6<br />
Dwelling Application is used when the homeowner does<br />
the wiring and the State inspector certifies the wiring.<br />
202. SERVICE REQUIRING EXTENSION OF LINES<br />
Line extensions shall be in accordance with the provisions<br />
of the MPUC’s Chapter 395 “Construction Standards and<br />
Ownership and Cost Allocation Rules for Electric Distribution<br />
Line Extensions,” and, the <strong>Company</strong>’s filed tariff or Term &<br />
Condition (T&C) on “Extensions." See paragraph 219 of this<br />
handbook for more details on customer constructed/owned<br />
lines.<br />
203. INSTALLATION OF SERVICE-SUPPLY<br />
LINES<br />
The <strong>Company</strong> is not required to install service-supply lines<br />
prior to the time that the wiring of the premises is actually in<br />
progress and the structure sufficiently completed to provide a safe<br />
and suitable terminus for the service-supply lines.<br />
204. TEMPORARY SERVICE<br />
Customers taking service on a temporary basis are required<br />
to pay an amount equivalent to the cost of installing and removing<br />
the <strong>Company</strong>'s service facilities, including the nonsalvable costs<br />
of material used. Temporary service, provided typically for<br />
building construction purposes, is intended to be used for a limited<br />
time period at a location where the facilities devoted especially to<br />
the service are not expected to have further usefulness at that<br />
location after the temporary period. There shall be no other<br />
attachments to the temporary structure; and, if it becomes unsafe,<br />
service may be disconnected (See paragraph 209). In special<br />
cases advance payment is required. See<br />
Illustration No. 7 in<br />
Section XII for overhead temporary service structure<br />
requirements. See Par. 918 and Illustration No.s 9 and 11 for<br />
underground temporary or permanent service structure<br />
requirements.<br />