Commissioning Procedure<br />

PRE COMMISSIONING CHECKLIST<br />

• Check that each circuit trips on low pressure. The alarm should appear within<br />

3 minutes.<br />

• The alarm will be recognised at the display circuit trip, to clear the alarms refer<br />

to Alarm Handling.<br />

CAUTION<br />

RECORD<br />

RECORD<br />

<strong>Chillers</strong><br />

42 Installation & Maintenance : 903-129 IM E 10/04/C<br />

Prior to the chiller compressors being allowed to start, the Water Flow Fail and<br />

Pump Interlock features MUST both be proven to work correctly.<br />

• To check the water flow fail safety protection is working satisfactorily:<br />

Reduce the flow rate to 75% of design and ensure that the evaporator pressure or<br />

flow protection switch trips at this flow rate, adjust as necessary.<br />

With compressors off, ensure this alarm is recognised as “Water Flow Fail” at the<br />

display and disengages the circuits operation immediately. Restore flow rate to the<br />

design and check the alarm has self-cleared.<br />

• To check the pump interlock safety feature works satisfactorily:<br />

Switch off the chiller water pump and check the interlock wiring connections at the<br />

chiller are open circuit.<br />

To switch the unit OFF, use the microprocessor keypad as follows:<br />

Press Prg<br />

, press , press , press & finally .<br />

Fully open all liquid line and discharge service ball valves on each circuit.