Manual for Development Projects - Planning Commission
Manual for Development Projects - Planning Commission
Manual for Development Projects - Planning Commission
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Chapter 4<br />
should re-order the priorities of the existing projects to accommodate the new priority within the available<br />
resources. What happens is that both the old and new priorities are sought to be accommodated in the<br />
limited available resources.<br />
4.3 At the time of approval of the projects, the availability of the resources in the Plan and PSDP should be<br />
looked into very carefully. The sponsoring agencies should structure their priorities according to the<br />
available resources and not come up with an over-ambitious programme, which may not be possible to<br />
implement.<br />
4.4 The financial schedule must be included in the PC-I and linked with the implementation schedule. The<br />
sponsoring agency should satisfy the approving authority as to how the proposed financial requirements of<br />
the project will be adjusted in the Plan.<br />
4.5 Some sponsoring agencies suggest that the detailed design and drawings etc., of the project should not<br />
be a pre-requisite <strong>for</strong> the approval of the PC-I. The approval should be given on the basis of the rough cost<br />
estimates, which may be adjusted within the permissible limit of a 15% increase. In this connection, the<br />
decision of the NEC dated 4-7-1988 is as under:-<br />
"Within six months of project approval, detailed design and costing should be finalized and submitted to<br />
the competent authority. Implementation of such project components, which require detailed designing,<br />
should be started only when these have been finalized".<br />
The above decision of NEC should be strictly followed by the executing agencies.<br />
4.6 The NEC further decided in the same meeting that all PC-Is costing Rs 50 million and above should be<br />
supported by a feasibility study. However, this does not rule out a feasibility study in the case of PC-Is<br />
costing less, where it may be needed.<br />
Location, Area and Population Coverage<br />
4.7 It should include the following:<br />
i) Place and administrative district where the project is located.<br />
ii) Map of the project area.<br />
Page 3 of 11<br />
iii) Reasons <strong>for</strong> selection of location. In this connection it may be noted that many projects have suffered<br />
tremendously in the past from cost over-runs and delay in implementation due to hasty selection of site.<br />
The project also suffer due to delay in acquisition of land. There<strong>for</strong>e the availability of land needs to be<br />
assured. In selecting the location, area and population to be served by the project, the income and social<br />
characteristics of the population will have to be kept in view. Similarly, the economic characteristics of the<br />
area i.e. present facilities and availability of inputs and regional development needs will also have to be<br />
taken into consideration.<br />
iv) PC-I <strong>for</strong>m should clearly indicate that the environmental aspects of the project have been duly taken<br />
into account.<br />
http://hd2/pc/popup/ch4_p.html<br />
9/23/2010