CASE study<br />
A megabuild marvel in Mayfair<br />
McGee uses Asta Powerproject<br />
to make the 'impossible' Mayfair<br />
Hotel megabuild a reality<br />
Specialist engineering contractor,<br />
McGee, used Asta Powerproject<br />
to sequence and manage a<br />
ground-breaking five-storey mega<br />
basement for Claridge's Hotel. The<br />
cutting-edge planning and project<br />
management software enabled<br />
McGee's project managers to<br />
implement pioneering techniques,<br />
mitigate structural risk, and coordinate<br />
material movements on an incredibly<br />
challenging site.<br />
The project, which received a Fleming<br />
Award and a Ground Engineering<br />
award and was the subject of a BBC<br />
television documentary, 'The Mayfair<br />
Hotel Megabuild', enabled Asta<br />
Powerproject to:<br />
Sequence the execution of a<br />
65,000-square-foot basement<br />
extension underneath a live hotel -<br />
something other engineering<br />
companies said was impossible<br />
Coordinate complex labour<br />
schedules involving regular<br />
building contractors and a team of<br />
mining contractors working around<br />
the clock<br />
Synchronise daily material<br />
deliveries from an offsite holding<br />
yard due to lack of storage space<br />
on-site<br />
Complete the five-storey mega<br />
basement six months ahead of<br />
schedule to critical and customer<br />
acclaim.<br />
A<strong>CC</strong>EPTING AN 'IMPOSSIBLE'<br />
ENGINEERING PROJECT<br />
McGee has a reputation for accepting<br />
ambitious projects - from complex<br />
demolition work to facilitate the UK's<br />
HS2 high-speed railway line to leading<br />
Phase 3 earthworks for the<br />
redevelopment of London's Battersea<br />
Power Station.<br />
But these projects seem<br />
straightforward compared to the<br />
trailblazing work that McGee completed<br />
for Claridge's Hotel in 2015/16 when<br />
they took on a job that no other<br />
engineering company thought was<br />
possible. Claridge's wanted to increase<br />
its capacity by 50%, adding a five-storey<br />
mega basement underneath the hotel to<br />
house two swimming pools, a spa, a<br />
state-of-the-art wine cellar, a kitchen,<br />
and laundry facilities.<br />
This plan was ambitious in itself, but<br />
another layer of complexity existed. The<br />
hotel needed to remain open<br />
throughout the build, and construction<br />
works could not disturb the first-class<br />
experience that Claridge's Hotel guests<br />
expect to receive.<br />
"Every other company invited to<br />
tender wanted to do a traditional<br />
project, but the client was adamant that<br />
they didn't want to close the hotel. But<br />
whenever someone says something<br />
can't be done, we say challenge<br />
accepted!", said Michelle Mackey,<br />
Project Engineer, McGee.<br />