Re-powering Study for the Northport <strong>and</strong> Port Jefferson Power Stations<br />
<strong>Appendix</strong> VII Northport Capital Cost Estimate Descriptions<br />
• Gl<strong>and</strong> Seal <strong>and</strong> Exhaust system<br />
• Bypass steam system<br />
• Condenser air removal system<br />
• Condensate system including tank <strong>and</strong> two 100% capacity condensate pumps<br />
• Hydrogen system<br />
• CO system<br />
2<br />
• Nitrogen system<br />
• Closed cycle cooling water system including a 20 cell fin-fan cooler sized for all new equipment<br />
cooling requirements including steam turbine generator<br />
• Main step <strong>up</strong> transformer 13.8 to 345kV<br />
• High side gas insulated breaker<br />
• Generator synchronizing<br />
• Generator <strong>and</strong> transformer protection<br />
• Fire protection for steam turbine area<br />
C4 HRSG Vendor Package<br />
A heat recovery steam generator (HRSG) with integral deaerator, CO catalyst <strong>and</strong> selective catalytic<br />
reduction (SCR) is provided to accept the exhaust gases from each combustion turbine. The steam cycle<br />
design is a triple pressure, reheat cycle with throttle steam conditions of 1900 psig, 1050ºF.<br />
C4 HRSG Balance of <strong>Plan</strong>t<br />
The following items are included in the HRSG balance of plant:<br />
• HRSG foundations<br />
• Main steam piping<br />
• Hot reheat steam piping<br />
• Cold reheat steam piping<br />
• LP steam piping<br />
• Boiler feed water system with two 100-percent flow boiler feed water pumps per HRSG<br />
• Stack, common concrete shell 275 feet high with three 18 foot diameter flues<br />
• Boiler blowdown system<br />
• Boiler chemical feed system<br />
• Steam/water sampling system<br />
• Aqueous ammonia storage, 25,000 gallon (approximately 5 days)<br />
• Aqueous ammonia vaporization skid, one per HRSG<br />
March 30, 2009 253