17.12.2020 Views

API RP 581 - 3rd Ed.2016 - Add.2-2020 - Risk-Based Inspection Methodology

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

5-32 API RECOMMENDED PRACTICE 581

tube

The adjusted characteristic life, and adjusted POF, P ,of the bundle is calculated using

f , adj

mod

from

Equation (5.63) using Equation (5.65).

tube

⎛ t ⎞

Pf , adj

= 1−exp

⎢−⎜ ⎟

⎢ η

⎣ ⎝ mod ⎠

5.5.3.3.3 Effects of Bundle Life Extension Efforts

β

⎥⎦

η

(5.65)

Minor repairs and cleaning operations performed on bundles prior to inspection do not affect the life of the

bundle. However, there are life extension methods that are often implemented during shutdowns that return

the bundle to service in an improved condition. An adjustment is made to the inspection interval based on

Table 4.2 for life extension methods and by determining a life extension factor, LEF . The adjusted service

duration, tadj , is calculated with the LEF using Equation (5.66).

dur

dur

( 1 )

tadj = + LEF ⋅t

dur

(5.66)

Note the actual service duration, t dur

, is the time period in years between the bundle installation date and

the inspection date that the life extension method was performed, as shown in Equation (5.67).

tdur

= Inspect Date − Install Date

(5.67)

The Effective Installation Date, Bundle Installation Date , is calculated using tadj

adj

dur

, as shown in

Equation (5.68).

Bundle Installation Date = Inspect Date − tadj

(5.68)

adj

Consequence of Failure

Bundle failure is defined as a tube leak. Financial consequence of failure (COF) is determined based on the

bundle criticality which includes costs associated with lost opportunity due to production downtime,

environmental impact costs, and costs associated with maintenance and replacement of the bundle. The

consequence of an unplanned shutdown due to a bundle tube leak is determined using Equation (5.69).

tube

Ratered

C ⎛

= ⎜Unit ⋅ ⋅D ⎟⋅ Outage + Cost + ( Cost ⋅ matcost)

+ Cost

⎝ 100 ⎠

f prod sd mult env bundle maint

dur

(5.69)

Where

Dsd

is the time in days for a planned or unplanned shutdown and matcost factor is from Table 4.3.

Risk Analysis

Risk over time is calculated to determine what inspection is required to manage risk. Uncertainty exists when

relevant, credible data is lacking. More relevant data reduces the amount of uncertainty in the risk

calculation. Information from inspection is often needed to improve confidence in the damage states and

damage rates associated with bundles. Risk for bundles is a function of time is the product of the POF and

the COF in financial terms, as shown in Equation (5.70).

Risk = P ⋅ C

(5.70)

tube tube tube

f f f

Risk Matrix

A risk matrix is a valuable visual tool for identifying high risk bundles. The risk of each bundle is

characterized by the POF and COF categories, shown in Part 1, Section 4.3.2.2 and enables each bundle to

be plotted on the risk matrix as shown in Part 1, Figure 4.2 and Figure 4.3.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!