26.09.2023 Views

CC Sep-Oct 2023

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

CASEstudy<br />

SEQUENCING A PROGRAMME<br />

WITH PIONEERING TECHNIQUES<br />

The hotel's extension plans carried<br />

significant risks. The new mega<br />

basement was situated directly<br />

underneath Claridge's Art Deco<br />

extension, constructed in the 1920s on a<br />

single reinforced concrete slab. McGee's<br />

Project Director, Jim Mackey, developed<br />

a creative construction plan to be<br />

executed by Project Engineer Michelle<br />

Mackey (who is also Jim's daughter).<br />

"We did some trial works to determine<br />

what the existing building structure was<br />

made of and what was and wasn't<br />

possible, then Jim sat down with our<br />

technical department and put together a<br />

3D animation of the sequence."<br />

With the high-level sequence mapped<br />

out, Jim handed the project to Michelle,<br />

who needed to turn a static plan into<br />

something more dynamic. Michelle<br />

chose Asta Powerproject planning and<br />

project management software to rise to<br />

this challenge.<br />

"Asta Powerproject enabled me to put<br />

in the detail we needed and then roll the<br />

programme up, so we could still present<br />

a high-level view. We didn't need<br />

everyone to see tasks hour by hour, but<br />

going into that level of detail meant we<br />

could flag any potential issues early on."<br />

The Claridge's project was divided into<br />

multiple phases, starting with a team of<br />

miners hand-digging a network of<br />

tunnels directly underneath the hotel.<br />

They dug down 30 metres to create a<br />

series of shafts that would become the<br />

hotel's new foundations.<br />

Concrete was poured into the shafts to<br />

create the new foundations, and new<br />

columns were constructed from within<br />

the shafts for the existing hotel building<br />

to rest on. Then the team excavated 500<br />

cubic metres of earth from around the<br />

columns, using heavy machinery<br />

assembled underground, to construct<br />

the new five-story basement.<br />

"Once I set up the programme in Asta<br />

Powerproject and tested the first few<br />

lines, I felt confident that I could<br />

sequence the project from start to finish<br />

and there wouldn't be any errors,"<br />

Michelle added.<br />

MANAGING COMPLEX TIME AND<br />

MATERIAL SCHEDULES<br />

It wasn't just construction techniques<br />

that challenged McGee. Working on a<br />

landmark building in the middle of<br />

London also presented logistics<br />

challenges, as the excavation work<br />

involved removing 45,000 tonnes of clay<br />

through one hole just 2.5 metres wide.<br />

McGee could not store waste material<br />

on-site due to insufficient space.<br />

Instead, materials had to be moved to<br />

and from Claridge's daily from a nearby<br />

holding yard, with a single loading area<br />

on-site. Asta Powerproject delivered the<br />

precision planning needed to ensure<br />

materials were collected on schedule,<br />

preventing programme delays.<br />

"The Claridge's project was very<br />

complex by nature. We had one space<br />

to work in, and all our equipment and<br />

materials came in and out of one<br />

opening. Asta Powerproject allowed us<br />

to take just-in-time material planning to<br />

the extreme."<br />

The project also involved coordinating<br />

tradespeople working two different shift<br />

patterns. While standard building<br />

contractors worked Monday-Friday,<br />

8am-6pm, two teams of miners worked<br />

seven days in alternating 12-hour shifts.<br />

McGee used Asta Powerproject to<br />

coordinate site resources with material<br />

requirements, managing the pace of<br />

work to synchronise deliveries with their<br />

progress. "We never wanted to be in a<br />

situation where teams arrived for their<br />

shift and the materials that they needed<br />

weren't available. Or a situation where<br />

we couldn't get materials in fast enough.<br />

With Asta Powerproject, we could drop a<br />

line down the programme to monitor<br />

and adjust progress on a daily basis,"<br />

said Mackey.<br />

Some material deliveries were timecritical,<br />

like the thousands of tonnes of<br />

concrete needed for the basement<br />

columns. Michelle's team needed to<br />

ensure that mining work finished at a<br />

time when concrete could be delivered<br />

to fill each shaft as quickly as possible.<br />

"We used Asta Powerproject to<br />

coordinate both timings and logistics.<br />

For example, we couldn't have mining<br />

teams finishing on a Saturday night and<br />

then the base of each shaft being left<br />

open for 30 hours until the concrete<br />

could arrive."<br />

COORDINATING CONSTRUCTION IN<br />

THE PRESENCE OF PAYING GUESTS<br />

If project logistics weren't challenging<br />

enough, McGee also had to coordinate<br />

site activity around what was happening<br />

in the hotel. In addition to ensuring<br />

<strong>Sep</strong>tember/<strong>Oct</strong>ober <strong>2023</strong> 11

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!