STANDARDS AND GUIDELINES FOR COMMUNICATION SITES FOUNDATION DESIGN AND INSTALLATION<br />

2.10.2.2 PREPARATION<br />

2.10.2.3 POURING<br />

• All excavations on which concrete is to be placed shall be substantially horizontal on undisturbed<br />

<strong>and</strong> unfrozen soil <strong>and</strong> shall be free of loose material <strong>and</strong> excess ground water. Methods <strong>for</strong><br />

removing excess ground water shall be provided if required.<br />

• The foundation area shall be graded to provide water runoff <strong>and</strong> prevent water from st<strong>and</strong>ing. The<br />

final grade shall slope away in all directions from the foundation.<br />

• Concrete <strong>for</strong>ms of wood, metal centering, cores, molds, <strong>and</strong> so <strong>for</strong>th, shall be used as required <strong>for</strong><br />

the proper execution of the plain <strong>and</strong> rein<strong>for</strong>ced concrete work. Sufficient quantities shall be used<br />

to properly execute <strong>and</strong> expedite work without endangering the safety or strength of any part of the<br />

construction.<br />

• All <strong>for</strong>ming shall be true <strong>and</strong> rigid, thoroughly braced, <strong>and</strong> sufficiently strong to safely carry all<br />

dead <strong>and</strong> live loads to which it may be subjected. The elimination of <strong>for</strong>ming by a monolithic pour<br />

against undisturbed soil shall be allowed only if approved by a soils engineer <strong>and</strong>/or a qualified<br />

Motorola representative.<br />

• All steel rein<strong>for</strong>cement shall be furnished <strong>and</strong> installed in accordance with the approved foundation<br />

drawing. Unless otherwise specified or shown on plans, rein<strong>for</strong>cement shall consist of pre<strong>for</strong>med<br />

bars of intermediate grade, manufactured from new billet stock. Metal rein<strong>for</strong>cement shall con<strong>for</strong>m<br />

to the requirements of the latest version of Specifications <strong>for</strong> De<strong>for</strong>mation of Pre<strong>for</strong>med Steel Bars<br />

<strong>for</strong> Concrete Rein<strong>for</strong>cement, ASTM A615-68, or applicable jurisdictional code, whichever is more<br />

stringent.<br />

• Anchors, bolts, <strong>and</strong> miscellaneous iron work shall be set as shown in the drawings be<strong>for</strong>e pouring<br />

concrete. Embedded items shall be held rigidly in place during placing <strong>and</strong> curing of concrete.<br />

Placing rebar in position as the concrete is placed shall not be permitted.<br />

• Concrete shall be vibrated <strong>and</strong> thoroughly consolidated around all embedded items.<br />

• At least one week prior to all concrete pours, the proposed concrete mix design shall be submitted<br />

to Motorola or its contractor <strong>for</strong> verification of design specifications.<br />

• When concrete is placed, certificates shall be furnished <strong>for</strong> each delivery vehicle or every 5.4 m3 (7<br />

cu. Yds), showing the mix proportions, additives, compressive strength, <strong>and</strong> the br<strong>and</strong> name <strong>and</strong><br />

type of cement.<br />

• Concrete shall be so deposited that there will be no separation or segregation of aggregate.<br />

Maximum free drop shall not exceed 2.43 m (8 ft.).<br />

• Concrete shall not be placed when the outdoor temperature is below 4.5° C (40 degrees F) nor<br />

when the concrete is likely to be subjected to freezing temperatures be<strong>for</strong>e final set, except when<br />

adequate provisions have been made <strong>for</strong> protection. When deposited in the <strong>for</strong>ms, the concrete<br />

shall have a temperature of not less than 15.5° C (60° F) <strong>and</strong> not more than 32° C (90° F). A<br />

suitable means shall be provided to maintain the temperature above 10° C (50° F) <strong>for</strong> 7 days. The<br />

materials shall be heated be<strong>for</strong>e mixing to prevent concrete from freezing.<br />

2.10.2.4 BACKFILLING<br />

• After completion of the foundation <strong>and</strong> other construction below grade, <strong>and</strong> be<strong>for</strong>e backfilling, all<br />

excavations shall be clean of vegetation, trash, debris, <strong>and</strong> inorganic materials.<br />

68P81089E50-B 9/1/05 2-13