Development of a Cold Gas Propulsion System for the ... - SSL - MIT
Development of a Cold Gas Propulsion System for the ... - SSL - MIT Development of a Cold Gas Propulsion System for the ... - SSL - MIT
5.2.3 High Side of CGSE As mentioned previously, in order to use the flight regulator, it was necessary to construct the entire high side of the CGSE. As shown in Figure 3-3, this required fill and shutoff valves as well as tubing to connect them to the tanks and the flight regulator. Sizing of these valves and the tubing was based largely on practical assembly considerations; flow characteristics were also taken into account but without rigorous analysis. For instance, the tubing used to connect the two flight tanks to a single line to feed into the regulator needed to be rated for at least 4500 psia, but it should also be bendable, since this would allow for less mass and a wider range of possible angles as opposed to using elbow fittings for each turn in the tubing. These criteria led to the selection of 0.5 in. OD (0.334 in. ID) stainless steel tubing, which also interfaced well with the fittings in the necks of the tanks. Two lines of this tubing (one from each tank) came together at a three-way tee fitting, with the third branch leading to the flight regulator. Because this line to the regulator had to carry the flow from both tank lines, it was believed that its internal diameter should be larger than that of the two tank lines. Very few three-way tee fittings satisfied this, but the one selected had a 0.5 in. ID passage leading towards the regulator. This dimension was maintained by using 0.75 in. OD stainless steel tubing with 0.51 in. ID to complete a straight run to the regulator. The regulator had a main valve orifice of 0.375 in. [54], so it was believed that the tubing selections described would not restrict the gas flow more than the regulator itself would. The selection of high-side tubing helped to guide the selection of the fill and shutoff valves. Both of these valves are manually-actuated ball valves. The flow path through a ball valve is a simple straight line, so when the valve is fully open, it has a high flow capacity with minimal effect on the flow through it [56]. The ball valves selected for the CGSE were manually actuated with a quarter-turn handle, since electric or pneumatic actuators that could be controlled remotely were too large and heavy. Since the shutoff valve was to be placed in line with the single high side feed path to the flight regulator, it was chosen to have an internal diameter of 0.5 in. to match the rest of the line. The fill valve was chosen from the same family of valves as the shutoff valve, but it did not need to be as large since it was not in the main flow path. In fact, it was considered advantageous to have a smaller fill valve, since that would limit the flow rate during filling and allow more time for conditions to settle in the flight tanks, and also provide the opportunity for some mass savings. Thus, the fill valve was selected to have a size of 0.25 in. It was placed on the branch of a three-way tee fitting which had a run of 0.5 in. ID along the main flow path to the regulator. The high side of the CGSE built for single-stream characterization testing is pictured in Figure 5-5. 78
Figure 5-5. CGSE high side as constructed for single-stream characterization tests. As shown in Figure 5-5, a four-way cross fitting with pressure and temperature sensors similar to those used at the inlet and outlet of the thruster solenoid valve was placed just before the inlet of the regulator to measure conditions on the high side throughout the single-stream tests. With the construction of the high side, the third and final configuration for the single-stream characterization tests was as illustrated in Figure 5-6. Figure 5-6. Third configuration for single-stream characterization tests [38]. 79
- Page 29 and 30: An alternate approach to resolving
- Page 31 and 32: accurate conditions for testing GNC
- Page 33 and 34: Ballistic hops tend to use less pro
- Page 35 and 36: 2.3.2 Comparison of Cold Gas and Mo
- Page 37 and 38: Handling propellant There are sever
- Page 39 and 40: and if the cold gas system was foun
- Page 41 and 42: 3 TALARIS CGSE Design Framework Aft
- Page 43 and 44: Figure 3-1. Scaling of TALARIS terr
- Page 45 and 46: (3) Providing attitude control Ther
- Page 47 and 48: Figure 3-2 also shows the body coor
- Page 49 and 50: 4 Modeling and Flow Control Compone
- Page 51 and 52: 4.1.2 Rocket Propulsion Equations L
- Page 53 and 54: variables in equation (4-8) deal wi
- Page 55 and 56: equations. Equation (4-10) was then
- Page 57 and 58: that of helium (0.227 MPa = 32.9 ps
- Page 59 and 60: thruster solenoid valve, and chambe
- Page 61 and 62: where
- Page 63 and 64: discussed later in section 6.3.4, t
- Page 65 and 66: The flight profile begins with maxi
- Page 67 and 68: hop, any given valve or regulator o
- Page 69 and 70: esponse time was an important perfo
- Page 71 and 72: directly opens and closes the main
- Page 73 and 74: If 1D isentropic flow is assumed, t
- Page 75 and 76: 5 Single-Stream Component Testing A
- Page 77 and 78: the solenoid valve, and a pressure
- Page 79: As indicated in Figure 5-3, initial
- Page 83 and 84: Figure 5-7 illustrates several aspe
- Page 85 and 86: 6 Full Eight-Thruster Flight System
- Page 87 and 88: Figure 6-2. TALARIS CGSE assembled
- Page 89 and 90: stream tests revealed that changes
- Page 91 and 92: Figure 6-5. Original CGSE control c
- Page 93 and 94: other constraints. This was difficu
- Page 95 and 96: variables (such as number of thrust
- Page 97 and 98: One solution to this problem would
- Page 99 and 100: One of the characterization tests w
- Page 101 and 102: or more thrusters were firing toget
- Page 103 and 104: Table 6-3. Valve timing metrics dur
- Page 105 and 106: Figure 6-11. Redesigned CGSE contro
- Page 107 and 108: The imaginary simplified thruster c
- Page 109 and 110: traverse phase of a hop and involve
- Page 111 and 112: Figure 7-3. GNC data from 3-DOF tes
- Page 113 and 114: Tests on this vertical stand demons
- Page 115 and 116: control the belay line can be put u
- Page 117 and 118: accounting for changes in thrust le
- Page 119 and 120: development under the supervision o
- Page 121 and 122: documenting progress takes time whi
- Page 123 and 124: were encountered, it was harder to
- Page 125 and 126: [10] Bryant, K. M., Knight, C. J.,
- Page 127 and 128: [31] Canadian Centre for Occupation
Figure 5-5. CGSE high side as constructed <strong>for</strong> single-stream characterization tests.<br />
As shown in Figure 5-5, a four-way cross fitting with pressure and temperature sensors similar to those<br />
used at <strong>the</strong> inlet and outlet <strong>of</strong> <strong>the</strong> thruster solenoid valve was placed just be<strong>for</strong>e <strong>the</strong> inlet <strong>of</strong> <strong>the</strong><br />
regulator to measure conditions on <strong>the</strong> high side throughout <strong>the</strong> single-stream tests.<br />
With <strong>the</strong> construction <strong>of</strong> <strong>the</strong> high side, <strong>the</strong> third and final configuration <strong>for</strong> <strong>the</strong> single-stream<br />
characterization tests was as illustrated in Figure 5-6.<br />
Figure 5-6. Third configuration <strong>for</strong> single-stream characterization tests [38].<br />
79