Re-powering Study for the Northport <strong>and</strong> Port Jefferson Power Stations<br />

<strong>Appendix</strong> VII Northport Capital Cost Estimate Descriptions<br />

• HRSG foundations<br />

• Main steam piping<br />

• Hot reheat steam piping<br />

• Cold reheat steam piping<br />

• LP steam piping<br />

• Boiler feed water system with two 100-percent flow boiler feed water pumps per HRSG<br />

• Stack, one common concrete shell 250 feet high with two 22 foot diameter flues<br />

• Boiler blowdown system<br />

• Boiler chemical feed system<br />

• Steam/water sampling system<br />

• Aqueous ammonia storage, 20,000 gallons (approximately 5 days)<br />

• Aqueous ammonia vaporization skid, one per HRSG<br />

D3 Fuel Oil Facilities<br />

The distillate oil s<strong>up</strong>ply includes demolition of the existing dock west of unit 1 <strong>and</strong> installation of a new<br />

dock for barge unloading including unloading pumps <strong>and</strong> piping. An existing No. 6 oil tank will be<br />

demolished <strong>and</strong> replaced with a new 5,000,000 gallon distillate oil storage tank, sized for approximately<br />

five days operation. The new storage tank will be equipped with distillate oil forwarding pumps.<br />

D4 Onsite Natural Gas System<br />

The natural gas s<strong>up</strong>ply system is comprised of fuel gas piping <strong>and</strong> fuel gas conditioning equipment such<br />

as a scrubber, moisture separator, coalescing filters, filter /separator, <strong>and</strong> metering equipment for each<br />

combustion turbine. The MHI 501G gas turbine utilizes a bleed from the main gas turbine compressor to<br />

cool the power turbine blades. The compressor bleed air is first cooled in a fin-fan type cooler (TCA<br />

cooler). Waste heat from the TCA cooler is used to heat the incoming fuel gas. This TCA heat exchanger<br />

is provided as part of the gas turbine package. New, underground gas piping from a connection point at<br />

the existing gas yard to the new units is included.<br />

G5 Instruments <strong>and</strong> Controls<br />

Existing equipment to be reused will be controlled by the new DCS. Existing field instruments,<br />

transmitters, control drives will be reused. An allowance has been included in the repowering project cost<br />

estimate for miscellaneous refurbishment/replacement of existing control components. The existing<br />

uninterr<strong>up</strong>tible power s<strong>up</strong>ply <strong>and</strong> battery system will remain in service for any existing equipment that<br />

may not be connected to the new system.<br />

This account includes the following required for the new combined cycle equipment:<br />

• Distributed control system, including HRSG controls, combustion turbine generator controls,<br />

boiler feed pump controls, computer for data acquisition <strong>and</strong> logging <strong>and</strong> controls for existing<br />

equipment to be reused.<br />

• Uninterr<strong>up</strong>tible power s<strong>up</strong>ply <strong>and</strong> battery system sized to s<strong>up</strong>ply power for emergency controls<br />

<strong>and</strong> safe plant shutdown.<br />