COMMISSIONING REPORTForm No.: WZSMS-M2201-QAC-F-022Rev.: 00Date:31-May-22Page:1 of 1Project Title: EPCC for TWPP FOR Sarawak Methanol ProjectContract No.: SP/EPCC/P1/2021/007Report no.: MS-M2201-QAQC-CMM-R-Date:OWNER: SARAWAK PETCHEM SDN. BHD.Pipeline section:Type of operation:Service Line Feeder Line Distribution LineItemCheck Point Location Date/Time Status (Acc/Rej) RemarksEquipment Serial No. Calibration Date Certificate No.VERIFICATIONWe hereby verify that the item(s) described above has been inspected, tested and complies with the term of the order.QC Inspector:OWNER Representative:Signature : Signature :Name : Name :Date : Date :*NOTE :All verification must complete with stamp
COMMISSIONING REPORT
Form No.: WZSMS-M2201-QAC-F-022
Rev.: 00
Date:
31-May-22
Page:
1 of 1
Project Title: EPCC for TWPP FOR Sarawak Methanol Project
Contract No.: SP/EPCC/P1/2021/007
Report no.: MS-M2201-QAQC-CMM-R-
Date:
OWNER: SARAWAK PETCHEM SDN. BHD.
Pipeline section:
Type of operation:
Service Line Feeder Line Distribution Line
Item
Check Point Location Date/Time Status (Acc/Rej) Remarks
Equipment Serial No. Calibration Date Certificate No.
VERIFICATION
We hereby verify that the item(s) described above has been inspected, tested and complies with the term of the order.
QC Inspector:
OWNER Representative:
Signature : Signature :
Name : Name :
Date : Date :
*NOTE :All verification must complete with stamp