Chapter 4<br />
iii) Equity<br />
(b) Sponsoring Agency's Own Fund<br />
(c) Private Investment<br />
(d) Local Body Services, if any<br />
(e) Non-Government Borrowing<br />
(f) Other Sources (e.g., Recoveries)<br />
Usually <strong>for</strong>eign aid negotiations should be undertaken after a project has been approved by the competent<br />
authority or at least cleared by the Concept Clearance Committee headed by the Deputy Chairman,<br />
<strong>Planning</strong> <strong>Commission</strong>.<br />
Financial Phasing<br />
4.17 The financial phasing of a project is to be given <strong>for</strong> each financial year related to the physical work<br />
proposed to be undertaken, keeping in view the implementation of similar projects in the past. It should be<br />
as realistic as possible. Funds utilization capacity of executing agency should be kept in view while<br />
determining financial phasing of project.<br />
Physical Scheduling of Activities<br />
4.18 The scheduling of activities and availability of physical facilities are interlinked with the completion<br />
period. The availability of physical facilities e.g., (i) access road, (ii) power supply, (iii) water, gas,<br />
telephone and other utilities, (iv) education facilities, (v) housing etc., have to be ensured. The sponsoring<br />
agency has also to indicate separately what facilities would be available from the project itself and to what<br />
extent these would be available from the public utilities. The scope of work to be carried out should be<br />
gone into very thoroughly to facilitate physical and financial phasing as well as supervision.<br />
Period of Implementation<br />
4.19 Time calculated <strong>for</strong> the completion of the project should be on a realistic basis. The following factors<br />
will have to be taken into consideration to firm up the implementation period:<br />
(a) Total allocation made in the Five Year Plan.<br />
(b) Expected allocations in the PSDP, keeping in view the past experience.<br />
Page 8 of 11<br />
(c) Time to be taken in preparing the detailed design(s), invitation of tenders and award of contract(s).<br />
http://hd2/pc/popup/ch4_p.html<br />