Headquarters Pfungstadt: Progress is being made<br />
For a long time it felt like nothing<br />
was happening on our construction<br />
site for the new headquarters in<br />
Pfungstadt. There were even rumors<br />
of an alleged construction stop. But<br />
sometimes it's the bureaucracy that<br />
gets in the way. After about seven<br />
months of waiting, work on the office<br />
building could finally begin.<br />
The necessary ground work had<br />
already been completed for some<br />
time.<br />
Now things are finally moving forward<br />
and our new office space is taking<br />
shape in the form of the floor<br />
slab. At 3 o'clock in the morning the<br />
work started. Eight trucks shuttled<br />
the concrete from Gernsheim to the<br />
construction site. A total of approximately<br />
65 tons of steel for the reinforcement<br />
and 260 m³ of concrete<br />
were used. The dimensions of the<br />
future office complex are now already<br />
clearly visible. The warehouse<br />
will later join the office building in<br />
the southwest.<br />
We are pleased with the great progress<br />
on our construction site and<br />
can hardly wait to move into the<br />
new headquarters in 2023.<br />