18.03.2021 Views

Insight 2017

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

The Queen’s College Library<br />

<strong>Insight</strong><br />

Issue 7, Michaelmas Term <strong>2017</strong><br />

New Library Special Issue:<br />

Introduction from Amanda Saville...p.1<br />

‘Queen’s Before Queen’s’ - John Blair...p.2<br />

‘The New Library Project’ - Paul Renton-<br />

Rose...p.6<br />

‘A (Near) Impossible Building’ - Stuart Cade...p.9<br />

‘Reflections on the New Library Project’ - David<br />

Goddard...p. 13


1<br />

elcome to Issue 7<br />

W of <strong>Insight</strong>. The front<br />

cover of this issue is a<br />

somewhat surreal yet<br />

beautiful image of the roof<br />

light to the New Library<br />

appearing to float between<br />

the terrace and lawn of the<br />

Provost’s Garden. It was<br />

taken in May just as the<br />

garden was being replanted<br />

and shows the<br />

copper beech tree in full<br />

leaf, healthy and happy<br />

after two years of adjacent<br />

construction.<br />

THE QUEEN'S COLLEGE LIBRARY INSIGHT<br />

The cover gives it away;<br />

this year’s issue, is, as<br />

promised, a “new library<br />

special” and contains<br />

articles that range from an<br />

account of the preconstruction<br />

archaeological dig to an<br />

assessment of all the work<br />

that has been carried out<br />

on the library buildings<br />

over the last four years.<br />

The first article is by John<br />

Blair, Fellow in Modern History, Anglo-Saxon archaeologist,<br />

former Fellow Librarian and one of the earliest supporters in<br />

College for an underground extension to the Library. John<br />

describes in detail the archaeological dig that took place in<br />

early 2015 in the Provost’s Garden, just before the<br />

construction work began. The results of the dig have cast new<br />

light on the expansion of Oxford eastwards from the original<br />

Saxon Burgh and John’s article brings it all to life. Next time<br />

you come to the Library, if you would like to see some of the<br />

finds unearthed during the dig you will find a cross section of<br />

excavated material on display in the new exhibition case in the<br />

Lower Library.<br />

The second article is by Paul Renton-Rose, Project Manager<br />

for Beard Construction, main contractor for the new library.<br />

Paul was in charge of all aspects of the new library build on<br />

site. His article reveals some of the many complexities<br />

involved in constructing such a bespoke building in a site in<br />

the centre of Oxford, surrounded by Grade I listed structures<br />

and with extremely difficult access. Some of the images in<br />

Paul’s article have reminded me just how challenging a<br />

building this was to construct. This can easily be forgotten as I<br />

sit under the roof light in our beautiful new library enjoying<br />

the fruits of the hard work of Paul and so many of his<br />

dedicated and specialist colleagues, who brought the<br />

Architects’ vision to reality so ably.<br />

Paul’s article is followed by a piece by Stuart Cade, one of the<br />

founding partners of MICA Architects, the company which<br />

earlier this year evolved from Rick Mather Architects, the firm<br />

Rowan Atkinson CBE unveiling the commemorative plaque to declare the New Library officially open.<br />

who designed the Library. I have known Stuart for eleven<br />

years and it is a delight to both of us that the building on<br />

which we have worked together for so long, has now come so<br />

spectacularly to life. Stuart’s article describes the design<br />

concepts behind the building and highlights the expertise of<br />

many of the consultants who worked on the project to design<br />

what he describes as “a (near) impossible building”. I would<br />

like to record my thanks both to Stuart and his colleague<br />

Mandy Franz, who, as Project Architect, made the “near<br />

impossible” into a reality.<br />

The final article is a retrospective by David Goddard, Clerk of<br />

Works and College Project Manager for the new library who<br />

looks back at the last four years of intensive work on the<br />

library buildings starting with the refurbishment project of<br />

2013-14 and culminating in the recent opening of our new<br />

library by old member Rowan Atkinson CBE.<br />

I am very grateful to all the contributors who willingly wrote<br />

for me, many of whom had already moved on to manage other<br />

building challenges whilst writing their articles. I am<br />

particularly grateful to my colleague, Sarah Arkle, whose first<br />

issue of <strong>Insight</strong> this is, who has done such a brilliant job in<br />

producing this issue.<br />

If you have ideas for future articles or indeed would like to<br />

contribute, please contact me at<br />

amanda.saville@queens.ox.ac.uk<br />

Amanda Saville, Librarian, November <strong>2017</strong>


Michaelmas <strong>2017</strong> 2<br />

Q U E E N ’ S B E F O R E Q U E E N ’ S : T H E<br />

ARCHAEOLOGY OF THE NEW LIBRARY AND<br />

OXFORD’S ‘EASTERN EXTENSION’<br />

John Blair, The Queen’s College<br />

he new underground library extends deep into the gravel<br />

T subsoil, and its creation involved the removal of all<br />

human deposits. An archaeological excavation – the largest<br />

ever conducted in modern times in the eastern part of the<br />

walled city of Oxford – was therefore required. The layout<br />

and development of this area between the late Anglo-Saxon<br />

period and the twelfth century have been almost completely<br />

obscure, so the exercise promised a glimpse into the unknown.<br />

That promise was fulfilled: what was uncovered was in one<br />

way predictable, in another very surprising.<br />

The excavation was carried out during 2015 by Oxford<br />

Archaeology under the direction of Richard Brown, and is<br />

described in a preliminary report. 1 Post-excavation work<br />

remains to be completed for the final publication, and some<br />

conclusions will probably be modified, but meanwhile Mr<br />

Brown and O.A. have kindly allowed me to set their findings<br />

in context for the benefit of members of Queen’s. Everything<br />

said here is, however, subject to revision in the light of the<br />

final conclusions.<br />

It is generally agreed that Oxford began as a rectilinear<br />

earthwork fort defending an important Thames crossing, and<br />

also enclosing the minster of St Frideswide (now the<br />

Cathedral) established there around the year 700. 2 The placename<br />

first appears on pennies of King Alfred, minted at<br />

Ohsnaforda in the 890s, but it remains unclear whether the first<br />

fort was built by Alfred, by his immediate successors, or even<br />

conceivably by one of his predecessors. The basic topography<br />

of the core area and its rectilinear defences, enclosing a main<br />

crossroads centred on Carfax, is reasonably clear.<br />

There has been considerable debate, however, about the<br />

eastern half of the walled area between Radcliffe Square and<br />

the East Gate, including the site of Queen’s. The northwards<br />

kink in the line of the late medieval city wall between Broad<br />

Street and Holywell has long encouraged the hypothesis that<br />

the eastern zone was an extension, probably added in the late<br />

tenth or eleventh century. That idea appeared to be confirmed<br />

by an excavation between the Old Bodleian and the Clarendon<br />

Building in 1899, which found a sharp southwards curve in the<br />

revetment of the Anglo-Saxon bank: it is difficult to<br />

understand this except as the north-east corner of the primary<br />

fort. 3<br />

On the other hand, a trench against the inner face of the New<br />

College section of the wall in 1993 disclosed an earlier clay<br />

bank, seemingly identical to the primary northern bank that<br />

had been recognised in 1985 behind St Michael’s Street. 4 That<br />

encouraged some re-thinking: could the whole circuit have<br />

been of a single, Alfredian, build after all? 5 In any case, there<br />

were already enough finds and small-scale observations from<br />

the eastern zone to show that late Anglo-Saxon settlement of<br />

some kind existed there, whether intramural or suburban. 6<br />

There were also the more recent excavations within Queen’s<br />

itself, in the Back Quad (2008) and the Nun’s Garden (2010),<br />

each of which had encountered fragmentary late Anglo-Saxon<br />

pits, including in one case a cut halfpenny of Æthelred II<br />

circulating during 997-1003. 7 It was therefore anticipated that<br />

at least some activity from around the year 1000 would be<br />

identified in the Provost’s Garden.<br />

That proved indeed to be the case (Figure 1). The earliest<br />

occupation (Phase 1) comprised three cellars, measuring<br />

respectively 4 x 2.5 m., 2.5 x 2.5 m., and 1.75 x 1 m. To their<br />

south-west were remains of a metalled lane surfaced with<br />

pebbles, marked by wheel-ruts, and a row of post-holes<br />

suggesting some frontage structure between the largest cellar<br />

and the lane. South and west of the cellars were scattered<br />

rubbish-pits, as usual on such sites. Pottery from the pits and<br />

cellars indicated a late Anglo-Saxon date (though the fill of one<br />

of the cellars contained two sherds of Kennet Valley Ware,<br />

introduced c.1050), and there was another Æthelred II coin, of<br />

c.1009-16.<br />

Subsequent developments (Phase 2a), up to the foundation of<br />

Queen’s in 1342, are at present only dated very broadly. A<br />

system of rectilinear boundary ditches cut some of the Phase 1<br />

features, but is also broadly compatible with the settlement<br />

layout of that date, and may have respected the lane. The<br />

abandonment of the lane is indicated by a rubbish-pit cut<br />

through its surface, containing pottery in the range c.1075-<br />

1150. There are apparently no grounds for thinking that the<br />

topographical configuration represented by the cellars and lane<br />

survived beyond the early to mid twelfth century.<br />

Phase 1 is exactly what we would expect of urban or suburban<br />

activity in the range c.980-1050. Cellars (probably contained<br />

within ground-level timber buildings) are the classic buildingform<br />

found in such contexts. Those from the Provost’s<br />

Garden are at the smaller end of the Oxford range, 8<br />

resembling more closely some examples from proto-towns and<br />

monastic centres like Stafford, Northampton and – more<br />

locally – Bampton. 9 To that extent this looks a less `urban’<br />

environment than, for instance, the frontages of Cornmarket<br />

or Queen Street.<br />

The impression that the late Anglo-Saxon activity was<br />

suburban rather than urban in character is strongly reinforced<br />

by the unexpected alignment of the features. Although the lane<br />

survived in a fragmentary state, it unmistakably ran from westnorth-west<br />

to east-south-east; the wheel-ruts in its surface<br />

show that it was a through-route rather than a purely local<br />

feature. The cellars, and the line of stakes on the frontage,<br />

were broadly aligned on the lane. While one should be cautious<br />

about extrapolating from small observations, it is hard to resist<br />

the obvious conclusion that this lane ran from somewhere in<br />

the region of the Clarendon Building and Hertford College<br />

towards the later medieval East Gate on the High Street<br />

(Figure 2).<br />

This looks like a non-urban settlement layout, which at some<br />

stage was scrapped and overlain by the conventionally<br />

rectilinear topography of the eastern walled area. It does not<br />

tell us when the wall around that area was built, but it does


3<br />

THE QUEEN'S COLLEGE LIBRARY INSIGHT<br />

Figure 1<br />

show that the internal layout did not come to resemble the<br />

rectilinearity of the late Anglo-Saxon core to the west until<br />

after the Norman Conquest. The discovery therefore casts<br />

serious doubt on the hypothesis that the eastern half of the city<br />

was part of the original Alfredian plan, and (setting aside for<br />

the moment the problem of the New College bank) it supports<br />

the earlier view that this was a relatively late extension,<br />

enclosing organic suburban settlement.<br />

The newly-found lane should be seen in relation to Catte Street<br />

(the eastern side of Radcliffe Square), where pre-Conquest<br />

road-metalling of similar appearance was observed in 1980. 10<br />

Together, these lanes now look like a ‘bypass system’, to<br />

channel north-to-south and north-to-east flows of traffic from<br />

the Banbury road down Parks Road, and then around the<br />

outside of the Alfred-period fortress. Whereas Catte Street<br />

presumably led on southwards to a Thames ford, the lane now<br />

discovered under Queen’s would have passed the north-east<br />

corner of the fort and then made for Magdalen Bridge.<br />

When the eastern defences were built (or remodelled as a<br />

continuous circuit), the two lanes would have assumed a new<br />

character as components of the intramural street-plan. Their<br />

northern ends diverged just inside a new gate – Smith Gate –<br />

giving access to the city from Parks Road. Whereas Catte<br />

Street lost its function as a through-route (it was cut short at<br />

Merton Street and then the city wall to the south), the lane<br />

across the Queen’s site would have remained the most direct<br />

route from Smith Gate to the new East Gate. In other words,<br />

it was an earlier incarnation of Queen’s Lane: the present<br />

configuration of sharp-angled bends – so familiar (and at<br />

times so tiresome) to all members of the College – must have<br />

been planned to accommodate blocks of tenements in broad<br />

conformity with the rectilinear layout of the original nucleus<br />

and the extended walls.<br />

When did that happen? Queen’s Lane had assumed its present<br />

configuration by c.1240, when it was known as ‘Thorald the<br />

Tawyer’s Lane’. 11 The replanning must, however, have


Michaelmas <strong>2017</strong> 4<br />

occurred by c.1210 at the latest, since some individual<br />

tenements in the blocks facing the High Street (under the main<br />

front of Queen’s and the shops east of the Lane entrance), 12<br />

and the block facing Catte Street (under Hertford College),<br />

have sets of deeds starting around or just after that date: 13 the<br />

lane must have been diverted before those tenements were laid<br />

out. Oxford has a great wealth of medieval deeds, but<br />

documentation at the level of individual tenements is<br />

essentially post-1200: the fact that the documented properties<br />

were evidently well-established when their deeds start pushes<br />

the replanning episode back into the twelfth century. That is<br />

of course consistent with the excavated evidence that the<br />

original lane was disused, and being cut by pits, no later than<br />

c.1150.<br />

There is a likely connection, though not a necessary one,<br />

between the building of the eastern walls (in their developed<br />

form of a continuous circuit) and the tenemental replanning. It<br />

is in theory quite possible that after the walls were built, the<br />

diagonal lane inside them – now entered at its two ends from<br />

Smith Gate and East Gate – remained in use for decades or<br />

even generations. Alternatively, the walls and the tenementseries<br />

that they enclosed could have been created in a single,<br />

comprehensive town planning exercise. It is normally assumed<br />

that the walls existed at least by the 1080s, but even that is far<br />

from clear. Both in Domesday Book, and in the next<br />

document that mentions it (a charter of 1153-4), the<br />

topographical status of St Peter’s-in-the-East church is left<br />

frustratingly ambiguous : ‘St Peter’s church of Oxford’, rather<br />

than ‘in Oxford’. 14 Even the charter’s description of it as ‘near<br />

the East Gate’ (ecclesia Sancti Petri de Oxenefordia que sita est iuxta<br />

portam de est) is not conclusive, since that might refer either to<br />

the second East Gate (150 metres south-eastwards) or to the<br />

putative original one (250 metres south-westwards).<br />

A different approach to this problem concerns the so-called<br />

‘mural mansions’: the special group of tenements that,<br />

according to Domesday Book, ‘were free in King Edward [the<br />

Confessor]’s time of all customary obligations except armyservice<br />

and repairing the wall’. 15 While the pre-Conquest<br />

origins of the system are thus certain, Hilary Turner’s<br />

topographical analysis in 1990 showed that the ‘mural<br />

mansions’ capable of being located on the ground<br />

concentrated heavily in the north-east part of the developed<br />

city, east of Radcliffe Square and north of High Street. 16 That<br />

cannot reflect late Anglo-Saxon arrangements in any simple or<br />

Figure 2


5<br />

THE QUEEN'S COLLEGE LIBRARY INSIGHT<br />

direct way, since several of the tenements whose proprietors<br />

were charged with wall-duty in a writ of 1227 must have taken<br />

shape after Queen’s Lane assumed its present dog-legged form.<br />

A more straightforward explanation would be that these<br />

tenements do not relate to the Anglo-Saxon system of wallmaintenance<br />

at all, but rather to a twelfth-century extension of<br />

it. On that view, one might envisage an agreement whereby the<br />

Crown allowed the extended walls to be built, on condition<br />

that the burden of maintaining them was apportioned between<br />

the tenants of the new house-plots that were thus enclosed and<br />

protected.<br />

Perhaps, then, there is something to be said for a new<br />

hypothesis: that the eastern walled circuit in its developed<br />

form, and the planned tenements inside it, were laid out<br />

together at a date not long before the abandonment of the<br />

settlement on the Provost’s Garden site by the 1150s. In Henry<br />

I’s reign Oxford was already recovering from its post-Conquest<br />

depression, and growing fast. 17 Another obvious possibility is<br />

that the Anarchy years of 1139-53 (which despite the political<br />

chaos were an era of strong economic growth. 18 ) created a<br />

compelling incentive to defend the valuable church of St Peter,<br />

and the now densely-settled zone between it and the city wall.<br />

It would have helped that the two powerful magnates with a<br />

direct interest in this part of eastern Oxford and Holywell<br />

manor were Angevin supporters, well-placed at court: Henry<br />

d’Oilly, the heir of Robert d’Oilly who had held St Peter’s<br />

church and Holywell in 1086, and Henry of Oxford, Matilda’s<br />

local henchman, who built a massive Romanesque house in the<br />

west of the city. 19 The 1153-4 charter mentioned above is an<br />

(ultimately ineffectual) grant by Henry d’Oilly to Oseney Abbey<br />

of St Peter’s church, which at that point was firmly in the<br />

clutches of John of Oxford, Henry of Oxford’s son and future<br />

bishop of Norwich. 20 John may well have been responsible for<br />

the sumptuous Romanesque rebuilding of the church that still<br />

largely survives (now St Edmund Hall library), and he certainly<br />

enjoyed a large and apparently complex residence west of St<br />

Peter’s churchyard, occupying what is now the eastern half of<br />

the Back Quad at Queen’s. 21 If the extension of the walls and<br />

the replanning of the area inside them happened in, say, the<br />

1140s, it is almost certain that the two Henrys were involved in<br />

one way or another.<br />

At this point we need to take a step back, and consider the<br />

status and fortunes of St Peter’s church: it may have been the<br />

single most important influence on the urban developments to<br />

its west. Although the early ecclesiastical heart of Oxford was<br />

certainly St Frideswide’s, there is persuasive circumstantial<br />

evidence that St Peter’s-in-the-East was also an Anglo-Saxon<br />

monastic complex, possibly one of a series established on the<br />

peripheries of Mercian centres by King Alfred’s daughter<br />

Æthelflaed. 22 During the tenth to twelfth centuries, it was often<br />

the fate of formerly independent minsters to be annexed as<br />

essentially the private property of secular and ecclesiastical<br />

magnates. Domesday Book (which unfortunately says nothing<br />

here about pre-Conquest arrangements) makes it clear that this<br />

had happened to St Peter’s by 1086: both the church and its<br />

manor of Holywell were controlled by the Norman baron<br />

Robert d’Oilly. 23 Its later twelfth-century status, as the personal<br />

church and residence of a great curial ecclesiastic, looks equally<br />

typical. The absence of early sources should not disguise from<br />

us the former wealth and status of this church, which would<br />

certainly have been surrounded by a substantial precinct and<br />

associated buildings.<br />

We have no evidence for what that complex was like (the<br />

broken circle shown on Figure 2 is purely schematic), but it<br />

could have included a significant part of what would become<br />

the walled extension north of High Street. There are hints of it<br />

in thirteenth-century deeds describing the tenements on the<br />

easternmost part of the Queen’s site: Bishop John’s house<br />

comprising a ‘messuage with houses, orchard(?) and the whole<br />

courtyard … in the churchyard of St Peter’s’ (mesuagium cum<br />

domibus et uirgulto et tota curia … in atrio Beati Petri), and the<br />

tenement to its south ‘in St Peter’s churchyard’. 24 An odd<br />

feature of these descriptions is that they ignore the intervening<br />

Queen’s Lane, which certainly existed when they were written.<br />

The explanation is presumably that they were carried over<br />

from earlier documentation, dating from a time before the<br />

replanning, when St Peter’s and its peripheral structures<br />

dominated the local landscape.<br />

If we take another step backwards, that perspective helps to<br />

set the early eleventh-century occupation in context. If the<br />

Queen’s site was suburban in the sense that it was outside the<br />

eastern rampart of the city, it was also suburban in the sense<br />

that it developed on the periphery of an Anglo-Saxon minster:<br />

many eleventh-century towns began as what an Alfred-period<br />

translator (rendering Bede’s phrase urbana loca into Old<br />

English) called ‘minster-places’. 25 This was therefore a place of<br />

a rather special and unusual kind, arising from the original<br />

placement of St Peter’s some way outside the fort: a suburb, as<br />

it were, twice over. And indeed it offers a classic illustration of<br />

the kind of small-scale cultivation for urban consumption that<br />

underlies so many places of this kind. The Domesday account<br />

of Holywell manor in 1086 mentions 23 men ‘having little<br />

gardens’ (hortulos habentes). 26 Smallholders of this kind, who may<br />

have combined obligations to their lords with marketgardening<br />

and craft production, were very common of the<br />

edges of eleventh-century towns. 27 Maybe some of their wares<br />

were sold from the roadside buildings now identified under the<br />

Provost’s Garden.<br />

Having said all that, there remains the problem – a big and<br />

important one – of the New College bank. The feature<br />

observed in 1993 is scarcely diagnostic physically: a city<br />

defence constructed in the twelfth century would probably still<br />

have been earthen, 28 and it is not obvious that the bank<br />

material of a rampart built in, say, 1150 would look different<br />

from one built in, say, 1000. However, Optically Stimulated<br />

Luminescence (OSL) results just released point to the startling<br />

conclusion that this feature, or parts of it, was constructed in<br />

the eighth century. 29 This remarkable new evidence (for<br />

immediate access to which I am deeply grateful to Ben Ford of<br />

Oxford Archaeology) raises implications that cannot be<br />

considered properly here, let alone answered. Possibly the<br />

eighth-century earthwork was a linear bank – or even a<br />

monastic enclosure around St Peter’s – that survived as a<br />

relict landscape feature to be incorporated into the twelfthcentury<br />

defences. It is hard to see it as an integral part of the


Michaelmas <strong>2017</strong> 6<br />

Alfred-period fort; rather, that must have been built<br />

immediately west of some structure surviving from the period<br />

of Mercian control. At all events, the suburban character of<br />

the occupation around the year 1000 can scarcely be<br />

reconciled with the earthwork being a coherent barrier<br />

between town and countryside at that stage. For the moment<br />

this question must remain unresolved, but debate will certainly<br />

continue.<br />

The Anglo-Saxon landscape of the Queen’s site is very deeply<br />

buried: under the twelfth-century urban replanning, under the<br />

late medieval College buildings, and finally under their<br />

Baroque successors. There is no possibility of exploring it<br />

except by deep excavation, which is why it has remained so<br />

mysterious hitherto. Over the past decade, Queen’s has had<br />

the confidence and courage to augment its facilities with a new<br />

kitchen, lecture-room and library. That has been at the cost of<br />

considerable disruption, now happily behind us. An<br />

unexpected bonus along the way has been a significant<br />

contribution to understanding the origins and early growth of<br />

Oxford.<br />

Notes and references<br />

1. R. Brown, Provost’s Garden, The Queen’s College, Oxford: Post-<br />

Excavation Assessment and Updated Project Design (unpublished client<br />

report, Oxford Archaeology, September 2016).<br />

2. J. Blair, Anglo-Saxon Oxfordshire (Stroud, 1994), 52-4, 61-3, 87-92,<br />

146-52; A. Dodd (ed.), Oxford Before the University (Oxford, 2003).<br />

3. Julian Munby in Dodd (ed.), Oxford Before the University, 172-83.<br />

4. Paul Booth in Dodd (ed.), Oxford Before the University, 183-6.<br />

5. Julian Munby in Dodd (ed.), Oxford Before the University, 24-5,<br />

concluding that `the proposed eastern extension remains really<br />

quite difficult to reconcile with the archaeological evidence’.<br />

6. J. Blair, Anglo-Saxon Oxfordshire, 161.<br />

7. A. Norton and J. Mumford, `Anglo-Saxon Pits and a Medieval<br />

Kitchen at The Queen’s College, Oxford’, Oxoniensia, 75 (2010),<br />

165-217, at pp.177-9; S. Teague, A. Norton and A. Dodd, `Late<br />

Saxon, Medieval and Post-Medieval Archaeology at the Nun’s<br />

Garden, The Queen’s College, Oxford’, Oxoniensia, 80 (2015), 143<br />

-85, at pp.147-8.<br />

8. J. Blair, Anglo-Saxon Oxfordshire, 162-4; Dodd, Oxford Before the<br />

University, 35-41.<br />

9. J. Blair, Building Anglo-Saxon England (Princeton, 2018), Fig. 131.<br />

10. Dodd, Oxford Before the University, 260, 397.<br />

11. H.E. Salter, Survey of Oxford, I (Oxford Historical Soc. n.s.14,<br />

1960), 160 (tenement NE 230); Cartulary of Oseney Abbey, ed. H.E.<br />

Salter, I (Oxford Historical Soc. 89, 1929), 269-71<br />

12. Salter, Survey, I, 135-47 (tenements NE 173-95, especially 175,<br />

177, 183, 190 with starting deeds no later than 1210).<br />

13. Salter, Survey, I, 92-8 (tenements NE 131-6, especially 131 with a<br />

starting deed of c.1220).<br />

14. Great Domesday Book fo. 158v; H.E. Salter, Facsimiles of Early<br />

Charters in Oxford Muniment Rooms (Oxford, 1929), No.73.<br />

15. Great Domesday Book fo.154.<br />

16. H.L. Turner, `The Mural Mansions of Oxford: Attempted<br />

Identifications’, Oxoniensia, 55 (1990), 73-9; cf. O. Creighton and<br />

R. Higham, Medieval Town Walls (Stroud, 2005), 39-40, 81, etc.<br />

17. Blair, Anglo-Saxon Oxfordshire, 177.<br />

18. Here I cannot resist recalling that my predecessor, John<br />

Prestwich, made this point very powerfully in a lecture that I<br />

heard as an undergraduate, in about 1974. I hope he would have<br />

relished the thought that urban replanning from the Anarchy<br />

period lies directly under Queen’s.<br />

19. J. Blair, `Frewin Hall, Oxford; a Norman Mansion and a<br />

Monastic College’, Oxoniensia, 43 (1978), 48-99, at pp.49-64.<br />

20. Salter, Facsimiles of Early Charters, No. 73.<br />

21. Salter, Survey, I, 152-3 (tenement NE 208); Cartulary of Oseney, I,<br />

276-9.<br />

22. Blair, Anglo-Saxon Oxfordshire, 112-13.<br />

23. Great Domesday Book fo. 158v.<br />

24. Salter, Survey, I, 152-3 (tenements NE 208-9); Cartulary of Oseney,<br />

I, 276; Cartulary of the Hospital of St John the Baptist, ed. H.E. Salter,<br />

I (Oxford Hist. Soc. 66, 1914), 344.<br />

25. J. Blair, The Church in Anglo-Saxon Society (Oxford, 2005), 330-41.<br />

26. Great Domesday Book fo.158v.<br />

27. C. Dyer ,`Towns and Cottages in Eleventh-Century England’, in<br />

H. Mayr-Harting and R.I. Moore (eds.), Studies in Medieval History<br />

Presented to R.H.C. Davis (London, 1985), 91-106; Blair, Church in<br />

Anglo-Saxon Society, 340-1.<br />

28. Cf. Creighton and Higham, Medieval Town Walls, 178-84.<br />

29. Results communicated by Jean-Luc Schwenninger in July <strong>2017</strong>.<br />

Thanks also to David Radford for his help with this and other<br />

sites.<br />

John Blair is a Fellow in History here at The Queen’s College and<br />

Professor of Medieval History and Archaeology. He was appointed to his<br />

present position at Queen’s in 1981. Outside his academic duties, he<br />

maintains a long-standing involvement in practical archaeology, and in the<br />

worlds of building and landscape conservation.<br />

The New Library Project<br />

Paul Renton-Rose, Beard Construction<br />

For Amanda<br />

une 2015 saw the start of the work on site for the new<br />

J<br />

library project, it had taken years of preparations by the<br />

various architects & design teams and now, with the<br />

archaeology complete, it was time to start the excavation. This<br />

transformed the Provost’s Garden into a construction site and<br />

started the engineering process of the New Library. The<br />

design team had set the bar very high with a wall to wall<br />

excavation that had to be executed with great care & precision<br />

to fit the library into the garden area without disturbing the<br />

surrounding 1690’s library building, listed walls, not forgetting<br />

the reportedly 200-year-old wisteria and copper beech tree.<br />

Protection to the west side of the library facade was formed<br />

with a 5.5-metre-high screen made from steel supports, ply<br />

and Monoflex sheeting. The protection of the historic wall on<br />

the south elevation was completed and agreed with all parties<br />

so piling could commence.<br />

A temporary support for the 38-tonne piling machine required<br />

a designed reinforced piling mat of approximately 1000 tonne<br />

of stone, this was imported, constructed and plate tested<br />

before we allowed the piling to proceed. A strong and stable<br />

platform is essential to keeping the rig flat on the ground and<br />

not allow excessive movement in the mast.<br />

Supporting the ground and historic parts of the Grade I listed


7<br />

THE QUEEN'S COLLEGE LIBRARY INSIGHT<br />

building and associated<br />

Grade II listed walls,<br />

took great skill and<br />

ingenuity on behalf of<br />

the construction team.<br />

The designed secant<br />

piling was located<br />

around the excavation<br />

up against the lines of<br />

the existing structures,<br />

and in one case within<br />

100mm of the library<br />

facade.<br />

Weekly monitoring of<br />

Piling machine<br />

t h e s u r r o u n d i n g<br />

buildings made sure that the ground support measures that had<br />

been put in place were working and could be constantly<br />

adjusted if required.<br />

Monitoring concrete before and after casting<br />

Whilst the New Library piling and excavation were being<br />

executed, the dismantling of the joinery in the Lower Library<br />

took place: labelling, scheduling, photographing all the parts,<br />

careful removal and transferring off site for 15 months into<br />

storage for later inclusion. Trying to keep a low profile in the<br />

back of the College garden with the only access via Queens &<br />

New College Lane was not easy. Trying to ship out soil;<br />

approximately 8861 tonnes of excavated materials and at the<br />

same time bring in 3000 tonnes of concrete and new materials<br />

through the tight<br />

restrictions of the<br />

Lane, was challenging<br />

to say the least. We<br />

restricted the sizes<br />

and width of the<br />

delivery vehicles and<br />

in some cases the<br />

m a t erials b eing<br />

delivered. As a result,<br />

daily monitoring and<br />

cleaning of the lane<br />

by our staff, and<br />

weekly cleaning with<br />

the road sweeper, was<br />

necessary.<br />

The pump used during the build to place concrete<br />

Contractors worked hard over the 18 months to keep<br />

members of the public and tourists safe whilst escorting the<br />

delivery trucks and materials safely to the site, sometimes, with<br />

agreement of all parties and Oxford City Council, in the early<br />

hours of the mornings to reduce the risk to the public and<br />

students.<br />

After extensive archaeology for approximately 3 months by<br />

Oxford Archaeology the site was passed over to us to progress<br />

with the works, during the bulk excavation one of the ground<br />

work team spotted and unearthed an earwax and tooth pick<br />

which was returned to the College for display (approximate<br />

length 10cm).<br />

The finds liaison officer dated this to 13th-15th (medieval)<br />

which would correspond to the early arrangement for The<br />

Queens College (before the wholesale rebuilding of the<br />

17th/18th) when this area seems likely to have been used as a<br />

quarry for building materials; pits for toilets; and the dumping<br />

of rubbish. The artefact, an expensive item for the time, was a<br />

personal grooming item likely to have been accidentally<br />

dropped down the toilet by a student or scholar.<br />

Toothpick/earwax implement found during the excavation<br />

With the type of reinforced concrete structure proposed, most<br />

buildings are built to a B.S. or E.N. (British or European<br />

standards) for location and verticality, in all instances the<br />

structures have exceeded this quality standard allowing the<br />

design team certainty in their design.<br />

Every reinforcement bar was engineered, designed, drawn,<br />

scheduled, delivered to site, cut, bent and then positioned by<br />

hand. Each was measured to fit its correct location to carry out<br />

the job it is required to do. 138 tonnes of steel reinforcement<br />

has been placed by hand (as shown in the photo below) by<br />

experienced skilled workers.<br />

Escorted deliveries along Queen’s lane to the<br />

construction site<br />

Our great band of<br />

banksmen from Curtis


Michaelmas <strong>2017</strong> 8<br />

Interesting Statistics for the Project<br />

299 concrete piles were used to support the ground &<br />

structure of the new building. They also anchor the library<br />

in place; pile length of 3000 metres (3km) if positioned end<br />

to end.<br />

There are 10 ground source piles which extend 50 metres<br />

below the building basement level.<br />

8861 tonnes of excavated soil was removed.<br />

2000 cubic metres of concrete was delivered and pumped<br />

into the ground (approximately 5000 tonnes).<br />

138 tonnes of reinforcement strengthens the concrete<br />

which supports the library structure.<br />

94,338.5 hours have been employed on site by the various<br />

trades (this excludes the production time of offsite<br />

manufacture and work by office or design staff).<br />

9km of electrical wiring was used.<br />

60 separate contractors have had an input to the works on<br />

site, many of them have a specialist knowledge for a<br />

particular part of the build.<br />

737 site personnel & visitors have been inducted and<br />

managed on site.<br />

The location of the site mid way along Queens Lane required a<br />

smaller than normal concrete truck which could deliver the<br />

concrete directly to the site along the very narrow road and<br />

around the tight corners in the lane. Our happy band of lads<br />

on the logistics team escorted the concrete trucks to and from<br />

the site daily ensuring the safety of the public and monitoring<br />

the vehicles passing safely through the historic lane. This<br />

amounted to over 2000 vehicle movements.<br />

Small concrete lorry escorted to and from the site<br />

Creating the ground-level main entrance to the New Library<br />

brought many challenges: working inside the historic Grade I<br />

listed building in a working library; making sure the vital<br />

services of the library were not disturbed, and, ensuring all of<br />

the designed construction fitted into the space required; lift,<br />

staircase and final finishes. It was one area of the build that<br />

had all the makings of a big problem, and could have all gone<br />

terribly wrong. However, it had been planned and designed<br />

well, the design fitted like a glove, millimetre precision in fact,<br />

no second chances.<br />

Positioning the 7-tonne piling rig into the building through the<br />

listed structure onto the timber floors was a concern to<br />

Contractors Design Services, our temporary works engineer,<br />

but with an engineered solution to strengthen the floors we<br />

quickly overcame the issue, and the piling rig operated easily to<br />

form the temporary piles and the permanent piles. The<br />

entrance in the Lower Library was hand excavated (about 450<br />

cubic metres) around the piles and support structure, with the<br />

new structure in place the temporary works were removed and<br />

temporary piles disposed of. Great care was taken throughout<br />

not to create too much disruption or disturbance to the<br />

College by the groundwork team.<br />

The Lower Library panelling was removed in order to install the new<br />

sliding glass door<br />

Reinstatement of the lower<br />

library panelling and<br />

bookcases, which arrived<br />

back from the Botley Road<br />

storage depot piece by<br />

piece, was carried out<br />

lovingly by the Cliveden<br />

conservation team of<br />

carpenters. The Lower<br />

Library panelling was<br />

refurbished, refinished and<br />

polished to match the<br />

existing panelling. Finally,<br />

the new glass sliding door<br />

was installed behind the<br />

panelling.<br />

The design for this project<br />

aimed to limit the visual Work by Cliveden Conservation to<br />

aspect of a complex reinstall the Lower Library Panelling<br />

mechanical and electrical design by concealing as much of the<br />

ventilation and electrical systems within the structure of the<br />

building. Under the raised flooring is the supply air ducting<br />

and the majority of the electrical services which are supported<br />

on hand crafted cable trays and baskets.<br />

What lies beneath: example of the cable tray and basket used underneath<br />

the flooring to conceal complex systems used in the build


9<br />

THE QUEEN'S COLLEGE LIBRARY INSIGHT<br />

The new library has 10<br />

bore holes for the<br />

ground source heat<br />

pump (GSHP) which<br />

extends down under<br />

the building by 50<br />

metres. It uses the<br />

stable underground<br />

temperature of the<br />

earth to heat and cool<br />

the building. They<br />

Ground source pipework<br />

achieve this by connecting the building and the earth via a<br />

network of underground pipes. These pipes use water to<br />

transfer heat from the earth to the building heat pumps to heat<br />

it and from the building to the earth to cool it.<br />

Ground source heat pumps are a lot more energy efficient and<br />

cost effective than traditional heating systems found in most<br />

homes and buildings. This is because although they only need a<br />

small amount of electricity to run, heat pump systems don’t<br />

burn any kind of fuel on site to produce their heat and use only<br />

the natural temperature of the earth as an energy generating<br />

method. This offers significant reductions in energy bills and<br />

CO2.<br />

Although not visible to the students, the plant room is very<br />

compact; hiding most of the mechanical & electrical services<br />

required to run the complex ventilation and power systems for<br />

the building. Having been very carefully designed and<br />

engineered by the design team the professional team of skilled<br />

craftsmen had to ensure all items fitted into their correct spaces<br />

and the systems all worked together.<br />

both men & women, who have put their heart and soul into<br />

their work every day for the last 20 months ensuring the<br />

project is finished to the highest quality which you can see<br />

today – it has been more than just another job; real people<br />

make things happen.<br />

I would like to list all the men and women on site who played<br />

their part in making this scheme a success but the list would be<br />

very long; 60 contractors have had an input to the works on<br />

site and some of them have had a very specialist input.<br />

There have been lighter moments in the project, New College<br />

Lane was closed for a week during the filming of ‘The<br />

Mummy’ <strong>2017</strong> (Tom Cruise). Careful planning on site and<br />

good liaison with the film location crew meant this did not<br />

stop the works or prevent materials reaching the site.<br />

Images from the set of The Mummy in New College Lane<br />

All projects rely on a team effort which, when working<br />

correctly, provides for a better product. I believe we have had<br />

a brilliant team of people working on the project, both on site<br />

& off site supporting the various functions of the build<br />

process. I would like to thank everyone involved for a job well<br />

done.<br />

I trust the College and students will value and enjoy the space<br />

created for many years to come.<br />

Paul Renton-Rose is a Project Manager for Beard Construction. His job<br />

role is to manage the construction process and liaise with clients,<br />

stakeholders, suppliers and to ensure Beard have the resources in place to<br />

complete the project safely and to a good standard. He says of his career,<br />

after 44 years in industry “I still find construction amazing… how did<br />

they build those pyramids?”<br />

Pipework in the Plant Room<br />

The safety systems installed are ready to be used should the<br />

need arise; these include an aspirating fire detection system,<br />

water misting fire suppression system, gas suppression to the<br />

Historic Collections Archive Store and plant room, emergency<br />

lighting and battery backup.<br />

This plant room has been the most compact and complex<br />

system I have been involved with, as most of the services are<br />

inter-linked and connect to the internet, they are also linked<br />

and monitored by the College Building Management System<br />

(CBMS).<br />

People make buildings, not machines. It is easy to forget about<br />

the many talented, professional, skilled workers and craftsmen,<br />

“A Near Impossible building” -<br />

designing and building the new<br />

library at Queen’s College<br />

Stuart Cade, Rick Mather Architects and MICA<br />

Prologue<br />

he team at Rick Mather Architects (RMA) are delighted<br />

T to see the opening of the New Library, which was<br />

completed earlier this year in time for a busy Trinity Term. As<br />

we often find, the transition from building site to occupied<br />

building has been rapid and it is great to see the new spaces<br />

immediately popular with the hardworking students of<br />

Queen’s.


Michaelmas <strong>2017</strong> 10<br />

We last wrote for <strong>Insight</strong> in 2015 at the outset of the<br />

archaeological and enabling works prior to the<br />

commencement of the main building contract. The subsequent<br />

two years have seen the completion of this preliminary work,<br />

the completion of the new building and, lastly, the reworking<br />

of the existing Lower Library. At time of writing the remainder<br />

of the collections were being moved into the new spaces and<br />

the entire build is now fully operational.<br />

Looking back, RMA commenced work on a scheme for The<br />

Queen’s College Library project in 2006 following a two-stage<br />

design competition. Our work has included detailed designs<br />

f o r b o t h t h e<br />

refurbishment of the<br />

Upper and Lower<br />

Library (completed in<br />

2013); designs for the<br />

large subterranean<br />

extension that is the<br />

New Library and<br />

alterations to the<br />

Lower Library. The<br />

latter has allowed us to<br />

create a generous new<br />

entrance space, and<br />

install a bespoke lift,<br />

which connects the An early design concept montage<br />

new and old buildings.<br />

In the 40-year history of Rick Mather Architects, the project,<br />

one of the last that Rick worked on, is one of our most<br />

significant. For the office it is significant in terms of the<br />

challenge posed by the site: its rich and ancient history; the<br />

precious medieval walls; the Grade 1 listed Library it adjoins<br />

and the magnificent buildings that it extends.<br />

The project is also significant in terms of what it achieves;<br />

extending a landlocked Library where all possible contiguous<br />

(and otherwise) extensions had been considered and found<br />

unfeasible. Furthermore, realizing a scheme that works on<br />

paper is a further challenge in practice. Given the logistical,<br />

planning, archaeological, heritage and physical parameters the<br />

large team feel that the project has built a (near) impossible<br />

building.<br />

The design<br />

The new building and its connection to the existing 1692<br />

Library is a bespoke building in all regards.<br />

The construction has employed 21st Century technologies<br />

allied with traditional trades and crafts to create a crisp and<br />

simple contemporary design and the conservation of historic<br />

spaces; equally marrying large-format, frameless glass with rich<br />

tailor-made oak carpentry.<br />

The designs include a new ground floor entrance; a reworked<br />

Lower Library and a new 8000sq/ft. below-ground extension<br />

containing vital new facilities. The Library extension contains<br />

extensive storage and plant facilities in the western half and a<br />

new reading room and office in the eastern half where all<br />

spaces are bathed in natural light. The effective use of every<br />

millimetre was carefully considered and the building was<br />

planned to maximize use of all walls and corners. In total the<br />

design creates 18 new distinct ‘spaces’ for the Library and<br />

associated Archive. In summary, the project has provided:<br />

A new Reading Room<br />

The reading room is the major new addition to the library. The<br />

r o o m<br />

provides a<br />

light and open<br />

space for 36<br />

users. It is top<br />

lit by a large<br />

new roof<br />

light, which<br />

emits natural<br />

light into the<br />

new building<br />

w h i l s t<br />

a f f o r d i n g<br />

The new reading room<br />

views to the west elevation of the existing Library. Space is<br />

maximized with shelving fitted against all walls. The Reading<br />

Room also gives access to two extensive areas of open book<br />

storage. Firstly, the open shelves; these flank the Reading<br />

Room and entrance and house half of the main circulating<br />

collection. They are configured to guide visitors through the<br />

new spaces; the shelves tapering to open the vista to the<br />

Reading Room. Secondly, and adjoining the Reading Room on<br />

the north and east side, are two linear spaces of roller racking<br />

to maximize storage and house the library’s reserve collections.<br />

Historic Collections and Archive Store<br />

Deep within<br />

t h e n e w<br />

building is the<br />

H i s t o r i c<br />

C o l l e c t i o n s<br />

and Archive<br />

Store, which<br />

provides space<br />

f o r t h e<br />

c o l l e g e ’ s<br />

s i g n i f i c a n t<br />

a n t i q u a r i a n<br />

collection in a<br />

secure and<br />

temperature<br />

c o n t r o l l e d<br />

environment.<br />

The design of<br />

the space<br />

c o m b i n e s<br />

Some of the historic collections in the new HCAS<br />

p r a c t i c a l i t y<br />

and aesthetics;<br />

maximizing storage but with a clean, simple look in deliberate<br />

contrast to the rich material it houses. The HCAS is provided<br />

with its own secure Reading Room; the Feinberg Room which<br />

borrows light from the large main roof light and has space for<br />

up to 4 Special Collections Readers to use simultaneously.


11<br />

THE QUEEN'S COLLEGE LIBRARY INSIGHT<br />

A new Peet Library of Egyptology<br />

A separate study room for the College’s Egyptology collection<br />

is located in front of the entry gates to the new reading room<br />

so as to be accessible to non-Queen’s members. The Peet has 4<br />

central reader spaces and a large study table. The walls are lined<br />

entirely with bookshelves to maximize space for this important<br />

collection. At the entrance, a glass screen is provided by a<br />

double-sided display case allowing Egyptian artefacts to be<br />

displayed in the round; visible to all Library visitors.<br />

A new multi-purpose space<br />

In the southwest corner a new space is provided for up to 15<br />

students for group study; small seminars and teaching for the<br />

wider College. The space has a sophisticated AV fit-out to<br />

enable it to support a variety of uses.<br />

Lower Library<br />

The Lower Library<br />

h a s b e e n<br />

sensitively returned<br />

to its original<br />

arrangement, as<br />

conceived by C. R.<br />

Cockerell in 1845,<br />

through careful<br />

e d i t i n g a n d<br />

removal of a series<br />

of later additions.<br />

The extra space in<br />

the new building<br />

Newly reconfigured Lower Library<br />

has allowed the<br />

aisles to be cleared of added shelves. Removing the<br />

overcrowded office and other late additions has returned the<br />

entrance space to its intended grandeur. East and West aisles<br />

are opened and provided with new seats and lockers and the<br />

cross aisle is open providing a view from the new Provost’s<br />

Garden to Back Quad. The Lower Library now has 22 high<br />

quality individual reader spaces and 8 new standing desks.<br />

A new entrance<br />

The Lower Library works also include a new entrance where<br />

the existing rehung oak doors have been paired with a new<br />

frameless glass sliding door. This new door provides both an<br />

environmental and<br />

security barrier for the<br />

Library, whilst also<br />

giving a spectacular view<br />

from the north end of<br />

the library to the<br />

southern end of<br />

Hawksmoor’s Front<br />

Quad.<br />

The new entrance to the library<br />

The entrance vestibule<br />

also provides a new lift<br />

linking both existing and<br />

new buildings and<br />

ensuring accessibility to<br />

t h e u n d e r g r o u n d<br />

extension.<br />

A responsible design<br />

The building employs advanced environmental design. 50m<br />

piles transfer thermal energy from deep below the building to<br />

the new air handling and heating/cooling coils in the plant<br />

room. This technology works both to pre-heat the building’s<br />

heating systems in the winter and vice-versa in summer using<br />

the known thermal stability of deep ground temperatures. The<br />

low energy strategy provides for both the new underground<br />

building and now also provides heating and cooling for both<br />

levels of the existing Library.<br />

The building further minimizes energy consumption by use of<br />

its physical location in the ground and maximizes the heat-sink<br />

qualities of its concrete structure – the space was exceptionally<br />

cool even in the June and July heatwave.<br />

The new building uses a single, efficient Menerga air handling<br />

unit which uses adiabatic technology (water) as a cooling<br />

medium and in-turn requires less energy to heat or cool. The<br />

unit similarly recycles and exchanges waste energy at a higher<br />

rate than conventional systems. Electrical energy consumption<br />

is minimized with responsive systems and LED lighting<br />

controlled by a new Building Management System.<br />

Finally, consideration of embodied energy was central to our<br />

material selection with 92% materials (stone, timber, soil and<br />

concrete) sourced within 50 miles of the site. In the case of the<br />

new garden, reused and recycled stone from the existing<br />

garden could be used again for the new terraces and paths.<br />

A new garden<br />

The underground library is topped with a new Provost’s<br />

Garden, bounded by two listed mediaeval stone walls, the<br />

existing library and the Provost’s Lodgings. The new design<br />

for the garden responds to the needs of the Provost (and their<br />

family) and the College - balancing privacy and flexibility –<br />

whilst recreating a serene and verdant garden.<br />

Aerial view of the new Provost’s garden<br />

We worked closely with Landscape Architect Jeremy Rye to<br />

devise a scheme that worked for all and could work effectively<br />

as a ‘roof garden’. The garden is a complex geometry of subtle<br />

slopes and gradients to provide the appearance and utility of a<br />

‘flat’ lawn whilst mediating between many different levels. The<br />

geometry also disguises the new roof light from the east end of


Michaelmas <strong>2017</strong> 12<br />

the garden and the new private lodgings from the west<br />

(Library) end. Most importantly, the new roof light and all<br />

interventions are invisible in the long view to the west<br />

elevation and statues of the existing Library.<br />

Queen’s with a number of opportunities to reconfigure and<br />

extend for future use.<br />

The build<br />

Construction of the new building commenced in spring 2015<br />

and ran for 89 weeks through two kind winters completing in<br />

spring <strong>2017</strong>.<br />

The main contractor, Beard, are a very experienced and skilled<br />

local company with a great deal of experience working in<br />

collegiate Oxford – and specifically at Queen’s, having<br />

completed the kitchen project in 2009. Their expertise and<br />

familiarity assisted in the two major challenges of the build:<br />

getting material to and from the site and digging a large hole<br />

that was both very close to and beneath existing historic listed<br />

structures.<br />

View of the new garden from the Provost’s Lodgings—looking toward the<br />

library<br />

The garden provides two terraces, a circuit of paths and a<br />

variety of new beds and space for a vegetable garden and new<br />

garden store. The paths and ramps make all areas of the<br />

garden accessible to wheelchair users. The below ground<br />

structure and overall garden design has been carefully<br />

configured to safeguard the existing magnificent copper beech<br />

tree which has been carefully protected throughout and we are<br />

pleased to say is prospering in its new setting.<br />

The challenge of building close to existing structures involved<br />

much careful design<br />

work, as well as<br />

buildability studies<br />

being carried out by<br />

the design team<br />

before the project got<br />

to site. Regular<br />

movement checking<br />

was completed in<br />

advance of going on<br />

site to ensure no<br />

damaging movement<br />

of the existing walls,<br />

Library or Lodgings<br />

was taking place.<br />

The forming of the<br />

piles and internal<br />

concrete box was a<br />

careful and steady<br />

process of piling, The new basement level in its early stages<br />

digging, supporting,<br />

backfilling, bracing and finally - with the lid - forming a rigid<br />

waterproof concrete box. The careful iterative process of<br />

building in-the-ground was particularly acute in forming the<br />

link between the new building and Lower Library, where a<br />

bespoke design was used to tunnel beneath the existing<br />

Library footings forming a new basement 5m below the<br />

functioning Library.<br />

Aerial view of the construction site where the garden was replanted<br />

Fitting out the building<br />

Choosing fixtures and fittings for a building is always an added<br />

pleasure for architects and we have greatly enjoyed being<br />

involved in designing the tables, insignias, manifestations, and<br />

fixed furniture together with selecting the new reading chairs,<br />

and other details.<br />

Elsewhere<br />

Benefitting the wider College, the project frees-up 4500sqft for<br />

reuse. Liberated spaces include an extensive basement and<br />

above ground spaces on Front and Back Quad providing<br />

The waterproof box was completed with the installation of 4<br />

super-sized frameless glass roof lights along the eastern edge.<br />

These enormous pieces were carefully manoeuvered into place<br />

by a number of cranes and small lifting machines in early <strong>2017</strong><br />

to finally seal the new building.<br />

The fit-out of the building was no less complex than the<br />

structural works with extensive special fittings to be concealed<br />

and accommodated. The invisibility of air-conditioning,<br />

heating and other services is the result of careful coordination<br />

between joinery and environmental design where the new<br />

shelving often straddles low-level ducts, and grilles. At the top<br />

of shelves, extract ventilation occurs together with much of


13<br />

THE QUEEN'S COLLEGE LIBRARY INSIGHT<br />

the lighting for the building.<br />

Bespoke shelving lines the walls of every space and is tailored<br />

to provide everything from shelf space, displays, signage and<br />

space for oversized parts of the collection.<br />

Architect, we worked with on the designs for the new<br />

Provost’s Garden.<br />

The new carpentry was also carefully coordinated with a large<br />

number of glazed screens, which are a major feature of the<br />

interior; dividing rooms and enclosing the new lift. Careful<br />

detailing and handling of glass ensured that large panels could<br />

be used and the overall effect of a reflective internal glass ‘face’<br />

in the entrance was able to be maintained.<br />

The finer finishing touches include acoustic ceilings; fabric<br />

wrapped panels; the installation of display cases and exquisite<br />

timber paneling in the Lower Library by Cliveden<br />

Conservation.<br />

In statistics:<br />

The project sank 299 concrete bearing and retaining piles<br />

each 30m long.<br />

We augured 10 special thermal piles each extending 50m<br />

into Oxford clay.<br />

On completion of the piled perimeter 8900 cubic metres of<br />

soil and gravel was excavated for reuse elsewhere.<br />

There are 5km of electrical, AV and data cabling, and 800<br />

linear metres of new shelving.<br />

Epilogue<br />

Having now seen the project realised, we are pleased that many<br />

key aspects of the original concept and design have worked as<br />

intended. Creating a bright day lit new library space was central<br />

to the aims of the design project, and many studies were carried<br />

out at all stages to test this. The roof light aperture, roof slope<br />

and height were all iteratively adjusted to ensure that light<br />

penetrated the new space(s) in the most effective way possible.<br />

The ultimate objective being to provide a comfortable space<br />

that belied its below-ground position. Similarly, we are pleased<br />

that the new Library is invisible from many views – an unusual<br />

objective for architects. The invisibility has been aided by the<br />

planting of the garden which has been established and was in<br />

use this summer.<br />

We are conscious that the project was disruptive for both<br />

College and its neighbours. Whilst a great deal was done to<br />

mitigate this, major projects are always noisy. Considering the<br />

scale of the project, many have remarked that Beard’s excellent<br />

management minimized disruption in a significant way.<br />

We would like to thank the design team of specialist<br />

consultants that we have employed to complete the project.<br />

Eckersley O’Callaghan, our structural and civil engineers,<br />

engineered a complex invisible ‘box’. Atelier Ten, our service<br />

engineers, who devised a sophisticated and effective low energy<br />

strategy (in addition to designing a most beautiful and compact<br />

plant room!)<br />

The full team also included a skilled Acoustician (Sandy Brown<br />

Associates); Fire Consultant (Simon Ham); Planning<br />

Consultant (Nik Lyzba); Health and Safety Consultant<br />

(Gardiner and Theobald) and Jeremy Rye who, as Landscape<br />

The ‘beautiful and compact’ plant room designed by Atelier Ten<br />

Working for Queen’s has been both professional, and a<br />

pleasure in all aspects. The College is an experienced ‘building’<br />

College and its representatives understand the complexities<br />

and nuances of construction and its processes. We would like<br />

to thank Becky Beasley and Angus Bowie for their pivotal role<br />

in the project happening and for leading the internal<br />

consultation process; particularly over the last 4 years. This<br />

project is Amanda Saville’s third new library (her best so far)<br />

and the project has been very fortunate to have her experience<br />

and expertise. Collectively, the College and client team led by<br />

David Goddard have provided experience and fostered<br />

collaboration with all parties, providing a constant presence<br />

while the project was on site; all with calmness and good<br />

humour.<br />

Finally, and particularly at this point, we recognise the privilege<br />

as architects of completing a new building for Queen’s, adding<br />

to a magnificent range of historic buildings and gardens. It is<br />

equally a privilege to add to the College’s much-loved and well<br />

used Library and to see it well prepared for the future.<br />

Stuart Cade is a founding partner of MICA Architects and a<br />

longstanding partner at RMA. Stuart has worked in Oxford for 20<br />

years and has led the practice’s 14 completed projects in Oxford including<br />

work on Oxford’s own Ashmolean Museum. Stuart is currently leading<br />

MICA’s major new commission at Jesus College, in central Oxford.<br />

Reflections on the new library<br />

project<br />

David Goddard, Project Manager<br />

The completion of the New Library marks the end of a four<br />

year programme of intensive redevelopment of our library<br />

facilities. The new underground library construction was the<br />

final phase of work which included the complete overhaul and


Michaelmas <strong>2017</strong> 14<br />

refurbishment of both the existing Upper and Lower Library<br />

spaces. The culmination of this period of work has also aptly<br />

coincided with the 675 th Anniversary of the Foundation of The<br />

Queen’s College.<br />

reader spaces were occupied, along with those in the existing<br />

Upper and Lower libraries. To me this clearly demonstrated<br />

that not only were the additional spaces necessary, but that the<br />

effort, time and energy the College invested in this project had<br />

been entirely worthwhile.<br />

From this: the construction site in early stages...<br />

The work undertaken was comprehensive, and provided the<br />

opportunity to explore, review and develop each and every<br />

aspect of this facility to ensure that the maximum potential<br />

could be achieved from such a valuable College asset. I am<br />

confident that, following completion of this extended and<br />

complex period of work, Queen’s can rightfully be proud of<br />

having one of the finest library buildings within the University.<br />

It is rare that the opportunity arises to become involved in<br />

such a prestigious project and all the more so when it involves<br />

working within, and alongside, such important Grade I listed<br />

buildings. In addition, the area of works was located in the<br />

footprint of a space that was previously occupied by a very<br />

precious garden. I consider myself fortunate that the College<br />

had the faith to entrust me with the responsibility of being The<br />

Project Client Manager. This role not only enabled me to have<br />

influence over the decision making processes, regarding design<br />

changes but also allowed me to ensure satisfactory<br />

coordination between all stakeholders and for overseeing an<br />

appropriate standard of quality control.<br />

The responsibility was particularly testing as in addition to<br />

such a complex project brief, careful thought had to be<br />

afforded to the site logistics. These included very complex and<br />

challenging access constraints and the need to minimise the<br />

detrimental impact on academic life both within Queen’s and<br />

the four neighbouring colleges.<br />

These challenges were eased considerably by the<br />

understanding, cooperation and sacrifice shown by everyone in<br />

College, and in particular the current Junior Members who<br />

gave such selfless support to the cause even though many<br />

would not get to enjoy the benefits of the completed library. I<br />

feel it only right to take this opportunity to sincerely thank<br />

everyone who played a part, no matter how small.<br />

As you are aware the New Library was completed for the<br />

beginning of Trinity Term <strong>2017</strong> and it was very rewarding to<br />

observe that within a short time of it’s opening, all the new<br />

To this: A view into the underground extension to the library<br />

In conclusion, despite the significant challenge that the library<br />

refurbishment programme and new building project have<br />

posed to the College for a number of years, it is reassuring to<br />

witness the successful completion, and we can now look<br />

forward to addressing some of the other areas in College that<br />

require investment and development.<br />

David Goddard is the Clerk of Works here at Queen’s College. He is<br />

responsible for all aspects of building maintenance. He leads a team that<br />

ensures the College is kept in working order whilst being sensitive to the<br />

nature and appearance of the Grade I and Grade II listed buildings<br />

The Queen’s College Library <strong>Insight</strong><br />

Published by The Library, The Queen’s College,<br />

Oxford, OX1 4AW<br />

Copyright The Queen’s College, Oxford, <strong>2017</strong><br />

All rights reserved<br />

ISSN 2049-8349


15<br />

THE QUEEN'S COLLEGE LIBRARY INSIGHT<br />

Liquid Legacies<br />

Beer and Brewing at<br />

The Queen’s College<br />

June<br />

to<br />

Winter<br />

<strong>2017</strong><br />

This small exhibition<br />

is located in the<br />

display cases in the<br />

Queen’s College<br />

Upper Library.<br />

Non-members of the<br />

College, please<br />

contact us in advance<br />

to arrange an<br />

appointment.<br />

01865 279130<br />

library@queens.ox.ac.uk<br />

The Queen’s College Chancellor Ale<br />

‘Some may question its flavour, but none its potency’<br />

J.M. Kaye, The Queen’s College Record, 1936

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!