ATTACHMENT 17

Airport CDM adverse Objectives conditions & Key Performance – impact assessment, Indicatorsprocesses, and best practices

D. Process for milestone: Commencement of apron/remote aircraft de-icing

This Process is highly recommended

Objective

First step: Inform all relevant airport CDM partners of the actual commencement of de-icing time (ACZT) in the

airport CDM platform.

ACZT

Update Airport CDM platform

Inform all partners

ACZT

Generate T-DPI message

Send to Network Operations

Second step: Check whether ACZT is in accordance with estimated commencement of de-icing time (ECZT)

and alert all relevant airport CDM partners if de-icing has not started according to plan.

ACZT

ECZT

ECZT-TOLERANCE CHECK

is ACTZ recorded at

ECZT + tolerance value?

Tolerance value of + 5 minutes

for example

NO

YESg Do nothing

Generate

alert

message

Inform partners

Update planning

Description

Inform airport partners and Network Operations of

ACZT when it occurs. In case commence of de-icing

is not started at ECZT + tolerance, all relevant partner

should be informed, and the de-icing sequence

planning updated. Relevant partners are initially the

handling agent, Airline operator, and ATC.

Trigger

ACZT: Automated input from de-icing coordinator or

vehicle

ECZT + tolerance value passed

Pre-condition

Actual off-block time recorded

Taxi clearance recorded

Weather conditions set to winter conditions

Flight crew de-icing request recorded