6.5 DEVELOP SCHEDULE

Project Schedule Management

Resource leveling: A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for

resources with the available supply. Leveling lengthens the schedule and increases cost in order to deal with a limited amount of resources

Resource Smoothing: Resource smoothing is a modified form of resource leveling, where resources are leveled only within the limits of the float

of their activities, so the completion dates of activities are not delayed