Development of a Cold Gas Propulsion System for the ... - SSL - MIT

Development of a Cold Gas Propulsion System for the ... - SSL - MIT Development of a Cold Gas Propulsion System for the ... - SSL - MIT

26.12.2012 Views

of the thruster valves never shut completely for the longer pulses, so the 10 individual commanded pulses effectively ran together into one long pulse. Only one of the thrusters even came close to meeting the requirements of the 5 Hz control cycle, and it still produced a minimum pulse width of only about 60 ms reliably [59]. This performance was far worse than that observed for the single-stream thruster (as illustrated in Figure 5-8), so an investigation of the possible reasons for this was conducted. At first, it was thought that the thruster valve used in the single-stream tests might have been unusually fast, and the results obtained with CGSE flight system simply represented a more typical distribution of valve timing performance. However, the response times observed in the first round of pulse testing of the CGSE flight system were far slower than the 30 to 60 ms range quoted in the SV128 specifications [52], so it was suspected that some external influence might be slowing the valves down. To examine this possibility in more detail, the valve response time was broken down into four timing metrics, as illustrated in Figure 6-9. Figure 6-9. Valve timing metrics [59]. As shown in Figure 6-9, the opening time of the valve was separated into two parts: open lag, which was the time between the command to open the valve and the point at which the load cell began to measure an increase in thruster force, and rise time, which was defined as the time between measuring 10% and 90% of the steady-state force. Similarly, closing time was broken into close lag and 90-10% fall time. Measurements for these four timing metrics for each thruster valve as taken in the first round of CGSE flight system pulse testing are presented in Table 6-3. 100

Table 6-3. Valve timing metrics during first CGSE flight system pulse tests [59]. Valve Timing Metrics [ms] Thruster 1 2 3 4 5 6 7 8 Avg. Open Lag 12 18 13 21 13 20 12 22 16 Rise Time 15 20 16 18 17 19 15 19 17 Close Lag 19 43 72 56 66 79 62 39 54 Fall Time 16 23 16 25 16 24 16 17 19 Table 6-3 reveals that the Close Lag time had by far the largest magnitude compared to all of the other valve timing metrics. Furthermore, thruster 1 was the one thruster performing close to acceptably, and it had a Close Lag time shorter than that of any of the other thrusters. 8 This suggested that most of the CGSE thrusters were staying open for an extended length of time after the closing signal had been sent. After conversations with Draper electrical engineers and re-examination of the CGSE control circuits depicted in Figure 6-4 and Figure 6-5, the flyback diode was targeted as the cause of this issue. In essence, the original control circuit allowed induced voltage to continue cycling power through the solenoid, holding the valve open for a significant length of time after the power/signal from the RIO was shut off. To eliminate this problem, a new CGSE control circuit was designed to quickly dissipate the induced voltage while still protecting the RIO. In the new CGSE circuit, the 24 V output from the RIO was used as a control signal only, providing the gate voltage to a MOSFET. The thruster solenoids drew their power from the low power battery via a newly designed low power distribution board, and the MOSFET acted as a switch to close and open the circuit. Because the MOSFET could withstand large voltage spikes, it was possible to place a resistor in series with the flyback diode to cut down the current more rapidly when the solenoid was switched off. The modified CGSE control circuit is shown in Figure 6-10. 8 The reason for this was not fully understood. Thruster 1 had the hardline dump circuit variant, but there was no apparent reason why that would have improved the Close Lag time. It is possible that there was a poor electrical connection to the flyback diode, either increasing the resistance of that path or failing to close it at all. If so, the RIO might have been exposed to back voltage if not for the additional diode in series with the solenoid, in which case it was quite fortunate that this anomaly did occur in the circuit with the hardline dump modification. 101

<strong>of</strong> <strong>the</strong> thruster valves never shut completely <strong>for</strong> <strong>the</strong> longer pulses, so <strong>the</strong> 10 individual commanded<br />

pulses effectively ran toge<strong>the</strong>r into one long pulse. Only one <strong>of</strong> <strong>the</strong> thrusters even came close to<br />

meeting <strong>the</strong> requirements <strong>of</strong> <strong>the</strong> 5 Hz control cycle, and it still produced a minimum pulse width <strong>of</strong> only<br />

about 60 ms reliably [59]. This per<strong>for</strong>mance was far worse than that observed <strong>for</strong> <strong>the</strong> single-stream<br />

thruster (as illustrated in Figure 5-8), so an investigation <strong>of</strong> <strong>the</strong> possible reasons <strong>for</strong> this was conducted.<br />

At first, it was thought that <strong>the</strong> thruster valve used in <strong>the</strong> single-stream tests might have been unusually<br />

fast, and <strong>the</strong> results obtained with CGSE flight system simply represented a more typical distribution <strong>of</strong><br />

valve timing per<strong>for</strong>mance. However, <strong>the</strong> response times observed in <strong>the</strong> first round <strong>of</strong> pulse testing <strong>of</strong><br />

<strong>the</strong> CGSE flight system were far slower than <strong>the</strong> 30 to 60 ms range quoted in <strong>the</strong> SV128 specifications<br />

[52], so it was suspected that some external influence might be slowing <strong>the</strong> valves down. To examine<br />

this possibility in more detail, <strong>the</strong> valve response time was broken down into four timing metrics, as<br />

illustrated in Figure 6-9.<br />

Figure 6-9. Valve timing metrics [59].<br />

As shown in Figure 6-9, <strong>the</strong> opening time <strong>of</strong> <strong>the</strong> valve was separated into two parts: open lag, which was<br />

<strong>the</strong> time between <strong>the</strong> command to open <strong>the</strong> valve and <strong>the</strong> point at which <strong>the</strong> load cell began to<br />

measure an increase in thruster <strong>for</strong>ce, and rise time, which was defined as <strong>the</strong> time between measuring<br />

10% and 90% <strong>of</strong> <strong>the</strong> steady-state <strong>for</strong>ce. Similarly, closing time was broken into close lag and 90-10% fall<br />

time. Measurements <strong>for</strong> <strong>the</strong>se four timing metrics <strong>for</strong> each thruster valve as taken in <strong>the</strong> first round <strong>of</strong><br />

CGSE flight system pulse testing are presented in Table 6-3.<br />

100

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!