Once the Construction of the project is completed as per the sanctioned layout

plan, the Promoter is bound to obtain OC / CC for the project and only

thereafter can offer possession to the customers ( Registration of Sale Deed /

Sub-lease Deed / Registry is mandatory before physical possession given). For

exit under RERA The CC / OC is to be obtained and filed with RERA.

Application of Completion Certificate (CC) to Competent Authority

After completion of all the construction and development activities, the

Promoter shall submit application of Completion Certificate (CC) along with

said Four certificates to the Competent Authority and the Competent Officer

may reject the said application along with required changes with in 7 working

days from the date of application and intimate the same to the promoter with

in 8 working days and if the same is not intimated with in the said time period

than the Competent Officer shall considered the said Completion Certificate

as Deemed Approved.