Sewerage Sewer Commission accuses mismanagement. Press charges against Jesse<br />
Sewage Plant (cont) Walker. Walker let go. Plant not complete yet. The sewer system still lacks<br />
a filter system and awaits thorough testing. 3-2-1912<br />
Walker resigns as engineer.<br />
Sewer Commission meets to decide about McBride. Charges against J. L. Walker,<br />
3-6-1912<br />
he resigned.<br />
A. J. Shaw Co., sewer contractor, takes an office in the Masonic Temple. To do<br />
3-29-1912<br />
general contracting. 3-30-1912<br />
Commission defers action on McBride - plant running well.<br />
Sewer Commission releases Hoopes - no explanation. Engineer J. K. Giesey<br />
4-2-1912<br />
replaces him. 5-11-1912<br />
Sewer builders must repair streets. 5-20-1912<br />
Sewer builders to restore dug up streets.<br />
The Council to try AMASTE to resurface State Street after sewer work on the<br />
6-1-1912<br />
street - putting streets back in shape after sewer work is expensive. 8-17-1912<br />
Sewer at last done - last trench filled in on Walnut Street. 8-20-1912<br />
The cost of laying sewer pipes $215,000. 10-2-1912<br />
Mathes - Sewer Commission Chairman 10-12-1912<br />
Sewage plant being tested - engineer Giesey testing mains and filter. 10-18-1912<br />
Settlement sediment begins - probably not complete for a year. 10-19-1912<br />
Everything working nicely. Henry Lambert in charge. 10-28-1912<br />
Engineer of Sewer completes work.<br />
Final report of the Sewer Commission, K. B. Mathes, chairman - total<br />
11-4-1912<br />
disbursement $402,198.29. 11-14-1912<br />
Dr. & Mrs. Luther sue for damage from Creek pollution in Bushville. 1-10-1913<br />
Sewer plant well overflowing - both pumps out. 1-23-1913<br />
All pumps broken - to borrow from Buffalo. 1-25-1913<br />
R. L. Fox, City Engineer. no date<br />
Sewerage Plant working again. 1-27-1913<br />
Sewer well again running over. 3-26-1913<br />
Sewer builders claim extra payment for work - will sue the Village. 10-22-1913<br />
The Village denies it still owes the sewer builders. 2-18-1914<br />
Disposal plant operation perfect for the first time. 7-2-1914<br />
Charles Street to get water. 10-29-1914<br />
Sewer builders work complete. Commissioners to resign tonight. 1-5-1915<br />
The Council agrees to settle the bill of Houston Brothers over sewer estimate. 2-23-1915<br />
Explosion in the Sewerage Pumping Station. 9-18-1915<br />
Engineer recommends a new pumping station up-creek from light and sewer plant. 10-9-1915<br />
Storm sewer job to Holohan - cost $5,600. 6-15-1916<br />
Storm sewer to drain the south section well to reduce the danger of typhoid. 7-3-1916<br />
The Council to put a pump from Buffalo into the Sewage Station. 8-1-1916<br />
Sewage well building under way by Warsaw Construction Co. 1-4-1917<br />
Parts of the Disposal Plant to be rebuilt. 8-9-1917<br />
Gas and oil leaking into the Sewerage well. 12-17-1918<br />
Engineer proposes a gravity system. 2-7-1920<br />
Sewage problem in the northeast. 12-7-1922<br />
Sewage report for the east end. 12-21-1922<br />
Oil seepage affecting sewage disposal. 8-14-1923<br />
New aeration bed needed for city sewage. 6-23-1925<br />
Conference on. 6-25-1925<br />
Sanitary sewers on election ballet November 12. 10-21-1926<br />
Sewer extension held up by Albany office. 3-18-1927<br />
Sewer lines being extended to 7 outlying streets. 4-2-1927<br />
Rocco Soccio gives up the contract to build the sewer extension line. 4-23 & 5-3-1927<br />
Britting and Stans of Buffalo to build. 5-19-1927<br />
Engineers installing lifts on the Clinton sewer line - Yeoman Bros. of Chicago. 9-13-1927<br />
City pumps twice as much sewage as water. 10-20-1927