66<br />

66<br />

The mounting of <strong>Company</strong> meters in switchgear is not<br />

recommended and generally will not be approved. Requests for<br />

special permission for such installations shall be accompanied by<br />

detaile d plans showing arrangements of all cables, busses and<br />

other apparatus which are adjacent to the proposed meter<br />

locations.<br />

All switchgear arrangement<br />

drawings must be submitted<br />

to the <strong>Company</strong>’s Meter Engineer for approval.