease of cable replacement,<br />
the<br />
<strong>Company</strong> strongly recommends that all underground cables<br />
be installed in conduit. Any direct buried primary cable shall<br />
not be permitted within five (5) feet of the traveled way.<br />
Contact the <strong>Company</strong>'s local Service Center or Marketing &<br />
Sales (M&S) Department for conduit installation<br />
details not<br />
contained<br />
in this handbook.<br />
All installations connected to <strong>Company</strong> owned facilities<br />
shall comply with the installation specifications contained herein.<br />
These requirements<br />
are based on the NESC or NEC, and<br />
considered<br />
to be good engineering practice.<br />
The Illustrations in Section XII of this handbook provide<br />
the<br />
required trench, riser and transformer foundation details.<br />
Direct-buried conductors and cables emerging from grade<br />
shall<br />
be protected from damage in accordance with NEC 310.5<br />
(D) (1).<br />
Any work listed as being the “responsibility” of the<br />
customer means<br />
that the customer will be required to complete<br />
the<br />
work involved<br />
to meet <strong>Company</strong><br />
s tandards and specifications.<br />
All<br />
work perfor<br />
med by the customer shall be subject to inspection<br />
by the <strong>Company</strong> pri or to energizing t he installation.<br />
67<br />
67