Re-powering Study for the Northport and Port Jefferson Power Stations Appendix I Northport Schedules Appendix I Northport Schedules March 30, 2009 142

Northport Repower Study Option 4 2x2x1 501G Re-use Unit 4 Steam Turbine Once Through Cooling LIPA issues RFP for PPA National Grid Selected for PPA Negotiate PPA PPA Approved BY LIPA NY State Comptroller PPA Approval Bid & Award Owners Engineer Contract Prepare Permitting Documents Obtain Permits Bid & Award EPC Contract Detailed Engineering & Design Begin Site Construction Award PO for CTG Manufacture & Deliver CTG Erect CTG Award PO for HRSG Manufacture & Deliver HRSG Erect HRSG Demolish Unit 4 Turbine Bldg Piping & Equip Install New Steam Piping and Refurbish U-4 STG Commissioning Unit 4 out of Service Begin Commercial Operation Re-powering Study for the Northport and Port Jefferson Power Stations Appendix I Northport Schedules Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Q1 Q2 Q3 Q4 Q5 Q6 Q7 Q8 Q9 Q10 Q11 Q12 Q13 Q14 Q15 Q16 Q17 Q18 Q19 Q20 Q21 Q22 Q23 Q24 Month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 March 30, 2009 143

Northport Repower Study<br />

Option 4<br />

2x2x1 501G Re-use Unit 4 Steam Turbine<br />

Once Through Cooling<br />

LIPA issues RFP for PPA<br />

National Grid Selected for PPA<br />

Negotiate PPA<br />

PPA Approved BY LIPA<br />

NY State Comptroller PPA Approval<br />

Bid & Award Owners Engineer Contract<br />

Prepare Permitting Documents<br />

Obtain Permits<br />

Bid & Award EPC Contract<br />

Detailed Engineering & Design<br />

Begin Site Construction<br />

Award PO for CTG<br />

Manufacture & Deliver CTG<br />

Erect CTG<br />

Award PO for HRSG<br />

Manufacture & Deliver HRSG<br />

Erect HRSG<br />

Demolish Unit 4 Turbine Bldg Piping & Equip<br />

Install New Steam Piping <strong>and</strong> Refurbish U-4 STG<br />

Commissioning<br />

Unit 4 out of Service<br />

Begin Commercial Operation<br />

Re-powering Study for the Northport <strong>and</strong> Port Jefferson Power Stations<br />

<strong>Appendix</strong> I Northport Schedules<br />

Year 1 Year 2 Year 3 Year 4 Year 5 Year 6<br />

Q1 Q2 Q3 Q4 Q5 Q6 Q7 Q8 Q9 Q10 Q11 Q12 Q13 Q14 Q15 Q16 Q17 Q18 Q19 Q20 Q21 Q22 Q23 Q24<br />

Month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72<br />

March 30, 2009 143