Re-powering Study for the Northport <strong>and</strong> Port Jefferson Power Stations<br />
<strong>Appendix</strong> VII Northport Capital Cost Estimate Descriptions<br />
• Water injection skid<br />
• On-line <strong>and</strong> off-line compressor water wash system<br />
• Fire protection (CO2) <strong>and</strong> fire detection systems<br />
• Lube oil system<br />
• Static exciter<br />
• Control system with control options for combined cycle application, e.g. temperature matching,<br />
external speed set point <strong>and</strong> high steam temperature protection<br />
• Vibration <strong>and</strong> temperature monitoring<br />
• Batteries <strong>and</strong> battery charger<br />
• TCA cooler to cool a main compressor bleed stream of compressed air to be used for power<br />
turbine blade cooling. Waste heat from this cooler is used to heat incoming fuel gas<br />
A1 Combustion Turbine Balance of <strong>Plan</strong>t<br />
Each combustion turbine balance of plant includes:<br />
• Combustion turbine foundation<br />
• Step <strong>up</strong> transformers, 13.8 to 345 kV (one for each CT)<br />
• Auxiliary transformers (one for each CT)<br />
• Generator breakers (one for each CT)<br />
• High side gas insulated breakers<br />
• Generator hydrogen <strong>and</strong> CO system<br />
2<br />
• Associated electrical connections, metering <strong>and</strong> protection<br />
• Oily water collection system<br />
• Wash water drain tank <strong>and</strong> pumps<br />
• Lube oil collection system<br />
• CTG equipment closed cycle cooling water system including a 14 cell fin-fan cooler<br />
B1 Existing Steam Turbine Upgrades<br />
The existing steam turbine generator <strong>and</strong> associated auxiliary equipment will be reused. Normal<br />
maintenance <strong>and</strong> overhaul cost for the steam turbine <strong>and</strong> other existing equipment is assumed to be part of<br />
the plants maintenance budget. The following steam turbine modifications are included in the repowering<br />
project cost estimate:<br />
• Replace HP <strong>and</strong> IP turbine blades <strong>and</strong> diaphragms as required to improve performance<br />
• Generator rewind<br />
• New Mark VI steam turbine controls<br />
• New static excitation system<br />
March 30, 2009 244