Once the Construction of the project is completed as per the sanctioned layout
plan, the Promoter is bound to obtain OC / CC for the project and only
thereafter can offer possession to the customers ( Registration of Sale Deed /
Sub-lease Deed / Registry is mandatory before physical possession given). For
exit under RERA The CC / OC is to be obtained and filed with RERA.
Application of Completion Certificate (CC) to Competent Authority
After completion of all the construction and development activities, the
Promoter shall submit application of Completion Certificate (CC) along with
said Four certificates to the Competent Authority and the Competent Officer
may reject the said application along with required changes with in 7 working
days from the date of application and intimate the same to the promoter with
in 8 working days and if the same is not intimated with in the said time period
than the Competent Officer shall considered the said Completion Certificate
as Deemed Approved.