DONATI SOLLEVAMENTI S.r.l. - Via Roma, 55 - 21020 Daverio (VA) - Tel. 0332 942611 - Fax. 0332 948597<br />

Column assembling:<br />

1.Once the solidification of the plinth has taken place, remove the protection from the threadings of the log<br />

bolts and check that the tall nuts can be unscrewed without being forced, remove them and the related<br />

washers.<br />

2. Insert, when needed, the electric cable 1 in the column resting on the floor and push it through the hole<br />

at the end of the column, using this layout as follows:<br />

a. In the case of cable 1 which comes out of the allocated tub (pipe) in the plinth, insert the cable<br />

directly inside the column until it reaches hole 2 at the end of the column (fig.21)<br />

b. In the case of cable 1 coming from the outside, push it into the column using a suitable fairlead<br />

3 placed at the bottom of the column, until it reaches hole 2 at the top (fig.22)<br />

3. Set up the column without the arm, lifting it by the upper part with appropriate equipment having put it in<br />

the sling as shown, assemble it on the foundation frame positioning the base plate 4 correctly and lining<br />

up the nuts 6, subject to the interposition of the related flat washers 5 (fig. 23).<br />

4. Check the verticality of the rotation axis as follows:<br />

a. Remove the protective plastic plugs from the housing of the pivots<br />

b. Insert the pivots 7 provisionally in their respective housing (see 4.3.5 Assembly of the arm)<br />

c. Check the verticality of the rotation axis, by using a level L and a bar which must be resting<br />

directly on the rotation pivots 7 (fig.24).<br />

d. The perfect plumbing can be obtained, if necessary, inserting suitable shims 8 (not included in<br />

the supply), corresponding to the log bolts, under the base plate (fig. 25).<br />

5. Screw tight the nuts 6 using a dynamometric spanner, applying the clamping couples (see table on<br />

page 12) based on the diameter of the logbolts, checking the nuts afterwards for unscrewing with the<br />

relative safety nuts 9 (fig. 26)<br />

fig.21<br />

fig.24<br />

fig.22<br />

fig.25<br />

25<br />

fig.23<br />

fig.26<br />

It is recommended that, after the first lifting operations the clamping of the nuts is<br />

checked again, to take up any slack due to the bedding of the plinth.