30.12.2012 Views

Final Site Information Package for National Remedy Review Board ...

Final Site Information Package for National Remedy Review Board ...

Final Site Information Package for National Remedy Review Board ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

SITE INFORMATION PACKAGE FOR NATIONAL REMEDY REVIEW BOARD<br />

PART B, SECTION 9: COMPARATIVE ANALYSIS OF ALTERNATIVES<br />

estimated effectiveness at completion of remedial actions is also slightly higher <strong>for</strong><br />

Alternative 4+ than <strong>for</strong> Alternative 3+. The differences in ranking among the OU 2<br />

alternatives under this criterion do not outweigh the differences between Alternatives 3+<br />

and 4+. The ranking of the OU 2 alternatives under this criterion, from highest to lowest, is<br />

as follows: e, d, c, a, and b. This ranking is based on the relative differences in post-remedial<br />

dissolved zinc loads in the SFCDR, immediately following the implementation of remedial<br />

actions.<br />

9.1.4 Reduction of Toxicity, Mobility, or Volume through Treatment<br />

All the remedial alternatives are considered to satisfy the statutory preference <strong>for</strong> treatment,<br />

and the treated water flow rates are relatively similar <strong>for</strong> all the alternatives. OU 2<br />

Alternatives (a) and (b) do not include treatment and, there<strong>for</strong>e, rank lower under this<br />

criterion. Alternative 4+ ranks higher than Alternative 3+ because, although the estimated<br />

flow rate <strong>for</strong> treatment at the CTP is very similar, a significantly higher number of adit<br />

discharges would be treated under Alternative 4+. The statutory preference <strong>for</strong> treatment is<br />

satisfied through reduction of total volume of contaminated media—in this case, surface<br />

water. The water treatment technologies to be employed would separate the metals from the<br />

water. These metals would then require disposal in repositories. For each of the remedial<br />

alternatives except <strong>for</strong> No Action, Tables B9-1a and B-91b present an estimate of the total<br />

dissolved zinc load removed from the water through treatment (and there<strong>for</strong>e a reduction in<br />

the zinc loading to the surface water). The estimates in Table B9-1a range from 700 pounds<br />

per day (lb/day) <strong>for</strong> Alternative 3+(a) to 1,880 lb/day <strong>for</strong> Alternative 3+(d); the estimates in<br />

Table B9-1b range from 600 lb/day <strong>for</strong> Alternative 4+(a) to 1,760 lb/day <strong>for</strong><br />

Alternative 4+(d).<br />

9.1.5 Short-Term Effectiveness<br />

All of the alternatives based on Alternative 3+ rank higher under the criterion of short-term<br />

effectiveness than those based on Alternative 4+ because Alternative 4+ would pose much<br />

greater short-term negative impacts during construction than Alternative 3+, regardless of<br />

which OU 2 alternative it is coupled with. This is primarily due to the extensive nature of<br />

the remedial actions that would be conducted under Alternative 4+, which would require a<br />

much longer time period to complete (decades longer); the similar water quality expected to<br />

be achieved after the implementation of remedial actions; and the similar time frame needed<br />

<strong>for</strong> natural source depletion to further improve water quality and achieve ARARs. The<br />

ranking of the OU 2 alternatives from highest to lowest short-term effectiveness is as<br />

follows: d, c, b, a, and e. This ranking is based on a balance of implementation time,<br />

effectiveness, and short-term risks.<br />

9.1.6 Implementability<br />

All of the alternatives based on Alternative 3+ rank higher under the criterion of<br />

implementability than those based on Alternative 4+, because Alternative 4+ would have<br />

substantially increased technical and administrative feasibility considerations compared to<br />

Alternative 3+. Alternative 4+ has generally the same types of implementability<br />

considerations as Alternative 3+, but with much larger quantities and larger repository<br />

requirements. The ranking of the OU 2 alternatives from most to least desirable on the basis<br />

of implementability is as follows: c, d, b, a, and e.<br />

B9-4

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!