Installation, Maintenance and Operation Manual - Tyco Thermal ...
Installation, Maintenance and Operation Manual - Tyco Thermal ...
Installation, Maintenance and Operation Manual - Tyco Thermal ...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Figure 5: Typical cable layout on bigger surfaces as tank walls<br />
Prepunched<br />
strapping<br />
Temperature<br />
sensor<br />
Temperature<br />
controller<br />
Figure 6: Fixation device: prepunched steel strap<br />
D Use insulation entry kits, where cable penetrates the metallic<br />
insulation cladding by design. In all other places, where<br />
cable passes through metal sheet like cladding front disks<br />
(e.g. on valves) protective rubber profiles G-02 should be<br />
used to mechanically protect the cable.<br />
3.4 Cutting the heating cable<br />
D Before cutting it, confirm the minimum required length <strong>and</strong><br />
tracing allowances.<br />
D Any change to designed circuit length will change power<br />
output <strong>and</strong> design must be reconfirmed.<br />
D Cut the heating cable to length after it is attached to the<br />
pipe.<br />
10<br />
Cold leads<br />
Heating cable<br />
Junction<br />
box