Redelivery

the redelivery of the Aircraft pursuant to the Redelivery Inspection and Acceptance Protocol with the

goal of achieving the Project Objective.

Lessor and Lessee will empower its Project Manager to make technical and commercial decisions on

its behalf in connection with the redelivery of the Aircraft to Lessor pursuant to the Redelivery

Inspection and Acceptance Protocol, recognising that certain decisions may need to be

communicated or escalated to/from the respective commercial management and/or technical teams

for resolution.

2.3 Lessor and Lessee Responsibilities

a) In order to meet the Project Objective, each of Lessee and Lessor will make commercially

reasonable efforts to:

(i) ensure that its Project Manager is able to devote sufficient time and effort to the redelivery of

the Aircraft so that its principal obligations in respect thereof are satisfied and to address

technical and commercial issues as they arise during the redelivery process in a manner

consistent with the goal of achieving the Project Objective and;

(ii) ensure that, as far as possible, the role of the Project Manager is filled at all times.

b) Application to Next Operator

(i) Lessee recognises that Lessor may wish the next operator or a prospective purchaser of the

Aircraft to participate in the redelivery process to facilitate aircraft transfer. Lessee agrees to

such participation of the next operator or such purchaser provided that as between Lessee

and Lessor:

2.4 Project Plan

a. Lessor will be responsible for the acts and omissions of the next operator or such

purchaser and;

b. the participation of the next operator or such purchaser in the redelivery process will not

affect the obligations of Lessor to perform its required actions pursuant to the Redelivery

Inspection and Acceptance Protocol to facilitate achieving the Project Objective.

a) Lessor and Lessee acknowledge that information and schedule dates are available at different

stages in the redelivery process, so the Project Plan will be provided to Lessor by Lessee in three

stages:

(i) Stage 1 Project Plan. No later than (X) months before the end of the lease term, Lessee will

provide Lessor with a draft Project Plan detailing the locations, timeline and critical

milestones for the Aircraft redelivery process. The draft Project Plan will set forth:

a. a list of the significant redelivery process tasks such as the induction date of the Aircraft

for the redelivery check;

b. confirmation of any Engine replacements;

c. proposed schedule for Aircraft Documentation Review and Aircraft inspection by Lessor,

and;

d. a schedule for Lessor and Lessee engagement through meetings in person and/or

teleconferences. Each significant task will be assigned a schedule date (major

milestone) in the draft Project Plan.

4 th Edition 2017 65