Project Cost Management

7.4 CONTROL COST

Variance analysis: as used in EVM, is the explanation (cause, impact, and corrective actions) for cost (CV = EV – AC),

schedule (SV = EV – PV), and variance at completion (VAC = BAC – EAC) variances.