Chapter-7<br />
i) Water<br />
ii) Health<br />
iii) Communications<br />
iv) Railways<br />
v) Manpower <strong>Development</strong><br />
vi) Women <strong>Development</strong><br />
vii) Population Welfare<br />
viii) Education<br />
ix) Youth Affairs<br />
Reports of the results of the review should be submitted to the Economic Coordination Committee of the<br />
Cabinet periodically.<br />
(b) The Federal Ministers should hold meetings with concerned agencies under the control of their<br />
Ministries to review implementation of development projects pertaining to their Ministries once every<br />
month. A day should be fixed by each Minister on which these review meetings would be held every<br />
month and this day should be permanently incorporated in the calendar of engagements of the Minister.<br />
(c) The Deputy Chairman, <strong>Planning</strong> <strong>Commission</strong> should review the progress of implementation of<br />
develop-ment projects at least once every quarter.<br />
In addition, the Economic Coordination Committee (ECC) of the Cabinet at its meeting held on April 30,<br />
1990 also decided that every Minister/Minister of State would take a meeting on the first Tuesday of<br />
every month to review the progress of aid utilization in respect of the projects/schemes being<br />
implemented by his/her Ministry/Division. Reports of these meetings would be sent to the Cabinet<br />
Division <strong>for</strong> submitting the main points of the reports to the Prime Minister.<br />
<strong>Projects</strong> Review Groups<br />
Page 13 of 26<br />
7.21 To develop a synthesis of all progress review activities with the Ministries/Divisions including<br />