4 General Technical Specification of Bhilai Steel Plant, SAIL ...
4 General Technical Specification of Bhilai Steel Plant, SAIL ... 4 General Technical Specification of Bhilai Steel Plant, SAIL ...
© 2007 MECON Limited All rights reserved General Technical Specification indication for cleaning / replacement of the filter element. The filter bodies shall preferably be of copper alloy or stainless steel and filter element of copper alloy or glass cloth suitably earthed to the filter body with copper wires. Two (2) or more pressure relief valves should be provided downstream of each set of pressure reducing valves. One or more main relief valve(s) should be capable of discharging 100% of the full oxygen flow and limiting the pressure within the defined limits. The secondary relief valve should be sized to discharge the nominal leakage from the pressure reducing valves. The relief valves should be positioned as close as possible to the pressure reducing valves. The vent lines from the relief valves should be preferably of stainless steel or copper. Consideration should be given for providing small size pressure equalisation bypass isolation valves across large diameter isolation valves in large pipeline systems so as to ensure safe pressurization of the downstream pipeline. The bypass pipe work and valve should be of copper or copper alloy. Fire break sections may be installed in the oxygen pipeline to limit the propagation of combustion in a steel pipeline. Fire break sections may be introduced immediately downstream of the main isolation and throttling valves where the velocities can be high. The fire break section will be either a length of copper pipe having the same inside diameter as the main pipe with flanges fitted at the two ends which is installed between the steel pipes or a copper insert tube made from copper sheet / tube and inserted inside the steel pipe downstream of the valves. The copper insert tube is generally used in large diameter steel pipelines. In steel pipelines, care should be taken to install isolation valves on straight sections of the pipeline. Any pipeline component which is likely to cause a change in the flow pattern, like reducer, bend, tee or “Y” connection, orifice plate etc., should be at a distance of at least four diameters away from the valve. For cleaning of the gaseous oxygen pipelines after erection, provision for “pigging” will be provided for pipelines having diameters upto DN 200. However, if the pipeline is pickled and phosphated as per approved procedure, pigging of pipelines is not essential. The bends on these pipelines will have a radius of 5 DN. Extra care will be taken regarding cleanliness of large dia. pipeline (DN 250 and above) during installation. The bends for the larger dia. Pipes will have a radius of 3 DN. Gaseous oxygen pipe work shall preferably have butt welded pipe joints. To reduce safety hazards the number of components should be kept to a minimum compatible with the system requirements. Flange joints shall be used only for connection of the pipe to the system components on the pipe work. Threaded joints and couplings should be sparingly used. 02.14. DESIGN CONSIDERATIONS Piping system shall be designed with high degree of reliability so that the systems perform the duty of fluid handling without structural or functional failure under most adverse condition of plant operation. All piping systems shall be designed with sufficient corrosion and stress margins to ensure a life time without failure, not less than the life of the plant. 7000 complete cycle of operation shall be considered for stress analysis purpose. Piping system shall not impose reactions on equipment terminals exceeding permissible limits even under adverse operating conditions. Personnel injury from discharge of hot fluids from drains, steam traps, hot pipes or exposures to pipe vibrations shall be guarded against. Piping coming under the purview of Indian Boiler Regulations (IBR) shall be designed in accordance with such regulations. The design criteria of piping coming under the purview of IBR shall have to be approved by "Chief Inspector of Boilers" Gases & Liquid Fluids Page 16 of 51 GS-02
© 2007 MECON Limited All rights reserved General Technical Specification of the respective State prior to manufacture. All welding procedures, stress relieving procedures, inspection / testing / certificates and all other records shall have to be approved by Chief Inspector of Boilers in approved form. Pipes having nominal bore less than 15 mm, shall not be used. Design pressure of steam and all other service pipelines shall be considered as 1.2 times the maximum expected pressure. However it shall not be less than 4.0 kg/cm 2 gauge for steam services and 3.5 kg/cm 2 gauge for other services. Design temperature for steam services shall be as pr IBR and for other pipelines shall be 5 deg. above the maximum sustained service temperature expected. All the piping coming under the purview of IBR, shall be designed with the allowable design stresses as per IBR. For all other piping, the allowable design stress shall not be more than that specified in ANSI B 31.1 or BS:806 latest revision. Pipe thickness of all pipeline shall be taken as per the pipe thickness schedules. The design and stress analysis shall take into account the effect of internal/external pressures, thermal expansion, self weight of piping, support reactions, shock due to relieving devices, surge and water hammer, earth quake and wind effect, noise and vibrations, corrosion and erosion etc. and any other effects dictated by recommended engineering practices. Adequate flexibility shall be provided in the pipelines to keep stress and reactions in the system arising due to thermal expansion or other effects within limits. Where the piping terminates at an equipment or at the terminal point of a system, the reactions and thermal movement imposed by piping on the equipment or the system concerned shall be well within the limits specified. The flexibility analysis of steam, condensate and hot service media pipelines shall be furnished. 01. Pipes shall be sized for minimum pressure drops and considering the velocity limitation for various types of fluids. 02. Adequate flexibility shall be provided in the pipelines to keep stresses and reactions in the system arising due to thermal expansion or other effects within limits. Where the piping terminates at an equipment or at the terminal point of a system, the reactions and thermal movement imposed by piping on the equipment or the system concerned shall be well within the limits specified. 03. If cold springing of pipeline is used, care shall be taken in determining the location and amount of cold spring gap. Cold spring gap shall be located at points where the bending and torsional moments are minimum. Use of cold spring gaps less than 10mm shall not be acceptable and cold spring gaps above 100mm shall be avoided. All outdoor piping exposed to sunlight carrying fluid at a temperature less than 80 0 C shall be designed considering thermal expansion corresponding to 80 0 C and empty pipe as one of the operating conditions although not necessarily the worst. 04. All piping shall have butt welded connections with minimum of flanged joints for connection to vessels and equipment to facilitate erection and maintenance. All high pressure steam valves and accessories shall have welded connections. Standard fittings shall be used wherever practicable. Unless otherwise specified, for all welded lines with pressure above 4 kg/cm2 g and / or temperature above 200 0 C, branch connections with branch sizes upto 25% of welded mains shall be made with special forged steel welded fittings. Gases & Liquid Fluids Page 17 of 51 GS-02
- Page 5 and 6: 01 FLUID SYSTEM 01.01 Water Supply
- Page 7 and 8: Sl. No. © 2007 MECON Limited All r
- Page 9 and 10: © 2007 MECON Limited All rights re
- Page 11 and 12: © 2007 MECON Limited All rights re
- Page 13 and 14: © 2007 MECON Limited All rights re
- Page 15 and 16: © 2007 MECON Limited All rights re
- Page 17 and 18: © 2007 MECON Limited All rights re
- Page 19 and 20: © 2007 MECON Limited All rights re
- Page 21 and 22: SL. NO. © 2007 MECON Limited All r
- Page 23 and 24: © 2007 MECON Limited All rights re
- Page 25 and 26: © 2007 MECON Limited All rights re
- Page 27 and 28: 20 F.D.A SYSTEM SUPPLIERS 21 © 200
- Page 29 and 30: Sl. No. © 2007 MECON Limited All r
- Page 31 and 32: Sl. No. © 2007 MECON Limited All r
- Page 33 and 34: Sl. No. 14. SPM analyser 15. SOx- N
- Page 35 and 36: SL. NO. 1. Hood, Stack and Lance se
- Page 37 and 38: © 2007 MECON Limited All rights re
- Page 39 and 40: SL. NO. © 2007 MECON Limited All r
- Page 41 and 42: 02. GASES AND LIQUID FUELS 02.01. R
- Page 43 and 44: © 2007 MECON Limited All rights re
- Page 45 and 46: © 2007 MECON Limited All rights re
- Page 47 and 48: © 2007 MECON Limited All rights re
- Page 49 and 50: © 2007 MECON Limited All rights re
- Page 51 and 52: © 2007 MECON Limited All rights re
- Page 53 and 54: © 2007 MECON Limited All rights re
- Page 55: © 2007 MECON Limited All rights re
- Page 59 and 60: © 2007 MECON Limited All rights re
- Page 61 and 62: © 2007 MECON Limited All rights re
- Page 63 and 64: © 2007 MECON Limited All rights re
- Page 65 and 66: © 2007 MECON Limited All rights re
- Page 67 and 68: © 2007 MECON Limited All rights re
- Page 69 and 70: © 2007 MECON Limited All rights re
- Page 71 and 72: © 2007 MECON Limited All rights re
- Page 73 and 74: © 2007 MECON Limited All rights re
- Page 75 and 76: © 2007 MECON Limited All rights re
- Page 77 and 78: © 2007 MECON Limited All rights re
- Page 79 and 80: © 2007 MECON Limited All rights re
- Page 81 and 82: © 2007 MECON Limited All rights re
- Page 83 and 84: © 2007 MECON Limited All rights re
- Page 85 and 86: © 2007 MECON Limited All rights re
- Page 87 and 88: © 2007 MECON Limited All rights re
- Page 89 and 90: © 2007 MECON Limited All rights re
- Page 91 and 92: © 2007 MECON Limited All rights re
- Page 93 and 94: © 2007 MECON Limited All rights re
- Page 95 and 96: © 2007 MECON Limited All rights re
- Page 97 and 98: © 2007 MECON Limited All rights re
- Page 99 and 100: © 2007 MECON Limited All rights re
- Page 101 and 102: 01.04 Primer Paint - P4 (Epoxy Base
- Page 103 and 104: © 2007 MECON Limited All rights re
- Page 105 and 106: 03.06 Finish Paint - F6 © 2007 MEC
© 2007 MECON Limited<br />
All rights reserved<br />
<strong>General</strong> <strong>Technical</strong> <strong>Specification</strong><br />
<strong>of</strong> the respective State prior to manufacture. All welding procedures, stress<br />
relieving procedures, inspection / testing / certificates and all other records shall<br />
have to be approved by Chief Inspector <strong>of</strong> Boilers in approved form.<br />
Pipes having nominal bore less than 15 mm, shall not be used. Design pressure <strong>of</strong><br />
steam and all other service pipelines shall be considered as 1.2 times the<br />
maximum expected pressure. However it shall not be less than 4.0 kg/cm 2 gauge<br />
for steam services and 3.5 kg/cm 2 gauge for other services.<br />
Design temperature for steam services shall be as pr IBR and for other pipelines<br />
shall be 5 deg. above the maximum sustained service temperature expected.<br />
All the piping coming under the purview <strong>of</strong> IBR, shall be designed with the<br />
allowable design stresses as per IBR. For all other piping, the allowable design<br />
stress shall not be more than that specified in ANSI B 31.1 or BS:806 latest<br />
revision. Pipe thickness <strong>of</strong> all pipeline shall be taken as per the pipe thickness<br />
schedules. The design and stress analysis shall take into account the effect <strong>of</strong><br />
internal/external pressures, thermal expansion, self weight <strong>of</strong> piping, support<br />
reactions, shock due to relieving devices, surge and water hammer, earth quake<br />
and wind effect, noise and vibrations, corrosion and erosion etc. and any other<br />
effects dictated by recommended engineering practices.<br />
Adequate flexibility shall be provided in the pipelines to keep stress and reactions<br />
in the system arising due to thermal expansion or other effects within limits. Where<br />
the piping terminates at an equipment or at the terminal point <strong>of</strong> a system, the<br />
reactions and thermal movement imposed by piping on the equipment or the<br />
system concerned shall be well within the limits specified.<br />
The flexibility analysis <strong>of</strong> steam, condensate and hot service media pipelines shall<br />
be furnished.<br />
01. Pipes shall be sized for minimum pressure drops and considering the velocity limitation<br />
for various types <strong>of</strong> fluids.<br />
02. Adequate flexibility shall be provided in the pipelines to keep stresses and reactions in<br />
the system arising due to thermal expansion or other effects within limits. Where the<br />
piping terminates at an equipment or at the terminal point <strong>of</strong> a system, the reactions and<br />
thermal movement imposed by piping on the equipment or the system concerned shall<br />
be well within the limits specified.<br />
03. If cold springing <strong>of</strong> pipeline is used, care shall be taken in determining the location and<br />
amount <strong>of</strong> cold spring gap. Cold spring gap shall be located at points where the bending<br />
and torsional moments are minimum. Use <strong>of</strong> cold spring gaps less than 10mm shall not<br />
be acceptable and cold spring gaps above 100mm shall be avoided. All outdoor piping<br />
exposed to sunlight carrying fluid at a temperature less than 80 0 C shall be designed<br />
considering thermal expansion corresponding to 80 0 C and empty pipe as one <strong>of</strong> the<br />
operating conditions although not necessarily the worst.<br />
04. All piping shall have butt welded connections with minimum <strong>of</strong> flanged joints for<br />
connection to vessels and equipment to facilitate erection and maintenance. All high<br />
pressure steam valves and accessories shall have welded connections. Standard fittings<br />
shall be used wherever practicable. Unless otherwise specified, for all welded lines with<br />
pressure above 4 kg/cm2 g and / or temperature above 200 0 C, branch connections with<br />
branch sizes upto 25% <strong>of</strong> welded mains shall be made with special forged steel welded<br />
fittings.<br />
Gases & Liquid Fluids<br />
Page 17 <strong>of</strong> 51<br />
GS-02